View
236
Download
0
Category
Preview:
Citation preview
8/2/2019 NASA 2008-1096
1/21
United States Government Accountability Office
GAO Report to Congressional Committees
NASA
Agency FacesChallenges DefiningScope and Costs ofSpace ShuttleTransition andRetirement
September 2008
GAO-08-1096
8/2/2019 NASA 2008-1096
2/21
What GAO Found
United States Government Accountability Of
Why GAO Did This Study
HighlightsAccountability Integrity Reliability
September 2008
NASA
Agency Faces Challenges DefiningScope and Costsof Space Shuttle Transition and Retirement
Highlights of GAO-08-1096, a report tocongressional committees
The Space Shuttle Program (SSP)is scheduled to retire in 2010, andthe transition and retirement of itsfacilities and assets will be animmense undertaking involvingapproximately 654 facilities worthan estimated $5.7 billion andequipment with an estimated valueof more than $12 billion. NASAplans to retire the SSP in 2010 tomake resources available for theConstellation program, which isproducing the next generation ofspace vehicles by 2015. Many of theSSPs resources are expected totransition to Constellation whileothers will be dispositioned orpreserved for their historic value.
The Consolidated AppropriationsAct, 2008 directed GAO to assessNASAs plans and progress intransitioning and retiring the SSPsfacilities and equipment. Morespecifically, GAO examined 1) thechallenges NASA faces in definingthe scope and costs of transitionand retirement activities, and 2)whether the cost of these efforts istransparent in NASAs budgetrequests. To address theseobjectives, GAO analyzed SSPplans, budget guidance, and otherdocuments, and interviewedrelevant government officials andcontractors.
What GAO Recommends
GAO recommends that NASAclearly identify all direct andindirect SSP transition andretirement costs, including anypotential exchange sale proceeds inits 2010 and future budget requests.NASA concurred with ourrecommendation.
The National Aeronautics and Space Administration (NASA) faces disparatechallenges defining the scope and cost of SSP transition and retirementactivities. For example, because the Constellation program is still finalizing requirements, the agency does not yet know what SSP property it needs toretain or the full cost of the transition effort. In addition, NASA faces otherchallenges that hamper its efforts to manage the transition and develop firmestimates of SSP transition and retirement scope and costs. For example,NASA has not developed final plans and/or cost estimates for makingartifacts including the orbiters Atlantis, Discovery, and Endeavoursafe f
public display.
The total cost of SSP transition and retirement is not transparent in NASAscurrent budget request and is not expected to be reflected in its fiscal year2010 budget request. This is due in part to delays in estimating costs, but alsto where costs are being reflected. For example, although SSPs directtransition and retirement costs are identified in the SSP budget line, indirectcosts related to environmental clean-up and restoration, maintenance ofrequired real property facilities during the gap in human spaceflight, anddemolition of excess facilities are not. In addition, NASA plans to offset somtransition costs by utilizing an exchange/sale authority that allows executiagencies to exchange or sell non-excess, non-surplus personal property andapply the proceeds toward acquiring similar replacement property.
The Space Shuttle Program Is Retiring in 2010 and NASA Is Transitioning to ConstellationProgram Spaceflight Vehicles in 2015
Source: NASA.
To view the full product, including the scopeand methodology, click on GAO-08-1096.For more information, contact CristinaChaplain at (202) 512-4841 or
chaplainc@gao.gov.
http://www.gao.gov/cgi-bin/getrpt?GAO-08-1096http://www.gao.gov/cgi-bin/getrpt?GAO-08-1096http://www.gao.gov/cgi-bin/getrpt?GAO-08-1096http://www.gao.gov/cgi-bin/getrpt?GAO-08-10968/2/2019 NASA 2008-1096
3/21
Contents
Letter 1
Results in Brief 2Background 3NASA Faces Challenges Defining SSP Transition and Retirement
Scope and Costs 5SSP Transition and Retirement Costs Are Not Transparent in
NASAs Budget 8Conclusions 12Recommendation for Executive Action 12Agency Comments and Our Evaluation 13
Appendix I Objectives, Scope, and Methodology 14
Appendix II Comments from the National Aeronautics and Space
Administration 15
Appendix III GAO Contact and Staff Acknowledgments 17
Tables
Table 1: Other SSP Transition and Retirement Challenges 7Table 2: Transition and Retirement Costs in the SSP Budget Line 9
This is a work of the U.S. government and is not subject to copyright protection in theUnited States. It may be reproduced and distributed in its entirety without furtherpermission from GAO. However, because this work may contain copyrighted images orother material, permission from the copyright holder may be necessary if you wish toreproduce this material separately.
