NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
MONTHLY PROGRESS REPORT on
NTDC DEVELOPMENT PROJECTSfor
March, 2013
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Ongoing Development Projects
Projects Ready for Implementation
Cross Border Interconnection Projects
1
ACTIVITIES
Ongoing Projects of NTDC
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of Work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
1-Extension at 500 kV Sheikh Muhammadi
Addition of 500/220 kV 1x450 MVA T/F
1,03817 21-01-2010 ADB
Tranche-IProject
Completed. 100 % Commissioned in June, 2012
Addition of 220/132 kV 1x160 MVA T/F
2- Extension at 500 kV Dadu
Addition of 500/220 kV 1x450 MVA T/F
1,05017 21-01-2010 ADB
Tranche-I
Project Completed. 100 % Commissioned in
June, 2012
Addition of 220/132 kV 1x160 MVA T/F
Project Completed. 100 % Commissioned in
December, 2012
3-
In/out of 220kV Ghazi Barotha – Shahi Bagh at Mardan
220 kV Double Circuit Transmission Line (30 km)
5339 30-11-2006 ADB
Tranche-IProject
Completed. 100 % Commissioned in December, 2012
3
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
4- 220 kV GIS Bandala
220 kV substation with two 220/132 kV 160 MVA T/Fs along with allied equipment. 1,950
32 30-11-2006 ADB Tranche-I
Civil & electrical works in progress.
76 % June, 2013
In/Out of 220 kV Gatti-KSK Transmission Line at Bandala (5+5 km)
Project Completed. 100 % Commissioned on
16-05-2012
5- 220 kV Rohri
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
4,84778 06-02-2008 ADB
Tranche-II
Civil and electrical works in progress.
75 % June, 2013
220 kV Dharki-Rohri New D/C T/L (115 km)
Project Completed. 100 % Commissioned in
June, 2012
220kV D/C Rohri New-Shikarpur T/L (50km)
220kV D/C T/L for In/Out of Fauji Mari-Rohri New at Engro Chemical CCPP (5+5km)
4
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No. Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected Commissioning
6-220 kV Khuzdar & 220kV Dadu-Khuzdar D/C T/L
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,90050 27-07-2004 JICA
Civil and electrical works in progress.
78 %
September, 2013220 kV Dadu-Khuzdar D/C T/L (274 km) Erection and
stringing work in progress.
85 %
7- 220 kV Kassowal
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,06736 02-02-2005 World Bank
Civil and electrical works in progress.
64 % December, 2013
Two 220 kV D/C T/L for In/out of 220 kV Vehari-Yousafwala D/C T/L at Kassowal (45+45km)
Project Completed. 100 % T/L commissioned
on 06-08-2012
8- 220 kV GIS Shalamar
220 kV gas insulated substation with three 220/132 kV 160 MVA T/Fs and allied equipment
3,61759 22-10-2007 JICA
Civil and electrical works in progress.
75 % September, 2013
Project Completed. 100 %
T/L commissioned on 20-11-2012
220 kV D/C T/L for In/Out of one circuit of 220 kV Ravi-KSK T/L at Shalimar (9 km)and under ground cable (3+3 km)
5
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
9- 220 kV Okara
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,88431 06-02-2008 ADB Tranche-II
Civil and electrical works in progress.
86 % June, 2013
In/out of 220 kV Yousaf Wala-Sarfraz Nagar D/C T/L at Okara (5+5 km)
Project Completed. 100 % T/L ready for
commissioning.
10- 220 kV T.T. Singh
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,75929 06-02-2008 ADB Tranche-II
Installation in progress. 86 %
June, 2013
In/Out of 220 kV Faisalabad-Multan D/C T/L at T.T Singh (1+1 km)
Civil works completed.
Erection and Stringing in
progress
86 %
6
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
11- 220 kV Loralai
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
5,08883 06-02-2008 ADB Tranche-II
Civil and electrical works in progress.
70%
June, 2013
220 kV D.G Khan-Loralai D/C T/L (200 km)
Erection and stringing in progress.
95 %
12-500 kV Rahim Yar Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment
4,93681 22-10-2007 JICA
Civil and electrical works in progress.
64 %
December, 2013
500 kV S/C T/L for In/Out of 500 kV Guddu-Multan 3rd Circuit at R.Y Khan (30+30 km)
Civil and Electrical works in progress.
