Lee’s Summit Road Improvements
NW Anderson Dr. to NW Lakewood Blvd
Project Manager: Kim Pemberton, City of Kansas City, MO
Project Description
This project will realign and improve Lee’s Summit Road from NW Anderson Dr. to NW Lakewood Blvd.
Design is currently underway.
The project is in the right-of-way acquisition phase
Construction funding is available in 2021
Upgrades include:
Widened & realigned roadway with new pavement
Curb and gutter
A multi-use trail and bike lanes
Retaining walls
New sidewalks
Project website:
Visit KCMO.gov and search for: “Lee’s Summit Road”
Funding Information Project funding is provided by voter-approved GO
Bond funding.
CONTACT:
Maggie Green
Public Information Officer Kansas City Public Works Office – 816-513-2612
E-mail – Maggie.Green@kcmo.org
Fact Sheet Project Number 89008194 Lee's Summit Road, NW Lakewood Blvd to Anderson Dr City of Kansas City, Missouri - Dept. of Public Works Probable Project Schedule
● October 2020 - Completion of new waterline system ● 2021 - Construction begins
○ Phase 1 - Lee's Summit Road, NW Lakewood Blvd to Space Center Dr ○ Phase 2 - Lee's Summit Road, Space Center Dr to Anderson Dr
● Fall 2022 - Construction ends Project Cost
● $9.3 million / $7.4 million for construction Project Details
● New Alignment ● New 12” Pavement ● 5’ Sidewalk, 5’ Bike Lanes, and 10’ Path ● New Concrete Driveways Approaches ● New Storm Sewer and Street Lights ● Proposed Right-of-Way
○ 4 New Retaining Walls ○ Fence Relocation to Property Line ○ Mailboxes Relocations
■ If you want to buy yourself a new mailbox to replace the existing one, do so before Oct 2020 and contact us so we can let the contractor know to install it
Traffic Details
● Total Daily Traffic Volume - 5,208 vehicles (2020), 6,011 vehicles (2040) ● Speed Limit - 40 mph, Change to 35 mph per City Standards ● Construction Traffic Patterns
○ 2 Phases, No Thru Traffic ○ Continuous Access to Space Center Dr ○ Continuous Access to Residences