Method of Lifting FT ATJ Bridge

Preview:

DESCRIPTION

method

Citation preview

jack.sunyoto 1

METHOD OF WORKLIFTING and LAUNCHING TRAVELER

ATJ – CABLE STAYED BRIDGEKONTRAKTOR UTAMA :

PT. WASKITA KARYA (Persero) Tbk.

jack.sunyoto 2

METHOD OF WORKLIFTING and LAUNCHING TRAVELER

BAGIAN DARI PEKERJAAN MODIFIKASI TRAVELER EX. PADAMARAN

SUB-SUPERVISI DAN LIFTING TRAVELER

jack.sunyoto 3

PREPARE OF LIFTING AND ERECTION FORM TRAVELER UNIVERSAL SATELITTE

jack.sunyoto 4

1Existing CHECKING and Supervision July, 10th 2015

FT terpasang / masih memerlukan penyempurnaan

Batang Kelapa

jack.sunyoto 5

2Launching Unit FT c/w COCONUTS TRUNKS --

FT masih harus maju 15 m

Batang Kelapa

Karena Roller Batang Kelapa kemungkinan – Launching unitTraveler under control ( Zig-Zag)

jack.sunyoto 6

EQUIPMENT LIST OF LIFTING AND ERECTION FORM TRAVELER UNIVERSAL SATELITTE

jack.sunyoto 7

3EQUIPMENT LIST TO BE THERE ----

FixcityRear Chair

Rear Hollow Jack 50 T

Gantry Lift

PT Bar

Front Chair Front Hollow Jack 50 T

Uni Chair

Static Roller

jack.sunyoto 8

EQUIPMENT and PARTS UNITS ----

HOLLOW JACK SYSTEM

COUPLER JOINT SYSTEM

HANGING LIFT SYSTEM

jack.sunyoto 9

4METHOD of INSTALLATION : LIST of EQUIPMENT -----

Equipment :1. Power pack system w/ hyd. jack 2 units2. Chain block caps 3 ton 6 units3. Lever block caps 3 ton 4 units4. Thread bar c/w nuts dia 36 4 sets (@21 m’)5. Launching Roller 4 units6. Casting Hanger 4 units7. Control panel w/ safety lighting 1 units

jack.sunyoto 10

KINEMATICS SCHEME OF FORM TRAVELER UNIVERSAL SATELITTE

jack.sunyoto 11

5METHOD of INSTALLATION : KINEMATICS SCHEME of TRAVELER ---

Fixing of Casting Hanger, prepare FWStressing 1st Cable Stayed, prepare Concreting,

Jack up and Setting of FW, prepare Concreting,Concreting of Beam and Cross Beam,

Prepare of Launching LH, Going Front of LH and Dismantling of CH,

Launching of Main Truss and FT,

1st

2nd Fixing of Casting Hanger, prepare FW

Stressing 1st Cable Stayed, prepare Concreting,Jack up and Setting of FW, prepare Concreting,

Concreting of Beam and Cross Beam, Prepare of Launching LH,

Going Front of LH and Dismantling of CH,

Launching of Main Truss and FT,

jack.sunyoto 12

PT BAR

Nuts –PT Bar

Washer

Hollow Jack

Chair - HJ

Sendi PT Bar

Static Roller

Universal Satelitte

jack.sunyoto 13

LIFTING AND ERECTION FORM TRAVELER UNIVERSAL SATELITTE

jack.sunyoto 14

6METHOD of INSTALLATION : LAUNCHING and LIFTING UNIT TRAVELER

------------------------

1. Install of Gentry Lift,2. Install and Fixing anchorage of Gentry Lift,3. Install of Rear Hollow Jack Unit,

5. Install of Front Chair4. Install of Universal Hollow Jack Universal

jack.sunyoto 15

7METHOD of INSTALLATION : 1st LAUNCHING UNIT TRAVELER ------

jack.sunyoto 16

8METHOD of INSTALLATION : 2nd LAUNCHING UNIT TRAVELER ----

jack.sunyoto 17

9METHOD of INSTALLATION : 3rd LAUNCHING UNIT TRAVELER ----

jack.sunyoto 18

10METHOD of INSTALLATION : end LAUNCHING UNIT TRAVELER --

jack.sunyoto 19

11METHOD of INSTALLATION : PREPARE and INSTALL PT BAR, RELEASE of TEMPORARY STRESS BAR----

jack.sunyoto 20

12METHOD of INSTALLATION : LIFTING TRAVELER ------

13METHOD of INSTALLATION : VIEW OF LIFTING TRAVELER ------

jack.sunyoto 22

14METHOD of INSTALLATION : FIXING CASHTING HANGER & ROLLING HANGER DISMANTLING of PT. BAR, HYDRAULIC JACK,

GANTRY etc -

jack.sunyoto 23

15METHOD of INSTALLATION : INSTALL TEMPORARY PRESTRESS CABLE etc -----

jack.sunyoto 24

16METHOD of INSTALLATION : JACKING UP FORMWORK – PREPARE of CONCRETING -----

jack.sunyoto 25

17METHOD of INSTALLATION : CONCRETING of BEAM,

INSTALL ANCHORAGE PRESTRESS and STRESSING -----

jack.sunyoto 26

18METHOD of INSTALLATION : JACKING DOWN of FORM WORK,-PREPARE of 1ST LAUNC TRAVELER and ETC -----

jack.sunyoto 27

19METHOD of INSTALLATION : GOING DOWN of CASTING HANGER,-

PREPARE of 1ST LAUNCH TRAVELER and ETC -----

jack.sunyoto 28

20METHOD of INSTALLATION : DISMANTILING of PT BAR LAUNBHING HANGER, MOVING OF ROLL -----

jack.sunyoto 29

21METHOD of INSTALLATION : FIXING and ANCHORING of ROLL --

jack.sunyoto 30

22METHOD of INSTALLATION : DISMANTLING of FORM PT BAR,-

FIXING and ANCHORING of LAUNCHING HANGER---

jack.sunyoto 31

23METHOD of INSTALLATION : STRESSING CABLE, JACK UP FORM WORK and CONCRETING 2nd -----

jack.sunyoto 32

24METHOD of INSTALLATION : CONCRETING DECK and STRESSING CABLE STAYED ---

jack.sunyoto 33

END STRUCTURE ATJ - CABLE STAYED BRIDGEBAGIAN DARI PEKERJAAN MODIFIKASI TRAVELER

EX. PADAMARANSUB-SUPERVISI DAN LIFTING TRAVELER

jack.sunyoto 34

TERIMA KASIH