57 %
7
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
13-Ext. at 500 kV Ghazi Barotha
Addition of one 500/220 kV 600MVA T/F with allied equipment.
1,65427 06-02-2008 ADB
Tranche-IICivil works in
progress. 37 % December, 2013
14- 220 kV Gujrat
220 kV substation with three 220/132 kV 250 MVA T/Fs with allied equipment.
1,96632 22-10-2007 JICA
Contract agreement
signed with M/S HYOSUNG Cooperation Korea on
03-01-2013.
5 % 2013-14220 kV D/C T/L for In/Out of 220kV Mangla-Ghakkar D/C T/L at Gujrat (2+2 km)
15-220 kV Ghazi Road, Lahore
220 kV substation with three 220/132 kV 160 MVA T/Fs and allied equipment
2,59243 25-02-2005 KfW
Bidding documents vetted by M/S Lahmayer and sent to KfW for concurrence.
5 %
2013-14220 kV D/C T/L for In/Out of 220 kV NKLP-S/Nagar S/C at Ghazi Road (30 km)
Ready for commissioning 100 %
220 kV D/C T/L for In/Out of 220 kV Ravi-KSK S/C at Ghazi Road (50 km)
8
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
16- 220 kV Chishtian
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
2,63343 22-10-2007 JICA
Civil work in progress. 20 %
December, 2013
220 kV Chishtian-Vehari D/C T/L (65 km) Civil and
Erection work in progress.
47 %
Extension at 220 kV Vehari Grid Station
17- 500 kV D.G Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment
4,46773 06-02-2008 ADB
Tranche-II
Civil works in progress. 23 %
December, 2013
Erection and stringing in progress
79 %In/Out of 500 kV Guddu-Multan 2nd Circuit at D.G Khan (20+20 km)
9
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Expected
Commissioning
18Augmentationof existing Grid Stations
Name of Grid Stations
No. of
T/FsVoltage
(kV)Capacity
(MVA)
3,90046
21-01-2010 ADB Tranche-II
i) Contract agreement for 13
T/Fs has been signed with M/S SUNIR and are expected to be
delivered in December 2013.
ii)Bidding document for 5 T/Fs has been sent to ADB for concurrence.
December, 2013
500 kV Rewat 1 500/220 750
500 kV Sheikh Muhammadi
4 220/132 250
220 kV Mardan 2 220/132 250
220 kV Burhan 4 220/132 250
220kV Bund Road 4 220/132 250
220 kV Bahawalpur 2 220/132 250
220 kV Quetta Industrial
2 220/132 250
10
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
19- SVC at NKLP Static Var Compensators of 450 MVA Capacity
2,08734 30-11-2006 ADB
Tranche-I
Contractor mobilized and
started the work.
10 % December, 2013
20- 220 kV Dera Murad Jamali
220 kV substation with 220/132 kV 1x160 MVA & 1x100 MVA T/Fs and allied equipment
88011
PC-I approved by CDWP on
07-04-2011NTDC own resources
Contractor mobilized and civil works in
progress.10 %
June, 2014
220 kV D/C single conductor T/L for In/Out of 220 kV Uch-Guddu S/C at Dera Murad Jamali (5 km)
T/L profile and Plan Tabling approved. 10 %
11
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
21-500 kV Lahore (South)
500 kV substation with two 500/220 kV 750 MVA T/Fs and allied equipment
12,664147 09-12-10 JICA
Contract agreement signed on 12-06-2012
with M/S CNEEC-
FNEPCC (JV).Contractor not yet mobilized.
5 % June, 2014
Two 500 kV S/C T/Ls for In/Out of 500 kV Sahiwal-Lahore S/C at Lahore New (15+15km)
Two 500 kV S/C T/Ls for In/Out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km)
220 kV D/C T/L for In/Out of 220 kV NKLP- Ghazi Road S/C at Lahore New (50km)
220kV D/C T/L for In/Out of 220 kV NKLP- Wapda Town S/C at Lahore New (45 km)
12
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
22- SVC at Quetta Static Var Compensators of 450 MVA Capacity
2,08734 06-02-08 ADB Tranche-II Not yet
started. NIL December, 2014
23- 500 kV Shikarpur
500 kV substation with two 500/220 kV 600 MVA T/Fs and allied equipment
8,08594 09-12-10 JICA
Contract agreement signed, L/C opened and contractor mobilized.