Page i GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
4/21
United States Government Accountability OfficeWashington, DC 20548
September 30, 2008
The Honorable Barbara A. MikulskiChairmanThe Honorable Richard C. ShelbyRanking MemberSubcommittee on Commerce, Justice, Science,
and Related AgenciesCommittee on Appropriations
United States Senate
The Honorable Alan B. MollohanChairmanThe Honorable Rodney P. FrelinghuysenRanking MemberSubcommittee on Commerce, Justice, Science,
and Related AgenciesCommittee on AppropriationsHouse of Representatives
The Honorable Mark UdallChairmanSubcommittee on Space and AeronauticsCommittee on Science and TechnologyHouse of Representatives
After providing the United States unrivaled access to space for decades,the space shuttle is slated to make its last flight in 2010. The NationalAeronautics and Space Administration (NASA) plans to retire the SpaceShuttle Program (SSP) to make resources1 available for the Constellationprogram, which is expected to achieve initial operational capability in2015. The transition and retirement of the SSPs facilities and assets
represent an immense undertaking. The SSP occupies approximately 654real property facilities and holds about 1.2 million line items of personal
1In recent years, NASA has spent about $3.5 billion a year on the SSP.
Page 1 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
5/21
property.2 NASA estimates the total replacement value of all SSP facilitiesis approximately $5.7 billion, which accounts for nearly one-fourth of thevalue of the agencys total facility inventory. The total SSP personalproperty acquisition value is estimated by NASA at about $12 billion, andthere are numerous locations where government personal property isused. The SSP transition and phase-out effort will be complex andchallenging, especially when coupled with simultaneously finalizing thedesigns for the Ares I crew launch vehicle and Orion crew explorationvehicle and conducting potentially the most complicated sequence ofshuttle flights ever attemptedcompleting the International Space Stationand conducting a fifth servicing mission to the Hubble Space Telescope all
by the end of 2010.
In light of the magnitude of this undertaking, in a joint explanatorystatement accompanying the Consolidated Appropriations Act, 2008 (Pub.L. No. 110-161), you asked us to assess NASAs plans and progress intransitioning and retiring the SSPs assets and facilities. More specifically,GAO examined 1) the challenges NASA faces in defining the scope andcosts of transition and retirement activities, and 2) whether the cost ofthese efforts is transparent in NASAs current and upcoming budgetrequests. To address these objectives, we obtained and analyzed SSPtransition and retirement plans and schedules, budget formulationguidance, and transition property assessments. We also interviewedresponsible and cognizant government and contractor officials at relevantNASA centers and NASA headquarters. For our full scope andmethodology, see appendix I. We conducted this performance audit fromFebruary 2008 to August 2008 in accordance with generally acceptedgovernment auditing standards. Those standards require that we plan andperform the audit to obtain sufficient, appropriate evidence to provide areasonable basis for our findings and conclusions based on our auditobjectives. We believe that the evidence obtained provides a reasonablebasis for our findings and conclusions based on our audit objectives.
NASA faces disparate challenges in defining the scope and cost of SSPtransition and retirement activities. Because the Constellation program isstill finalizing its requirements, the agency does not yet know the full
Results in Brief
2NASA defines and groups property into two overarching classifications, real property and
personal property. Real property includes land, buildings, and other structures that cannotbe readily moved without changing their essential character. Personal property is propertythat can be transported elsewhere with relative ease.
Page 2 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
6/21
extent of SSP property it needs to retain or what the full cost of thetransition effort will be. In addition, NASA faces other challenges thatfurther hamper the agencys efforts to manage transition activities anddevelop firm estimates of SSP transition and retirement scope and cost.For example, NASA has yet to develop final plans and/or cost estimates forsafing3 artifacts, including the space shuttle orbiters Atlantis, Discovery,and Endeavour.
The total cost of SSP transition and retirement is not transparent inNASAs current budget request and is not expected to be fully reflected assuch in NASAs fiscal year 2010 budget request, when the agency plans to
include its first official estimate of the scope and cost. Although SSPsdirect transition and retirement costs are included in the SSP budget line,the Cross-Agency Support portion of NASAs budget request includesfunding for significant SSP transition and retirement activities the agencyconsiders indirect costs, including environmental compliance andremediation and demolition of excess facilities. These funds, however, arenot identified as SSP transition and retirement costs, nor is it easy todiscern that they could be in examining this budget line. In addition, NASAplans to offset some transition costs by utilizing an exchange/saleauthority that allows executive agencies to exchange or sell non-excess,non-surplus personal property and apply the proceeds toward acquiringsimilar replacement property.
To provide congressional decision makers with a more transparentassessment of funding needs for the SSPs property transition andretirement activities, we are recommending that NASA include morecomprehensive estimates of transition and retirement costs in its futurebudget requests to include identification of all direct and indirect costsand potential exchange/sale proceeds.
