ID Task

Mode

Task Name Duration Start Finish

0 Children's Gourmet

Cookbook

104 days Mon

09/07/12

Thu

29/11/12

1 Acquisition 25 days Mon 09/07/12Fri 10/08/12

2 Manuscript received 0 days Mon

09/07/12

Mon

09/07/12

3 Content edit 25 days Mon 09/07/12Fri 10/08/12

4 Handoff to Editorial 0 days Fri 10/08/12 Fri 10/08/12

5 Editorial 30 days Mon 13/08/12Fri 21/09/12

6 Organize manuscript

for copyedit

5 days Mon

13/08/12

Fri 17/08/12

7 Copyedit 20 days Mon 20/08/12Fri 14/09/12

8 Copyedit incorp 5 days Mon 17/09/12Fri 21/09/12

9 Handoff to

Production

0 days Fri 21/09/12 Fri 21/09/12

10 Design and Production 20 days Mon

13/08/12

Fri 07/09/12

11 Cover design 5 days Mon 13/08/12Fri 17/08/12

12 Set pages 10 days Mon 20/08/12Fri 31/08/12

13 Interior illustration

design

15 days Mon

20/08/12

Fri 07/09/12

14 Pages review 20 days Mon 24/09/12Fri 19/10/12

15 Proofread and index 10 days Mon

24/09/12

Fri 05/10/12

16 Incorporate 1st

Pages review

5 days Mon

08/10/12

Fri 12/10/12

17 Send proofed pages

to Production

0 days Fri 12/10/12 Fri 12/10/12

18 Enter page

corrections and

index

5 days Mon

15/10/12

Fri 19/10/12

19 Color prep and printing 29 days Mon

22/10/12

Thu 29/11/12

20 Send to color house 1 day Mon

22/10/12

Mon

22/10/12

21 Generate proofs 5 days Tue 23/10/12 Mon

29/10/12

22 Print and ship 20 days Fri 02/11/12 Thu 29/11/12

09/07

Carole Poland

10/08

Robin Wood

Copyeditors

Robin Wood

21/09

William Flash

Robin Wood;Katie Jordan

William Flash

John Evans;Katie Jordan

Carole Poland

12/10

Katie Jordan;Robin Wood

Carole Poland

Color Setting Services

Printing Service

F S S M T W T F S S M T W T F S S M T W T F S

17 Jun '12 08 Jul '12 29 Jul '12 19 Aug '12 09 Sep '12 30 Sep '12 21 Oct '12 11 Nov '12 02 Dec '12 23 Dec '12

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress