i
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
Document: Outline Method Statement
Project: Waterford Estuary Cable Crossing – Site Investigation
Client: Eir
Report Number: CM1003/SI/FS/R/001
File Origin: Z:\PROJECTS 2016\CM1003 Eir Submarine Cable Waterford\Foreshore - Site Investigation\Outline Construction Method Statement Rev 0.docx
Document Checking:
0 08-Dec-2016 Foreshore SMC AC AC
3 Westbourne Place, Cobh, Cork, P24 Y560, Ireland. Tel: +353 (0)21 4815441, Email: Cobh@ByrneLooby.com
www.ByrneLooby.com
ii
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
1 Introduction .................................................................................................................................... 1
2 Brief Description of the Works ........................................................................................................ 2
3 Outline Method Statement ............................................................................................................. 3
3.1 Slit Trench ............................................................................................................................... 3
3.2 Geophysical Survey ................................................................................................................. 3
3.3 Borehole Site Investigation ..................................................................................................... 4
3.3.1 Mobilisation .................................................................................................................... 4
3.3.2 Towing of Barge .............................................................................................................. 4
3.3.3 Shell and Auger Works .................................................................................................... 4
4 Health and Safety ............................................................................................................................ 5
4.1 Method Statement & Risk Assessment ................................................................................... 5
4.2 Personal Protection Equipment .............................................................................................. 5
4.3 Safety Boat .............................................................................................................................. 5
4.4 Weather Conditions ................................................................................................................ 5
4.5 Communications ..................................................................................................................... 5
5 Environmental Considerations ........................................................................................................ 6
5.1 Marine Mammal Observer ...................................................................................................... 6
5.2 Refuelling ................................................................................................................................ 7
1
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
2
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
3
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
4
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
5
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
6
ByrneLooby www.ByrneLooby.com
December 2016 Rev 0
7
ByrneLooby www.ByrneLooby.com