How do we start the 4D process?

How is this BIM art created?

What is the schedulers role in BIM?

How does the BIM scheduler interface with the

rest of the project?

Objectives

There are many different views on the worth of a

schedule.

How valuable a schedule is depends greatly on

how well it is put together, operated and

maintained.

A schedule can be a beautiful thing.

Introduction

Art?

Art!

Gödel, Escher,

Bach: An Eternal

Golden Braid

It is the “And”!

AND

How do we start the 4D

process?

Part 1

BuildingInformationModeling Process Map www.yatescompanies.com

bcrosby@wgyates.com 781 Larson St. Jackson, MS 39202 O: 601-352-7396 M: 601-383-8359 www.wgyates.com www.yatescompanies.com

Field Installation

Author Shop /

Fab Models

Author Design

Model

Schematic

Design

Model

Marketing

Prefabrication

Modularizatio

n

Estimating

Scheduling

Syn

c

6D Owner Information

Phase (COBie)

3D Coordination Phase

(Clash Detection)

4D and 5D

Models

(Schedule and

Cost)

Adam Smith needs revision!!

Nash Equilibrium – from A Beautiful Mind

BuildingInformationModeling Process Map www.yatescompanies.com

bcrosby@wgyates.com 781 Larson St. Jackson, MS 39202 O: 601-352-7396 M: 601-383-8359 www.wgyates.com www.yatescompanies.com

Field Installation

Author Shop /

Fab Models

Author Design

Model

Schematic

Design

Model

Marketing

Prefabrication

Modularizatio

n

Estimating

Scheduling

Syn

c

6D Owner Information

Phase (COBie)

3D Coordination Phase

(Clash Detection)

4D and 5D

Models

(Schedule and

Cost)

Architec

ts

General

Contractor

Construction

Manager

Owners

General

Contractor

Construction

Manager

General

Contractor

Constructio

n Manager

General

Contractor

Construction

Manager

Modelers

Construction

Manager

General

Contractor

Owners

General

Contractor

Modelers

Trades

Owners

Specialty

Contractors

Specialty

Contractors

General

Contractor

Trades

Specialty

Contractors

General

Contractor

Trades

Owners

Engineers

Arch/CM/G

C/Owner

All

Architec

ts

How is this BIM art

created?

Part 2

BuildingInformationModeling Process Map www.yatescompanies.com

bcrosby@wgyates.com 781 Larson St. Jackson, MS 39202 O: 601-352-7396 M: 601-383-8359 www.wgyates.com www.yatescompanies.com

Field Installation

Author Shop /

Fab Models

Author Design

Model

Schematic

Design

Model

Marketing

Prefabrication

Modularizatio

n

Estimating

Scheduling

Syn

c

6D Owner Information

Phase (COBie)

3D Coordination Phase

(Clash Detection)

4D and 5D

Models

(Schedule and

Cost)

Schedule – Model - Field

What is the schedulers role in BIM?

How does the BIM scheduler interface with the rest of the

project?

Part 3 and 4

Schedule – Model - Field

Project Management

Daily Reports

Job Walks

Phone Calls

Schedule Updates

Pay Applications

Meetings

What does the project require?

Role and Interface

Contractors

Old Style Management

Designers

Suppliers

CM Agent

OWNER

BIM Style

InContractorsDesigners

Contracts

Incentives

CollaborationRelationships

Efficiency

Productivity

Sharing

Accountability

Information

Suppliers

CM Agent

OWNER

In

Suppliers

Contractors

TEAMWORK

Designers

INFORMATION

CM Agent

OWNER

Conclusion

The Schedule is the Keystone of Information.

Use all of the tools available to communicate and work to the

schedule.

A Beautiful Project

A collaborative schedule

well communicated is an

amazing thing.

Be An Artist.

Paul Teicholz

Labor-Productivity Declines in the Construction Industry: Causes and Remedies (Another Look)

100% Design Coordination

90% Reduced Rework

75% Prefabrication

50% Less Change Orders

20% Shorter Duration

10% Cost Savings for Owner

Zero Punch List

Where is BIM going?

Start Learning

Don’t start with the software,

Start Learning the Process.