5 % June, 2014
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu -Guddu Cct # 1 (20+20 km)
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu – Guddu Cct # 2 (22+22 km)
220 kV D/C T/L for In/out of 220 kV Guddu – Sibbi S/C at Shikarpur(50 km)
13
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Overall
ProgressExpected
Completion
24-
Power Dispersal from 747 MW CCPP Guddu
500kV Guddu-Muzaffargarh S/C T/L (256 km)
7,85691 29.07.2011 Buyer’s Credit
Basis
Tender opened on 08.10.2012 evaluated and sent to BOD for
approval.NIL Dec. 2014Two 500 kV T/L for In/Out of
500 kV Guddu-Multan S/C T/L at 500 kV Muzaffargarh (10 +10 km)
Extension at 500kV Muzaffargarh
25-Power Dispersal from Uch-II
220 kV Uch-II – Sibbi D/C T/L (125km)
2,50830 16.08.2012 ADB
Tranche-III
Tenders opened on 12.12.2012 and
evaluated by C.E Design. Technical committee of BOD
NTDC allowed to get concurrence from ADB for negotiation with the
bidder.NIL Dec. 2014
220 kV D/C T/L for In/Out of 220kV existing Uch-I to Shikarpur New S/C T/L at Uch-II (0.5 km)
Reconductoring of 220kV T/L Uch-I to Uch-II (1 km)
Extension at 220kV Sibbi substation
Work in progress from NTDC own resources.
14
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusOverall
ProgressExpected
Completion
26-Power Dispersal from Neelum Jhelum HPP
Package-I500 kV D/C T/L from Neelum Jhelum to Gujranwala (270 km)
22,582251
PC-I cleared by CDWP on 18-06-2012
Buyer’s Credit Basis
Tender opened on
09-08-2012, evaluated
and submitted for
BOD approval. NIL 2015-16
500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Azad Pattan (5km)
500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Karot (5 km)
Package- IIExtension at 500 kV Gujranwala
Draft Bidding documents
submitted to NTDC on
Nov. 29,2012.
27-
Power Dispersal Arrangements from Duber Khwar Power House
220 kV D/C T/Line from Duber Khwar to Khan Khwar Power House (33km)
249428
(For Lot-I & II)
Approved under PC-I of Hydel Power Project
Deposit work of G.M (Hydel)
Work is withheld due
to ROW problems.
89% June. 2013
15
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER 16
Sr. No.
Name of the Projects Scope of work Estimated Cost
(MRS/MUS$) Financing Project Status Expected Completion
28-
Dispersal of power from 2x50MW Wind Power Plants at Mirpur Sakro
132kV D/C T/L on Greeley conductor from WPP#1 to 132kV Thatta G/S (60km)
81614
NTDC own resources
Tenders for construction opened on 11.02.2013.
Dec. 2013
132kV D/C T/L on Greeley conductor for In/Out of one cct of WPP#1 to Thatta 132kV line at WPP#2 (2km)
132kV S/C SDT T/L on Cairo conductor from WPP#1 to 132kV M.P Sakro G/S (15km)
Tenders for purchase of
material opened on
30.03.2013. Construction of two 132kV line bays each at Thatta and Mir Pur Sakro Grid Station
Total 110,9401,520
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 500kV Projects
Sr. No. Description Addition in T/L & T/F Capacity
1- 500 kV S/C Transmission Lines Length 1150 km
2- 500/220 kV Transformation Capacity (New Projects) 5100 MVA
3- 500/220 kV Transformation Capacity (Extension) 1500MVA
4- 500/220 kV Transformation Capacity(Augmentation) 300MVA
500/220 kV Transformation Capacity(Grand Total) 6900MVA
17
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 220kV Projects
Sr. No. Description Addition in T/L & T/F
Capacity
1- 220 kV D/C Transmission Line 1257.5 km
2- 220/132 kV Transformation Capacity(New Projects) 6930 MVA
3- 220/132 kV Transformation Capacity(Extension) 320MVA
4- 220/132 kV Transformation Capacity(Augmentation) 1620MVA
220/132 kV Transformation Capacity(Grand Total) 8870MVA
18
Projects Ready for Implementation
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of Approval by
ECNECFinancing Project Status Expected
Completion
1-3rd Circuit from Jamshoro to Rahim Yar Khan
500 kV Jamshoro-Moro-R.Y.K S/C T/L (535 km)
24,831285
PC-I Cleared by CDWP on 21.10.2011
ADBTranche-III
Tender scrapped due to technical & administrative reasons by MD
NTDC. Rebidding in
progress.