In a major space policy address on January 14, 2004, President George W.Bush announced his Vision for U.S. Space Exploration (Vision) and
directed NASA to retire the SSP after completing construction of theInternational Space Station in 2010 and focus its future human spaceexploration activities on a return to the Moon as a prelude to future humanmissions to Mars and beyond. As part of the Vision, NASA is developing
Background
3Safing entails removing hazardous material so the item can be safely stored and/or
displayed.
Page 3 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
7/21
new vehicles under the Constellation program, with an initial operationalcapability currently scheduled for 2015. In order to acceleratedevelopment and minimize development costs, NASA elected to pursueshuttle-derived options and the use of heritage systems for the newsystems. The agency also found that shuttle-derived options are moreaffordable, safe, and reliable and provide the use, in some instances, ofexisting personnel, infrastructure, manufacturing and processing facilities,transportation elements, and heritage system hardware.
NASA will transfer whatever real (land, buildings, and facilities) andpersonal (e.g., system hardware, tools, plant equipment) property is
practical given program requirements to Constellation and other programsto offset the need for new acquisitions. Transferring property providesNASA with distinct financial benefits. First, the receiving program avoidsthe cost of acquiring the needed property. Second, the SSP avoids thecosts associated with disposing of the property. The SSP and itscontractors are currently conducting transition property assessments(TPA) of property belonging to the SSP in two phases. In Phase 1 theagency is identifying existing SSP personal property and determiningproperty category, item status, availability date, and whether the propertyshould be transferred or declared excess. This process is ongoing andcontinues to identify SSP property. For example, as of May 2007 NASA hadidentified about 1 million line items of SSP personal property. By May 2008this number had increased to about 1.2 million line items. During Phase 2of the TPA process, the agency is developing detailed plans for disposingof excess SSP personal property including identifying hazardous materials,cataloging recoverable precious metals, providing historical artifactjustification, and identifying final destinations. Based on discussionsbetween the Space Shuttle and Constellation programs, it is estimated thatabout 40 to 47 percent of SSP personal property will be transferred toConstellation and other NASA programs and the remaining property willbe declared excess.
NASA has yet to include an official estimate of the total cost of the SSP
transition and retirement in any of its budget requests. Although NASA hasdeveloped a series of cost estimates for itranging from the $4.4 billionreported by the NASA Inspector General in January 2007,4 to theapproximately $1.8 billion estimate prepared by the agency to support its
4NASA Inspector General,NASAs Plan for Space Shuttle Transition Could Be Improved
by Following Project Management Guidelines, IG-07-005 (Washington, D.C.: Jan. 29, 2007).
Page 4 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
8/21
fiscal year 2009 budget requestand has been funding SSP transition andretirement activities out of its approved Shuttle budget, the agency has notincluded any of the estimates for fiscal years 2011 and beyond in its budgetrequests to the Congress. NASA transition managers maintain that NASAmade a strategic decision not to release an estimate of transition andretirement costs for fiscal years 2011 and later until the scope of the effortand the associated costs and schedule were better defined. According toNASA transition managers, the agency has now accomplished this betterdefinition and plans to include an estimate substantially lower than theearlier $1.8 billion estimate for the total cost of SSP transition andretirement in its fiscal year 2010 budget request.
We have previously reported on NASAs management of the billions ofdollars of government equipment under its control.5 We found weaknessesin the design and operation of NASAs systems, processes, and policiescovering the control and accountability of equipment. We maderecommendations that focused on ways to strengthen NASAs internalcontrol environment and improve its property management.
NASA faces disparate challenges defining the scope and costs of SSPtransition and retirement activities. The Constellation program is finalizingthe requirements that will inform the SSP of what real and personalproperty needs to be retained and what should be declared excess.Furthermore, the property assessments needed to inform NASAs budgetplanning process may not be completed in time to support the costestimates the agency plans to include in its fiscal year 2010 budget request.In addition, NASA faces other challenges that further hamper the agencysefforts to develop firm estimates of SSP transition and retirement scopeand cost, including finalizing plans for safing artifacts.
The Constellation program is still finalizing its requirements and definingneeded capabilities; therefore, the agency does not know, in all instances,
what SSP property needs to be retained and what property can bedeclared excess. According to SSP and Constellation transition managers,there is a symbiotic push and pull relationship between the SSP and theConstellation program. Ideally, in this relationship the SSP would push the
NASA Faces
Challenges DefiningSSP Transition andRetirement Scope andCosts
Lack of FinalizedConstellation Program
Requirements Contributesto SSP Transition andRetirement Uncertainties
5GAO,Lack of Accountability and Weak Internal Controls Leave NASA Equipment
Vulnerable to Loss, Theft, and Misuse, GAO-07-432 (Washington, D.C.: June 25, 2007).
