1

Electric Bus Management System

Project ProposalWilliam Chow, Amer Al-Mousa, Osama Mohammed

2

Electric Bus Management SystemProject Overview

Managerial Process Plans

Technical Process

Questions

3

Project OverviewProblem Outline

Purpose, Scope, and Objectives

Constraints

Project Deliverables

4

Problem OutlinePublic transportation faces problems with

pollution and high fuel prices.

Currently no electric bus made by any North American manufacturer.

5

PurposeThe purpose of this project is to provide a

flexible control system.

The system will provide an easy interface to add new electrical hardware.

Provide a GUI for the control system.

6

ScopeThe scope of this project is only to provide a

software control system.

The software control system will also be modular, so future software engineer students may add more features.

7

ObjectiveProvide a software foundation for later

software engineering students to build upon.

Provide a working software control system for the electrical hardware supplied.

8

ConstraintsThe major Constraint is with how much

hardware Electrodynamics is supplying.

No battery provided at this point.

9

Project DeliverablesDeliverable Due Date

Project Proposal October 9th

Project Proposal Presentation October 16th

Progress Report January 8th

Progress Report Presentation January 15th

Final Report Draft March 15th

Final Report March 29th

Final Presentation April 7th

10

Managerial Process PlansStart-up Plan

Estimation PlanStaffing PlanResource Acquisition PlanProject Staff Training Plan

Work PlanDeliverables (Work Activities)Schedule Allocation

Control PlanRequirement Control PlanSchedule Control PlanQuality Control PlanReporting Plan

11

Start-up PlanEstimation Plan: Formal techniques and tools will be used estimate, track

and evaluate the progress of the project (Rational Team Concert) RTC

Top-down approach is used to identify deliverables, sub-deliverables, up to the task level

Deliverables are grouped into a Work Breakdown Structure WBS

Tasks are implemented in a time-boxed iterations-sprint (2-4 weeks)

The progress of each task and its work package is tracked using automated project management tools

12

Start-up Plan - (Cont.)Staffing Plan: Three of us should contribute equally into the project, and

would be available for the whole duration of the project

Resource Acquisition Plan: Any required resources, such as hardware, software,

documentations, and any other type of resources, should be supplied by the client

Project Staff Training Plan: Educational sessions

13

Work PlanDeliverables (Work Activities): The Documentations

The Software development Documentations The Product Documentations

The GUI sub-systems The Admin UI The Dashboard UI

The Central Management System (CMS) Helper Systems

Microcontrollers Microcontroller to control motor Microcontroller to simulate driver

Work Plan (Cont.)

Initial WBS

EBMS

Hardware

Central Management

System

Documentations

Dashboard UI

Microcontrollers

Product Docs

Development Docs

Admin UI

GUI systems

Helper Systems

14

15

Work Plan – (Cont.)Schedule Allocation:

16

Control PlanRequirement Control Plan We do not expect many changes in the requirements Changes are classified as a minor, or major changes Risks to be highlighted at the very beginning

Schedule Control Plan Some of the deliverables have a fixed due dates and it should

be respected Tasks are sized and implemented in their assigned sprints,

otherwise remaining work is carried over to next sprint as a technical debt

Planning tasks in short sprint is usually accurate

17

Control Plan – (Cont.)Quality Control Plan The over all system undergoes different type of verifications

tests Every component has a Functional Verification Test Plan – FVT Design reviews, Test Plan reviews, and Code reviews

Reporting Plan Tasks are placed in the sprint backlog, then assigned to team

members Team members report their progress of their individual

backlogs Automated tools are used for compute the sprint progress, and

the over all progress

18

Technical ProcessElectric Bus Management System (EBMS)

Technical System OverviewTools and Programming LanguageProcess Model

EBMS• The Electric Bus Management System (EBMS) is a

system designed to control electrical devices or systems of an electric bus or vehicle

19

EBMS Components• EBMS composed of several subsystems

• 2 Different Software Systemso Central Management System (CMS)o GUI (Dashboard, Admin UI)

• 2 Microcontrollerso Microcontroller to control Electric Motoro Microcontroller to interface with a Mechanical Device

used to simulate a bus driver

20

Devices Interacting with EBMS• 2 Devices

o Electric Motor (EBMS should be able to interact with any electrical device that can part of an electric bus)

o Mechanical Device that issues commands simulating a bus driver

21

GUI• 2 displays• Admin UI: simple console-like (Console Display)

display to make it easy to add components to the system and print messages

• Dashboard UI: Resembles the Dashboard of a car

22

CMS• Central component of the EBMS• Updates Dashboard Display• Sends commands to electrical devices (through a

microcontroller)• Receives commands from the driver simulator• Responds to commands issued through Admin UI

23

Microcontrollers• They are programmable chips that are used to

interact with electrical devices• Device Specific• CMS uses functions programmed into a

microcontroller to communicate with an electrical device hooked up to the microcontroller.

24

25

EBMS Communications

26

              Black Arrow: Function Call              Blue Arrow: Response Message

27

28

Iterative & Incremental Life Cycle Model

29

Tools and Programming LanguagesTools• IDE used to help with programming lower layer (microcontrollers)

Programming Languages• Lower Layer: C• Higher Layer: C++, Java, or C Sharp

Hardware• 2 microcontroller (for the electric motor and for simulating a driver)• Server Machine – install CMS & GUI on it (or virtual server)• Electric motor• Network Protocol (to communicate with microcontrollers)