HIE-ISOLDE. Layout Experimental hall Final status (?). 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012. Erwin Siesling. History: summer 2011. Maximize space on floor. Decoupe mur. Plateforme prolongee. 2 m. Cooling restrictions. All racks on platform. 2 m. - PowerPoint PPT Presentation

Citation preview

Layout Experimental hall

Final status (?)

3rd HIE ISOLDE Physics Coordination Group meeting

CERN, 3 September 2012

HIE-ISOLDE

Erwin Siesling

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 2

History: summer 2011

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

2 mDecoupe mur Plateforme prolongee

Courtesy: Stephane Maridor

Maximize space on floor

3

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

4.1m

2 m

Courtesy: Stephane Maridor

4

All racks on platform

CV says NO...

Cooling restrictions

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 5

Hall 170 ventilation systems

platform

wall wall

wall

1st extension 2nd extension

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 6

platform

wall wall

wall

1st extension 2nd extension

Hall 170 ventilation systems

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 7

Max heat dissipation

platform

wall wall

wall

1st extension 2nd extension

Max 70kW

100kW ?Max 45kW

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

Rack distribution

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

6x3 RACKS “PC” 500A

DIPOLE 45˚20 RACKS “PC”

QUAD/STEERER

2x2 RACKS “PC” 250A

DIPOLE 22.5˚

3 spare RACKS dipole

5 VAC racks

2 BI racks(+3)

4 WIC racks

Electric. Dist. racks

Rack distribution

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

Cable distribution

All EPC, BI and VAC cabling installed in stage 1 before experiments in place – cables for stage 2(b) rolled and stored on the hall floor

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

All EPC, BI and VAC cabling installed in stage 1 before experiments in place – cables for stage 2(b) rolled and stored on the hall floor

Cable distribution

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 12

Minimizing floor occupancy

2x2 RACKS “PC” 250A

DIPOLE 22.5˚

3 spare RACKS dipole

6x3 RACKS “PC” 500A (+1 cabling rack)

DIPOLE 45˚

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 13

Minimizing floor occupancy

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 14

Heat to air dissipation

6x3 RACKS “PC” 500A (+1 cabling rack)

DIPOLE 45˚20 RACKS

QUAD/STEERER

2x2 RACKS “PC” 250A

DIPOLE 22.5˚

3 spare RACKS dipole

5 VAC racks

2 BI racks(+3)

4 WIC racks

Max 4x12.5=50kW

Max 29kW

Max 12.5kW Max 2x4kW

Max 5kW

or

Platform: Max 46.5kW to air (if spare runs for a 44.5 ˚ magnet)Floor: Max 50kW to air (if bend running at max) – leaving 20kW for experiments

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 15

Alignment platform

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 16

Nicole experiment?

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 17

Acknowledgement

• EN/MEF : STEPHANE MARIDOR, ELEFTHERIOS ZOGRAFOS• GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• BE/OP : DIDIER VOULOT• EN/HDO: YACINE KADI• EN/CV : PAUL PEPINSTER, BENOIT LACARELLE• EN/EL : RENE NECCA• EN/STI : RICHARD CATHERALL, ANA-PAULA BERNARDES• TE/ABT : BRENNAN GODDARD• BE/RF : MATHEW FRASER• TE/EPC : MICHELE MARTINO

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 18

Extra slides

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

STAGE 1

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

STAGE 2a

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

STAGE 2b

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

1580

892

1344

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 26

Hie-Isolde Planning

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2011 2012 2013 2014 2015 2016

Civil

Main servicesCryo

CM 1&2 CM 3&45.5MeV/u

10MeV/u

Beam Transfer Line

CM 5&6

17 Dec 2012 - Q3 2014

sd sd sdCM1&2

Isolde & REX Ops shutdown

LS1

Cryo Mod 1 & 2 install (Isolde normal operations)

Timeline:

sd

VentilationDemi waterElectrical syst.s

Start LS1 3 dec 201217

End LS1:Start Low E physics

Commissioning (Isolde normal operations)

Commissioning during shutdown (EBIS beam)

Beam commissioning Nov. + 5 months

Cryo only ready Feb 2014

Start-up 2015HIE physics at

5.5MeV/u

Hie Isolde 3rd HIE PCG, 3 Sept 2012 Erwin Siesling 27

Commissioning planning