Page 5 GAO-08-1096 NASA's Transition Challenges
http://www.gao.gov/cgi-bin/getrpt?GAO-07-432http://www.gao.gov/cgi-bin/getrpt?GAO-07-4328/2/2019 NASA 2008-1096
9/21
property that it no longer needs for the safe operation of the space shuttleto the Constellation program in order to avoid property maintenanceand/or disposal costs. Likewise, in order to avoid acquisition costs, theConstellation program would pull the SSP property that it has designatedas needed. Thus far, however, this relationship has not worked as well asthe agency has desired. Essentially, the Constellation program has notfinalized its requirements for personal and real property from the SSPbecause it is still in the process of defining its own programmaticrequirements. For example, at the time of our review, the Constellationprogram had yet to hold its Preliminary Design Review during which it willfinalize its preliminary design and operations concepts, two key steps in
determining the Constellation programs hardware and processing facilityneeds. Further, according to the Exploration Systems Mission Directorate(ESMD) Transition Manager, the Constellation program is just nowrealizing the importance of pulling SSP assets to avoid costs, as any andall of the SSP transition and retirement costs post-2010 will be borne byNASA at the expense of the follow-on program(s) or Center Managementand Operations budgets.
NASA will not complete the last phase of the TPA process until after theagencys budget request for fiscal year 2010 is submitted and may notcomplete all TPA activity until the end of fiscal year 2009. NASA plans tocomplete Phase 1 of the TPA process by the end of September 2008.However, delays in finalizing system designs within the Constellationprogram are hampering the efforts of the Solid Rocket Booster element ofthe SSP to complete Phase 1 on time. In effect, Phase 2 of the TPA processwill develop the type of detailed information needed to support accurateSSP transition and retirement cost estimates. The TPA Phase 2 process,however, is not scheduled for completion until January 2009well afterthe fiscal year 2010 budget request is formulated. Furthermore, the SpaceShuttle Main Engine does not anticipate completing TPA Phase 2 untilAugust 2009, well after the budget request is submitted to Congress.
NASA faces other challenges that further hamper the agencys efforts todefine the scope and cost of SSP transition and retirement. In addition tothe issues discussed above, NASA has not yet developed final plans and/orcost estimates for safing artifacts, including the orbiters Atlantis,Discovery, and Endeavour. Moreover, the SSP lacks a centralizedinformation system to track and control all SSP property. A centralizedsystem would be particularly useful as transition and retirement activities
NASA Will Not Completethe TPA Process Until
After the Agencys BudgetRequest for Fiscal Year2010 Is Submitted
Other Challenges FurtherHamper NASAs Efforts
Page 6 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
10/21
are expected to rapidly increase in 2010. These and other challenges aresummarized in table 1 below.
Table 1: Other SSP Transition and Retirement Challenges
Funding uncertainties NASAs transition plan indicates that the SSP transition and retirement scope and schedule for eachyear are also constrained by the amount of funding the SSP Program Manager is able to allocatefrom the SSP annual operating budget for transition and retirement activities. Changes to the SSPflight manifest have direct impacts on the amount of funding available for SSP transition andretirement activities. Therefore, a firm transition and retirement completion date cannot bedetermined.
Safing artifacts SSP transition and retirement costs associated with safing artifacts for public museum display maybe more difficult and expensive than originally anticipated. Safing involves removing hazardousmaterial from SSP hardware so that it can be safely handled and displayed. Another challenge withsafing SSP hardware is removing hazardous items from the orbiters, including self-igniting fuels.According to NASA officials, every major aerospace museum in the country, including those at NASAcenters, wants one of the three operational orbiters, but the museums may not have the resources orexpertise for the necessary safing. As an example, according to NASA officials, the National Museumof the United States Air Force at Wright-Patterson Air Force Base expressed interest in obtaining anorbiter to display as part of its collection. The museum entered into discussions with NASA whereinthe museum considered offering to bear the costs of safing for the privilege of displaying an orbiterpermanently at its facility. However, the Museum subsequently withdrew from the discussions,acknowledging that it lacked the requisite technical knowledge to accomplish the tasks.
Decentralized propertymanagement systems
The SSP does not have a centralized database that identifies, tracks, and/or controls all SSPproperty. Instead, SSPs property management databases are decentralized and spread across the
agency and its contractors. The SSP relies on NASAs property management offices to track andmanage government real property and government-held personal property. NASAs existing propertymanagement systems for government-held personal property, however, do not track SSP personalproperty by program. The SSP relies on its prime contractors to track and control contractor-heldSSP personal property. These contractors, however, use a variety of different software and databasesystems for this purpose. SSP transition managers indicated that there were literally tens ofsystems in use at different locations. The key tasks of SSP transition and retirement includeidentifying and categorizing SSP personal property through the TPA process. The disparate nature ofthe SSPs property management systems precludes the efficient execution of this task.
