Klang Valley MRT
Sungai Buloh-Kajang Line Underground Works Package
Presented by Mr Satpal S. Bhogal
Project Director - MMC GAMUDA KVRMT (T) SDN BHD
1
Key Stakeholders Project Owner:
Mass Rapid Transit Corporation SDN BHD (Government of Malaysia) Engineering Firms:
Mott MacDonald, AECOM Sub-Contractors:
Herrenknecth AG, Bauer, CEC International Malaysia, China Railway Engineering Equipment Group of Company, Nanyang Tunnel Engineering, OTA Sdn Bhd, Protext Sdn Bhd.
2
How ITA Criteria were addressed in the Entry Submission: The success of bringing the Project in on time and within budget is largely credited to the design and construction innovations developed for and during the project.
These include:
• Variable Density Tunnel Boring Machine
• Steel fibre Reinforced Concrete Segments and Universal Tunnel Lining Rings
• Station Depths Reduced with lifting Vertical Alignment
• Deep Soil Mixing
• Re-scheduling of TBM Drives during the Project cycle.
3
Relevance of the Project and the Tunneling Solution • Geological Challenges
• 50% of the tunneling alignment sitting in highly graded Karstic Limestone
• Classified as extreme karst (5 on a scale of 1-5)
• Intricate three-dimensional network of solution channels, steep side crevices and highly irregular rock head
• Overlain with soft soils
• High groundwater table
4
The Success Story The tunneling works were completed in April 2015 without any
major incidents of sinkhole or subsidence in the Karstic Limestone
The tunneling solution was a major factor in overcoming opposition to the selected alignment from highly influential affected stakeholders and allowing underground construction to proceed
MGKT employed 90% of all tunneling engineers locally and trained 50% of its operations crew from their own tunneling academy set up in December 2011
The VD-TBM has since won the International Tunneling award for Technical Innovation
5
6
Project site comprised 2 equal route lengths of geological areas, Karstic Limestone & Kenny Hill. For Stations, open excavation with rock blasting in Limestone to construct bottom up and D-Walls with temporary columns to support top-down construction in Kenny Hill. For Tunnels, VD machines in Limestone and EPBs in Kenny Hill.
8
Tunnelling Training Academy [TTA]
Inaugrated in Dec 2010 by Dr Tun Mahathir
Training on full size TBM components
TRX Station (Interchange Station Lines 1&2)
11
Open excavation in karstic limestone. Bottom-up construction.
Finished Station Perspective.
12
Variable Density Tunnel Boring Machine was recognised for its innovation and performance at the 2014 ITA Awards.