Oksut Project Progress Presentation28 Mayıs 2019Develi, Kayseri
May 2019
Content
• IntroductionDr. Alper Sezener, General Manager
• Project Construction UpdateGraeme Rapley, Project Director
• Operational Readiness ProcessRodney Chanin, Operation Director
• Exploration & Business Development ActivitiesDr. Alper Sezener, General Manager
• OHS & Sustainability UpdateÖzgür Ararat, OHS & Sustainability Director
• HR&Training UpdateT. Cem Serin, HR & Legal Compliance Director
• Questions & Comments
2May 2019
3
Introduction
May 2019
5
Öksüt: Funded High Margin Gold Production
Öksüt Gold Project
Project HighlightsMine Type Open Pit, Heap Leach
Avg. LOM Annual Production 110koz Au
Avg. LOM AISC(1) (US$/oz) $490
Reserve Mine Life 8 years
Development Capex (US$MM) $221
LOM Sustaining Capital(1) (US$MM) $10
P&P Reserves(2)(Moz) 1.3
Au grade (g/t)(2) 1.4
Life of Mine Strip Ratio (w:o) 2:1
First Gold Pour (3) Q1-2020
Catalyst Schedule
EIA approval received in November 2015
Forestry Permit & GSM License received July 2016
Pastureland Permit received January 2018
Investment Incentive Certificate received February 2018
Start construction 2018 on track for Q1 2020 gold pour
Bought back Stratex and Teck royalties in 2015 & 2016
US$150MM low-cost financing in-place
Installing Road Barriers
(1) Non-GAAP measure see “Non-GAAP Measures” in Centerra’s MD&A and news release of May 1, 2019.(2) Refer to February 22, 2019 news release and Technical Report on Öksüt Gold Project dated Sept. 3, 2015.(3) Forward-looking information refer to news release of May 1, 2019.May 2019
Key Milestones
6
● 4th November 2015 EIA Approval● 6th June 2016 ESIA Approval● 14th July 2016 Forestry Permit● 11th August 2016 Operation Permit● 12th January 2018 Pastureland Permit● 25th March 2018 Main Access Road/Haul Roads Starts● 25th April 2018 Heap Leach Pad and site infrastructure
Starts
● May 2019 Commence Stripping Over Burden● July 2019 Start Stocking Piling Ore● January 2020 Commence Crushing Ore/Stacking on
Heap Leach● February 2020 Commence Irrigation of Heap Leach● February 2020 First Gold Pour
May 2019
Project Construction
7May 2019
Construction Schedule
8May 2019
General Earthworks Plan – Ongoing Works
9May 2019
Project Overall Completion – as of 12 May 2019
10
Construction Progress : 56 % (as of May 12, 2019)May 2019
Major Packages % Completion Status as of 12 May 2019
11
Project's Overall Completion84 % First Gold
Major Packages
Site Wide Earth Works Construction
Crusher MPEI Construction
Raw Water Supply System
Administration Buildings
ADR Plant EPC
Main Substation
Lining System
Site Electricity Distribution
Sendremeke 154kv Powerline 100 %
69 %
90 %
42 %
48 %
56 %
49 %
75 %
81 %
52 %
May 2019
Site Photos
Administration Area
12May 2019
Site PhotosHDPE Liner Heap Leach Pad Secondary Crusher Building
13
ARD Plant
May 2019
Operational Readiness
14May 2019
Mining
*Resource/Reserve Update- 31 December 2018
15May 2019
MiningMining Progress May 2019
16
Keltepe Pit May 2019
May 2019
Process
● Management in place and starting the phase-in of the crusher team first, ADR team to follow.
● Preparing for the commissioning of crusher plant in July.
● The metallurgical accounting and reporting system has been generated.
● Stacking plan for the first lift of HL is completed see below.
17
Heap Leach Stacking 2019
May 2019
Process
● Cyanide transportation schedule for 2019 and 2020 was completed which coincides with the Cn storage completion.