2015-16
500 kV Moro-Dadu S/C T/L (55 km)
500 kV Switching Station at Moro
Extension at 500 kV Jamshoro, Dadu & R.Y.K Grid Stations.
2-Power Dispersal from Chashma Nuclear (C3 & C4)
220 kV Chashma Nuclear – Bannu D/C T/L (125 km)
3,10335
PC-I is under scrutiny in Planning
Commission
Buyer’s Credit Basis
Route under checking. 2015-16
220kV D/C T/L for In/Out of existing C1 &C2 at C3 & C4 (2 km)
Extension at 220kV Bannu
20
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of Approval by
ECNECFinancing Project
StatusExpected
Completion
3-
Power Dispersal from 1200 MW Thar Coal Based Power Plant
500 kV Thar – Matiari D/C T/L (250 km)
22,306259 16.08.2012 Buyer’s Credit
Basis
T/L Plan and Profile
Drawings completed.
2015-16
500 kV Switching Station at Matiari
4- 220 kV Nowshera
220kV sub station with 220/132kV 3x250 MVA T/Fs along with allied equipment
1,87631 06.02.2008
Proposed in ADB
Tranche-IV
Hiring of project
preparatory consultants in
process.
2015-16In/Out of 220 kV Ghazi Barotha – Shahi Bagh D/C T/L at Nowshera (5+5 km)
21
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of Approval by
ECNECFinancing Project Status Expected
Completion
5- 220 kV Lalian New
220kV sub station with 220/132kV 3x250 MVA T/Fs along with allied equipment
1,58118 11.11.2011
Proposed in ADB
Tranche-IV
Hiring of project preparatory
consultants in process.
2015-16Two 220 kV D/C T/L for In/Out of 220 kV Gatti – Ludewala D/C T/L at Lalian New (4+4 km)
6- 220 kV Mansehra
220kV sub station with 220/132kV 2x250 MVA T/Fs along with allied equipment
90511
07.04.2011
ADBTranche-III
Tenders opened on 26-02-2013 and are
under evaluation.2015-16Two 220 kV D/C T/L for
In/Out of 220 kV Alai Khawar – Islamabad Peshawar Road D/C at Mansehra (0.5+0.5 km)
22
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of approval by
ECNECFinancing Project Status Expected
Completion
7- 220/132 kV D.I.Khan
220kV sub station with 220/132kV 2x250 MVA T/Fs along with allied equipment
3,77944
09.12.2010Proposed in ADB
Tranche-IV
Land for G/S acquired.
Construction of boundary wall in
progress.
2015-16220 kV D/C T/L for In/Out of 220 kV Chashma Nuclear-Ludewala S/C T/L at D.I Khan (100km)
Total 58,401
661
23
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Projects Ready for Implementation
Sr. No. Description Addition in T/L & T/F Capacity
1- 500kV S/C Transmission Lines Length 1090 km
2- 220kV Transmission Line 246 km
3- 220/132 kV Transformation Capacity 2500 MVA
24
Cross Border Interconnection Projects
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
1-Import of 100MW Power from Iran.
220 kV Pak Iran Border-Gwadar D/C T/L (100km)
44
Survey work in progress.
Iranian Bank August, 2014Work awarded to contractor and
contractor mobilized.
220KV GIS at Gwadar with 2x160MVA T/Fs
2-Import of 1000MW Power from Iran.
500kV HVDC Bipolar Transmission Line from Pak - Iran Border to Quetta (585km).
413
MoU signed between Pakistan & Iran on 31.05. 2012
to implement the project.
Not yet committed 2015-16
500 kV Convertor Station at Quetta.
26
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
3-Import of 1000MW Power from Tajikistan.
500kV HVDC Bipolar Transmission line from Pak-Afghan Border to Peshawar (71km).
189 Feasibility Study completed.
Positive response from
World Bank and IDB
2015-16
500 kV Converter Station at Peshawar
4-Import of 200-500 MW Power from India.
Different options for Interconnection are under study. -
World Bank has offered to sponsor pre-feasibility study
for the project
Positive response from
World Bank-
Total 646
27
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Report Prepared by: Designation Contact No.
Maqsood Ahmad Qureshi
Additional ManagerProjects Planning
0347-4447720 042-99202609
Fahmeeda Shafi Dy. Manager Projects Planning
042-99202609
28