KYTC Bridge Preservation and Maintenance Program
David Steele, P.E.Branch Manager for Bridge
Preservation
Bridge Inventory
9,025 = Number of State Maintained Bridges
632 = Structurally Deficient (7%)
4,709 = Number of Local Maintained Bridges
District Bridge Crews
District Bridge Crews
District Bridge Crews
Bridge Preservation Conference
Central Office Staff
• Branch Manager (P.E.)• Chief Bridge Inspector• Contract Section–Repairs (3 people) Paint (1 person)• Scour and Preventive Maintenance (1 P.E.)• Load Rating Engineers (2 P.E.’s)• Ohio and Big Sandy River Bridges Manager (1 P.E)• Inventory – Pontis System Administrators (2)• Snooper Manager• Administrative Specialist
Before