● Cyanide management plan works are being coordinated with the supplier.
● Activated Carbon and reagents order was placed for early August delivery.
● The site lab is constructed and the contractor is setting up.
18
ADR Plant
May 2019
Maintenance
• Maintenance is closely following the construction progress and ensuring that is being done to an acceptable level.
• Crusher and ADR asset registrations are completed in the systems.
• Crusher circuit consumables, operating and critical spare parts have been identified and ordered.
• Crusher eequipment standard jobs and maintenance schedules are being compiled.
• Shop and hand tools as well as mobile service equipment has been ordered.
• Preparing training programs for blue collar workers.
19May 2019
Exploration
20May 2019
21
Öksüt Gold Project
Tethyan Metallogenic Belt
*Sourced from MDRUMay 2019
Project Location and Prospects
Öksüt Gold ProjectOperation License
Boundaries
Keltepe
Guneytepe
Yelibelen
Buyuktepe
Keltepe NW
Boztepe
Öksüt Gold
Project
Kayseri Keltepe NW
Keltepe
Guneytepe
Buyuktepe
Boztepe
Boztepe W
Yelibelen
22May 2019
YelibelenOxide-Au
Target
BuyuktepeOxide-Au
Target
Keltepe - Keltepe NW Oxide Au Resource +Supergene Cu target
Boztepe WestPorphyry Cu/Au
Target
N
Keltepe Pit
Güneytepe Pit
GüneytepeOxide-AuExtension
2019 Proposed Drilling Program
23May 2019
OHS & Sustainability
24May 2019
Significant Incidents (SI)
# Incidents
ICAM Completion
Management Review
QTD # 1 1 2YTD # 2 2 2
Critical Risks (CR’s) (Highest to Lowest Occurrence)
Critical Risk Categories QTD YTD
1 Mobile Equipment (Heavy & Light Vehicle) 1 1
2 Release of Energy 0 03 Cranes and Lifting 0 04 Working at Heights 1 15 Exposure to Chemicals 0 0
25
Key Projects & InitiativesImplementation Status
Safety Leadership Initiative
Reduction of Mobile Equipment Incidents
Compliance Audits
# Findings % Complete Status
QTD # 6 100 100YTD # 6 100 100
KEYAudits, Risk
Management & AIP Objectives
0-33% Implemented
33-66% Implemented
>66% Implemented
Initiatives & Projects
Major Issues (deliverables
compromised)Minor Issues (recoverable)
On Track or Approved
Lag IndicatorsTotal Reportable Injury Frequency
Rate (TRIFR)
Target YTD Status
<1,32 0,36
Severity Rate
Target YTD Status
<5.50 4
Health and Safety Performance
Preventative ActivitiesYTD Y/E TARGET
#Safety Meetings 1291 2250#Inspections 555 1768#Training Hours 20107 51000#Near Miss Reports 2 x
#Hazards Identified 1171 1080
WS HS 1– 2 attendance 115- 144 550- 550
1 1
2 0
1 1
2 0
Q1 Q2 Q3 Q4
SI CRISignificant Incidents vs Critical Safety Risks
May 2019
Environmental Performance
26
* No reportable incident YTD
Compliance AuditsType # Findings % Complete Status
Regulatory 0 %100 ↑Internal Audit 0 %100 ↑
CN Code N/A N/A N/A
Projects & InitiativesTitle Status
Biodiversity Management Plan Active
ESIA and Management Plans Active
Total of IncidentTo date This Reporting Period
0 0Date Raised Registration Number Location Incident Summary Corrective
Action Close out Date
- - - - - -
May 2019
Social Performance
27
Stakeholder Engagement
# Community Meetings # Local Officials Visit # Total
MTD YTD MTD YTD MTD YTD
19 81 4 31 23 112
Grievance Resolution
# Grievance % resolved within the targeted timeframe # of unresolved Grievances(cumulative)
MTD YTD MTD YTD MTD YTD
0 16 %0 %100 0 0
CSR/Community Projects Donations Livelihoods RestorationApproved Budget(2018)