Bow wave of dispositionactivity
NASAs SSP transition and retirement effort is facing a bow wave of activity that will occur uponretirement of the program in 2010. In order for NASA to maintain the shuttles flight capability, astockpile of spare, replacement, and contingency parts must be available for the SSP. This meansdisposition of the majority of the shuttles personal property must wait until the program is retired.NASA plans to declare excess over 700,000 lines of SSP property beginning in fiscal year 2009through at least fiscal year 2016. About 67 percent, or about 472,000 lines, of this disposition,
however, is scheduled for fiscal years 2011 and 2012. By comparison, NASA dispositioned 62,994pieces of property in 2007. The sudden and substantial increase, or bow wave, of disposition activityfollowing the shuttles retirement has the potential to overwhelm NASAs capacity to dispose of SSPproperty and lead to schedule delays and cost overruns.
Page 7 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
11/21
Export control NASA maintains that some SSP personal property is subject to varying levels of export control by theU.S. State Departments International Traffic in Arms Regulations and/or the U.S. CommerceDepartments Export Administration Regulation. According to NASA officials, satisfying export controlregulations for excess SSP personal property should be accomplished through appropriatedocumentation such as end use certificates. Additional processing, up to and includingdemilitarization, may be required for items obtained from the Department of Defense or appearing onthe U.S. Munitions List. NASA is still in the process of identifying potential export-controlled SSPhardware. NASA will be unable to determine the level of export control needed in each instance oraccurately estimate the cost of enforcing export controls until this process is completed.
Historic preservation The National Historic Preservation Act directs federal agencies to establish a program that identifiesand evaluates properties to be nominated to the National Register of Historic Places, takeresponsibility for the preservation of historic properties they own or control, and take into account the
effect of any undertaking on a site, building, structure, or object that is included in or eligible forinclusion in the National Register of Historic Places. NASA maintains that the SSP has national, stateor local importance to the history of human spaceflight and that it has a responsibility to ensurehistorically significant property is properly documented and considered during SSP transition andretirement. NASA completed an agency-wide survey of SSP-related historic properties in 2007.
Source: NASA.
All of these challenges further hamper NASAs efforts to develop firmestimates of SSP transition and retirement scope and cost. Lastly, at thetime NASA will be experiencing an increase in transition activity, it willsimultaneously be finalizing the designs for the Ares I and Orion vehiclesand conducting potentially the most complicated sequence of shuttleflights ever attemptedcompleting the International Space Station andconducting a fifth servicing mission to the Hubble Space Telescope all bythe end of 2010. These activities will likely create additional challenges forthe transition efforts, as they may require more attention than anticipatedfrom the workforce as well as more resources should unexpectedproblems occur.
SSP transition and retirement costs are not transparent in NASAs currentbudget request and are not expected to be fully reflected in its 2010request. This is partly due to challenges and delays in finalizing costestimates as described above as well as where costs are being reflected in
the budget. Specifically, in laying out its plans for SSP transition andretirement, NASA elected to capture transition and retirement costs withinits existing budget structure rather than display them separately.Consequently, the costs of the SSP transition and retirement are dispersedthroughout NASAs budget request. SSPs direct transition and retirementcosts are included in the SSP budget line. The Cross-Agency Supportportion of NASAs budget, however, includes funding for significant SSPtransition and retirement activities that NASA considers indirect costs,including environmental compliance and remediation and demolition of
SSP Transition andRetirement Costs AreNot Transparent inNASAs Budget
Page 8 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
12/21
excess facilities. These funds, however, are not identified as SSP transitionand retirement costs and it is not easy to discern that they are transitionrelated. Furthermore, NASA plans to offset some transition costs byutilizing an exchange/sale authority that allows federal agencies toexchange or sell non-excess, non-surplus personal property and apply theproceeds toward acquiring similar replacement property.
The SSP budget request for fiscal year 2009 identifies a funding need ofabout $370 million for transition and retirement through fiscal year 2010 topay for activities within each of the SSPs three major projectsflight and
ground operations, flight hardware, and program integration (see table 2).NASA will use these funds to cover the costs of the prime contractor, SSPpersonnel, and support contractors working on transition and retirementactivities. These activities, however, do not represent the full scope of SSPtransition and retirement.
Table 2: Transition and Retirement Costs in the SSP Budget Line
Dollars in millions
Fiscal year 2007 2008 2009 2010 Total
Flight/ground operations 4.2 1.6 2.0 2.4 10.2
Flight hardware 16.7 60.1 85.8 189.4 352Program integration 2.7 1.4 1.5 1.7 7.3
Totals 23.6 63.1 89.3 193.5 369.5
Source: NASAs Fiscal Year 2009 budget request.
