MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
One phase rural distribution installation with direct connection to
HV trunk line
P.A. MONFILS, Jean-Louis LILIEN, A. OMBOUA
2MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
• Scope of the project
• Local conditions
• Makola application
• Load
• Reliability aspects
SUMMARY
3MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Scope of the project
The problem The solution
4MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Typical low load user (Makola)
5MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Refrigerators 3 kVA
Human health center 3
TV and video 2
Private lighting 24
Public lighting 7
Water pumping 3
TOTAL 42 kVA
• One 500 people village:Estimated load (UNESCO)
Typical low load user (Makola)
6MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Local conditions
7MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Local conditions
• 846 km from the main power supply• Very low short-circuit level: 360 A• Very low load:
– Frequent over-voltages– Important power availability
(50 kVA = 3.10-4 SIL)
• Very high keraunic level (lightning activity)
8MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Local conditions
• High soil resistivity: > 3000 .m– HV earth resistance: 35– Risks for the inhabitants
• in case of line-to-earth fault• in case of lightning on the HV line
– Needs deep analysis of earthing system
9MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
F ig 5 -5 : C o nfig ura tion du c ircu it A : terre du p ylône B : terre du poste H T C : terre du réseau B T
R T 3
A B C
• Schematic diagram
Makola application
10MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
• SF6 VT technology: high reliability
• Limited maintenance• Limited weight: easy to
transport/handle• Limited cost (no switch
bay)• Direct from 245 kV to
230 V (50 kVA)
Makola application
11MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Makola application
12MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Makola application
13MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Makola application
14MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Load recording
15MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Load recording
16MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
Reliability aspects
• Improved technology (SF6 VT) with very limited maintenance
• Immediate protection by ZnO surge arrester
• One year experiment: the reliability of the equipment is much higher than the HV system (min 5 power outages per month)
• Possible improvement by use of HV fuses
17MONFILS Pierre-André (BE)
Barcelona 12-15 May 2003
• Improvement of the quality of life of rural populations (< 3% of peoples access electrical power in Congo)
• Electrical energy gives access to drinking water, food preservation, lighting.
• Electrical energy may help starting development of local activities
• Our solution is cost effective, easy to handle and reliable
Conclusions