MTD YTD Approved Budget MTD YTD Approved Budget MTD YTD
341K 1067 25097 20K 0 0 250K 17836 17836
May 2019
Environmental Activities
28
ENVIRONMENTAL ACTIONSActions Partners Status
1. Biodiversity Studies
- Flora StudiesProf Hayri DUMAN (Gazi Unv),Cecilia AMOSSO (Golder Italy),
Prof. Dr. Cem VURAL (Erciyes Unv) On going
- Fauna Studies
Prof. Dr. Cem VURAL (Erciyes Unv) , Prof. Dr. Osman İBİŞ (Erciyes Unv),
Doç.Dr. Şafak Bulut (Hitit Unv), Prof.Dr. Ahmet Karataş (Niğde Unv),
Bird inspector Mehmet Ünlü (Niğde Unv)
On going
2. Environmental Monitoring
- Water Quality (Graundwater, suface water etc.)GOLDER (Artek,ALS)
Prof. Dr. Hasan YAZICIGİL (ODTU)Prof. Dr. M. Zeki ÇAMUR (ODTU)
On going
- Air Quality (Dust ,Noise etc.) GOLDER (Batı Laboratory) On going
3. Waste Management Develi Municipality , KASKI Licensed recycling / disposal companies On going
4. Cultural Heritage Kayseri Provincial Directorate of Culture and Tourism (Museum Directorate) On going
May 2019
29
Environmental Monitoring
May 2019
ESAP Commitments
30May 2019
CR & CSR
3131
Visit with General Manager to Mayor of Develi Municipality on April, 2019
Meeting with Local Media in DeveliDistrict on April, 2019
Planned Tree Planting Activity with Governmental Authorities, 2019
New CR Liaison Office restoration studies was continued, 2019
Stakeholder Engagement Components
18 March Çanakkale Victory and Martyrs’ Day event in Develi Center was
attended on 18th of March, 2019
Newspaper announcement for 1,5 Million Hours Lost Time Incident Free
on April 2019May 2019
LRP Programs
32
LRP Programs
LRP - 2019
Subject Date Status
Income generating activities for users of Pastureland-Beekeeping May-December Completed
Agricultural equipment support for users of Pastureland May-June On going
Access to Grazing Areas and Agricultural Fields(Öksüt Quarter) February-April Completed
Improving water supply for users of Pastureland May - September On going
Animal watering pond improvement and new pond construction for users of Pastureland May - November On going
Access road renovation at Pasturelands May - November On going
May 2019
CSR Programs
33
CSR ProgramsCSR- 2019
Subject Planned implementation period Status
Support to Regional Cultural Festival and Sport Activities July-August Not Started
Robotic Coding and Educational Brain Games Project for Students
Career Days for High School Students May-June On going
Theater for 23rd of April, National Sovereignty and Children's Day Ceremony April Completed
Support for Epçe Girls Volleyball Team March Completed
Support for Girls Volleyball Teams from Other Quarters October- December Not Started
Movie Days for the Students March-June Completed
Technical Fair and Exebition Visits for Farmers October- December Not Started
Social and Youth Centers-Develi Center June-December Not Started
Quick Impact Projects Improvement and Development of Common Use Areas May-December On going
Income generating activities- villige Cooperatives June-November Waiting for grant support
Income generating activities for Women May-December On going
May 2019
HR & Training
34May 2019
35
Manpower Tables
Numbers are updated as of May 16th,2019May 2019
36
Manpower Tables
OMAS Contractors
93 as of May 16th,
2019 OMAS Manpower Plan
May 2019
37
Training
May 2019
THANK YOU!
Questions?
Issues!
38May 2019