The Cross-Agency Support appropriation account6 within NASAs budgetincludes or will include funding for significant SSP transition andretirement activities. This appropriation accountwhich is not alignedwith a specific program or projectincludes what are essentially NASAsadministrative or overhead costs for all of its centers and activities. Cross-
Agency Support will include SSP transition and retirement funding within
SSP Budget Line
Cross-Agency SupportAppropriation Account
6The Consolidated Appropriations Act, 2008, required NASA to modify and test its
administrative financial management system in order for the system to be able to budget,account, control and report on appropriations it receives in Fiscal Year 2009 and thereafterunder a new appropriation account structure. The new structure will comprise sevenappropriation accounts within NASAs budget: Science, Aeronautics, Exploration, SpaceOperations, Education, Cross-Agency Support, and Inspector General.
Page 9 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
13/21
its Environmental Compliance and Restoration, Center Management andOperation, and Strategic Institutional Investments budget lines. Thesefunds, however, are not identified as SSP transition and retirement costs.As such, it is difficult to discern the full costs of the transition andretirement effort.
Funding for SSP-related environmental clean-up is included under NASAsEnvironmental Compliance and Restoration program.7 NASA currentlyestimates that the SSP has contributed to environmental contamination at94 of 163 sites and that the agencys total environmental clean-up liabilityis about $1 billion over several decades. Agency officials maintain that
they are unable to separate the cost of SSP environmental clean-up fromthe total estimate of the agencys environmental liability because, in mostinstances, NASA is unable to differentiate between clean-up associatedwith the SSP and clean-up associated with legacy programs such asApollo. Agency officials indicate that historically NASA has spent about$51 million annually on environmental compliance.8
Environmental Compliance andRestoration
The CM&O budget request is part of the Cross-Agency Supportappropriation account that funds the maintenance of facilities. Funding forthe property disposal offices at the centers that will physically dispose ofexcess SSP personal property and funding to maintain real propertyfacilities is included in the CM&O line. The SSP is supposed to providefunding to these offices for any level of SSP property disposal above theirnormal level of activity, e.g., 62,994 pieces of property in fiscal year 2007.The sheer volume of SSP disposal activity, hundreds of thousands of lineitems of personal property, however, will likely consume the near fullattention of these offices during the time frame of the SSP transition andretirement. Consequently, the baseline CM&O funding will be appliedprimarily to SSP transition and retirement activities. In terms of facilitiesmaintenance, centers and programs maintain a tenant/landlord-likerelationship wherein programs such as the SSP and Constellation in effectpay the centers for the use of facilities, except where specific facilities are
Center Management andOperation (CM&O)
7At NASA, the Environmental Compliance and Restoration program provides for
personnel, services, and activities necessary to complete the clean-up of hazardousmaterials and wastes that have been released to the surface or groundwater at NASAinstallations, NASA-owned industrial plants supporting NASA activities, and other currentor former NASA sites where NASA operations have contributed to environmental problemsand where the agency is obligated to contribute to clean-up costs.
8NASAs annual funding for Environmental Compliance and Restoration increased in
recent years to fund clean-up of the Plum Brook Nuclear Reactor site.
Page 10 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
14/21
entirely program funded. Any facility maintenance costs beyond thosecovered by the lease-type arrangements between the centers and theprograms are offset by the CM&O budget.
NASA plans to eventually demolish excess SSP facilities. According toagency officials, NASA plans to fund the demolition of excess realproperty within the Strategic Institutional Investments line within theCross-Agency Support appropriation account at a level of about $15million annually. The officials noted that because NASA has alreadyscheduled demolition activities through 2015, NASA would probably notrequest funds to demolish excess SSP facilities until after fiscal year 2015.
However, facility demolition post retirement of the Space Shuttle willoccur when needed.
Strategic InstitutionalInvestments
Exchange/Sale Authority NASA plans to offset some transition costs by utilizing an exchange/saleauthority that enables federal agencies to exchange or sell non-excess,non-surplus personal property and apply the proceeds toward acquiringsimilar replacement property. This authority may also enable agencies toreduce certain costs, such as storage and administrative costs associatedwith holding the property and processing it through the normal disposalprocess. NASA intends to use proceeds from the exchange/sale of SSPpersonal property to offset the cost of acquiring replacement Constellationhardware.9 According to NASA,it will use the General ServicesAdministration (GSA) to conduct Federal Asset Sales of all personalproperty located at or near NASA Centers and the Defense ContractManagement Agency for the disposition of personal property located atvendor facilities.10According to agency officials, however, NASA has notprepared an estimate of anticipated exchange/sale revenue. The officialsindicated that proceeds received from the exchange/sale of SSP propertywill be transferred initially to an existing budget clearing account, wherein
9GSA issues regulations describing how and when the exchange/sale authority may be
used, as well as setting reporting requirements on their use. 41 C.F.R. 102-39. NASAsought and obtained GSA concurrence that the proceeds from the sale of non-excess, non-surplus personal property from SSP could be used to acquire replacement Constellationassets needed for human spaceflight activities.
10The Memorandum of Agreement between GSA and NASA stipulates that NASA will
receive 80 percent of the gross proceeds from NASA (generic) property sales. For thoseitems designated by NASA as shuttle related or unique, NASA negotiated to receive 90
percent of sales gross proceeds. According to NASA, GSA recovers its costs by retainingthis portion of the proceeds from the sale of the property and DCMA recovers its costthrough per hour charges to NASA.
Page 11 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
15/21
the agency will move the funds to a lower-level direct budget workbreakdown structure element to supplement the acquisition ofreplacement property by the Constellation Program.
SSP transition and retirement is an immense undertaking involvingnumerous actors across government and the aerospace industry. NASAfaces great challenges in completing all planned efforts between now andthe end of 2010. Effective implementation of these efforts requires carefulplanning to safely complete the ISS and repair the Hubble Space Telescopewhile expeditiously freeing SSP funding and facilities for the Constellationprogram. NASA is still in the process of developing the required plans.
Incomplete planning, however, does not preclude the agency fromproviding the Congress with a more informed basis for decision making.Indeed, NASAs strategic decision to delay submission of an estimate untilplanning is near complete has placed the Congress at a knowledge deficitrelative to available information when considering the agencys totalfunding needs. In the current budget environment, in which needs outpaceavailable funding, it is imperative that NASA provide the Congress with thebest information available, even if that information is incomplete orsubject to change.
To provide congressional decision makers with a more transparentassessment of funding needs for the SSPs property transition andretirement activities, we are recommending that the NASA Administratordirect the Space Operations Mission Directorate to include in NASAsfiscal year 2010 and future budget requests the agencys best estimates ofthe total direct and indirect costs associated with transition and retirementof space shuttle property, including estimates of potential exchange/salerevenue. These estimates should include but not be limited to
Conclusions
Recommendation forExecutive Action
those costs borne directly by the SSP; those funds requested under Cross-Agency Support that will be used to
support property transition and retirement activities, such as
funds requested to demolish excess facilities and buildings, and funds requested for environmental compliance and remediation, and; the potential proceeds from exchange/sales of excess space shuttle
property.
NASAs fiscal year 2010 and future budget requests should also identify allrequired transition and retirement activities which NASA has identified butnot yet included in cost estimates and report NASAs progress incompleting SSP transition and retirement activities.
Page 12 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
16/21
In written comments on a draft of this report (see app. II), NASAconcurred with our recommendation. NASA acknowledged that, thus far,it had not included estimates of the full scope and cost of Space Shuttletransition and retirement costs in any of its budget requests and that theagency is still in the process of finalizing the scope and cost of SpaceShuttle transition and retirement activities. NASA stated that it expectsestimates for fiscal year 2011 and beyond to be sufficiently mature toinclude in the Presidents budget proposal for 2010 and that the agencyintends, subject to approval by the Office of Management and Budget, toinclude the estimates in its fiscal year 2010 budget request. NASA alsoacknowledged the need to provide the Congress estimates of anticipated
revenue from exchange sales but noted that, even taking into account thelarge amount of personal property to be disposed after fiscal year 2010, theagency does not expect large amounts of revenue from exchange sales.NASA also stated that the SSP was only one contributing factor to specificsites requiring environmental remediation and that NASA consolidates itsbudget for environmental remediation. This report recognizes that legacyprograms contributed to environmental contamination and that NASA hasa consolidated budget for environmental remediation apart fromindividual programs. Nevertheless, environmental remediation of SSP sitesrepresents a substantial portion of the total costs associated withtransition and retirement of the SSP. Separately, NASA provided technicalcomments which have been addressed in the report as appropriate.
We are sending copies of the report to NASAs Administrator andinterested congressional committees. We will also make copies availableto others upon request. In addition, the report will be available at nocharge on GAOs Web site at http://www.gao.gov.
Should you or your staff have any questions on matters discussed in thisreport, please contact me at (202) 512-4841 or at ChaplainC@gao.gov.Contact points for our Offices of Congressional Relations and PublicAffairs may be found on the last page of this report. GAO staff that made
key contributions to this report are listed in appendix III.
Cristina T. ChaplainDirector, Acquisition and Sourcing Management
Agency Commentsand Our Evaluation
Page 13 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
17/21
Appendix I: Objectives, Scope, andMethodologyAppendix I: Objectives, Scope, and
Methodology
To assess National Aeronautics and Space Administrations (NASA)challenges in transitioning and retiring the Space Shuttle Programs (SSP)assets and facilities and to determine if the cost of these efforts istransparent in NASAs budget requests, we obtained and reviewed NASAdocuments including the Human Space Flight Transition Plan, SpaceShuttle Program Transition Management Plan, Space Shuttle ProgramTransition and Retirement Requirements, and the Space Shuttle ProgramRisk Management Plan. We also examined NASAs contractdocumentation, budget requests, and NASAs 2009 Planning, ProgrammingBudgeting and Execution Guidance. We physically inspected property andinterviewed and received detailed briefings from NASA and contractor
transition management officials at NASA Headquarters in Washington,D.C.; the Kennedy Space Center in Orlando, Florida; the Johnson SpaceCenter in Houston, Texas; the Marshall Space Flight Center in Huntsville,Alabama; the Stennis Space Center in Mississippi; and the MichoudAssembly Facility in New Orleans, Louisiana. We also attended NASAsTransition Quarterly Program Managers Review at the Stennis SpaceCenter. We discussed government property disposal policies and practiceswith General Services Administration officials in Washington, D.C., andDefense Contract Management Agency officials at the Kennedy SpaceCenter. In addition, we held discussions with Congressional ResearchService staff members on their prior and ongoing work related to NASAstransition effort. Furthermore, we met with NASAs Office of InspectorGeneral to discuss its report on the Space Shuttle Programs transition andretirement and reviewed previous GAO testimonies and reports related toNASAs transition effort.
We conducted this performance audit from February 2008 to August 2008in accordance with generally accepted government auditing standards.Those standards require that we plan and perform the audit to obtainsufficient, appropriate evidence to provide a reasonable basis for ourfindings and conclusions based on our audit objectives. We believe thatthe evidence obtained provides a reasonable basis for our findings andconclusions based on our audit objectives.
Page 14 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
18/21
Appendix II: Comments from the NationalAeronautics and Space AdministrationAppendix II: Comments from the National
Aeronautics and Space Administration
Page 15 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
19/21
Appendix II: Comments from the NationalAeronautics and Space Administration
Page 16 GAO-08-1096 NASA's Transition Challenges
8/2/2019 NASA 2008-1096
20/21
Appendix III: GAO
Contact and Staff Acknowledgments
Page 17 GAO-08-1096
Appendix III: GAO Contact and StaffAcknowledgments
Cristina Chaplain (202)512-4841 or chaplainc@gao.gov
In addition to the contact named above, Jim Morrison, Assistant Director;William C. Allbritton; Helena Brink; Greg Campbell; Sylvia Schatz; John S.Warren; and Alyssa Weir made key contributions to this report.
NASA's Transition Challenges
GAO Contact
Acknowledgments
(120720)
mailto:chaplainc@gao.govmailto:chaplainc@gao.gov8/2/2019 NASA 2008-1096
21/21
GAOs Mission The Government Accountability Office, the audit, evaluation, andinvestigative arm of Congress, exists to support Congress in meeting itsconstitutional responsibilities and to help improve the performance andaccountability of the federal government for the American people. GAOexamines the use of public funds; evaluates federal programs and policies;and provides analyses, recommendations, and other assistance to helpCongress make informed oversight, policy, and funding decisions. GAOscommitment to good government is reflected in its core values ofaccountability, integrity, and reliability.
The fastest and easiest way to obtain copies of GAO documents at no cost
is through GAOs Web site (www.gao.gov). Each weekday, GAO postsnewly released reports, testimony, and correspondence on its Web site. Tohave GAO e-mail you a list of newly posted products every afternoon, goto www.gao.gov and select E-mail Updates.
The first copy of each printed report is free. Additional copies are $2 each.A check or money order should be made out to the Superintendent ofDocuments. GAO also accepts VISA and Mastercard. Orders for 100 ormore copies mailed to a single address are discounted 25 percent. Ordersshould be sent to:
U.S. Government Accountability Office441 G Street NW, Room LMWashington, DC 20548
To order by Phone: Voice: (202) 512-6000TDD: (202) 512-2537Fax: (202) 512-6061
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htmE-mail: fraudnet@gao.govAutomated answering system: (800) 424-5454 or (202) 512-7470
Ralph Dawn, Managing Director, dawnr@gao.gov, (202) 512-4400U.S. Government Accountability Office, 441 G Street NW, Room 7125Washington, DC 20548
Chuck Young, Managing Director,youngc1@gao.gov, (202) 512-4800U.S. Government Accountability Office, 441 G Street NW, Room 7149Washington, DC 20548
Obtaining Copies ofGAO Reports andTestimony
Order by Mail or Phone
To Report Fraud,Waste, and Abuse inFederal Programs
CongressionalRelations
Public Affairs
http://www.gao.gov/http://www.gao.gov/http://www.gao.gov/fraudnet/fraudnet.htmmailto:fraudnet@gao.govmailto:dawnr@gao.govmailto:youngc1@gao.govmailto:youngc1@gao.govmailto:dawnr@gao.govmailto:fraudnet@gao.govhttp://www.gao.gov/fraudnet/fraudnet.htmhttp://www.gao.gov/http://www.gao.gov/Recommended