TRANSFORMING. REGENERATING. REVITALISING.
PRINCE OF WALES
DETAILS OF THE PLANS WHICH WERE SHOWN AT THE RESIDENTS LIASION MEETING HELD ON MONDAY 18TH SEPTEMBER AT ST GILES
CHURCH, PONTEFRACT
PRINCE OF WALES ORIGINAL CONSENT & MASTERPLAN (2013)
TRANSFORMING. REGENERATING. REVITALISING.
The scheme was granted outline planning permission for mixed-use development. This approval
was for the following elements:
RESIDENTIAL DEVELOPMENT
EMPLOYMENT / COMMERCIAL
COMMUNITY
RETAIL
Consented Masterplan - December 2013
A medical centre (D1)
A community centre (D1)
A new road, access roads, a linear park,
footpaths, public squares and public open
spaces, car parking, landscaping and
associated works
917 residential units (use class C3)
21,583 sq metres of employment (B1)
2,474 square metres of retail, restaurants
cafés and drinking establishments
10 live-work units (sui generis)
PRINCE OF WALES APPROVED DESIGN CODE
TRANSFORMING. REGENERATING. REVITALISING.
Entrance Layout Approved Design Code (November 2014)
A Design Code was agreed with Wakefield Council in 2014 to ensure quality of development
throughout. As part of this, a green/urban square was introduced with commercial uses to frame
a square.
Significant engagement through workshops took place with a Design Panel to review the Design
Code. A community engagement event also took place in September 2014 at Pontefract Town
Hall with the public generally supportive of the proposed Design Code.
The Design Code was finally approved on 7th November 2014 which included the plans on this
and the following two boards. Residents should note that these are outline plans and that any
future detailed plans will be the subject of further consultation.
TRANSFORMING. REGENERATING. REVITALISING.
PRINCE OF WALES APPROVED DESIGN CODE
Green/urban Square Approved Design Code (November 2014)
Design Strategy - Entrance Approved Design Code (November 2014)
Instead of general employment units
(known as B1 uses) fronting onto the site
entrance as outlined in the original
masterplan, an urban green square with
retail and live-work units were proposed
at the Park Road entrance as it was
considered to be suitable in terms of
location, good access and compatibility
with phasing.
As well as including built development in
the form of retail and live-work units, the
suggestion for the Park Road entrance
included a green/urban Square.
Forming part of the approved Design Code was an updated masterplan, which reflected the
movement of community facilities and the introduction of a green/urban square surrounded by
the retail and live-work units.
This masterplan was approved by Wakefield Council in November 2014 and has guided all
on-site development since that time.
Current Masterplan (Approved November 2014)
PRINCE OF WALES CURRENT MASTERPLAN
TRANSFORMING. REGENERATING. REVITALISING.
175 homes have been built by
Avant Homes and Harron Homes.
Another 140 will be built in the next
two years as part of the current
phases being brought forward.
Signalised junction and entrance
off Park Road installed.
New Pontefract East link road
delivered on-site of former spoil
heap, with improvements to
Skinner Lane due to commence.
New Cycleway/Greenway being
constructed.
TRANSFORMING. REGENERATING. REVITALISING.
PRINCE OF WALES PROGRESS SINCE 2014
Aerial Photograph - January 2014
Aerial Photograph - May 2017
175 homes now
built
400 residents moved in
Greenway under con-struction
TRANSFORMING. REGENERATING. REVITALISING.
PRINCE OF WALES WORK ON-SITE NOW
Construction of new
Cycleway and Greenway
due to complete in Spring
2018.
New entrance feature to be
installed off Park Road.
We are also temporarily
greening a section of public
open space in the centre of
the site, ready to be used
from Spring 2018.
The Greenway
Entrance Wall Feature
TRANSFORMING. REGENERATING. REVITALISING.
PRINCE OF WALES WHAT WE’RE PROPOSING NEXT
2017
Continue construction of Greenway.
Seeding of public open space at the centre of the site (for temporary use ahead of final
design).
Commence Skinner Lane road improvements.
Proposed masterplan to be consulted on and revised following feedback, prior to being
Proposed new masterplan
RESIDENTIAL DEVELOPMENT COMMUNITY USE COMMUNITY USE KEY:
TRANSFORMING. REGENERATING. REVITALISING.
PRINCE OF WALES WHAT WE’RE PROPOSING NEXT
Residential Phasing Plan
2018
Public consultation on proposals for what will become the urban green square and central
open space.
Further phase of housebuilding to begin off Skinner Lane (Phase 3), subject to planning.
Further phase of housebuilding to begin behind the retail park (Phase 6), subject to planning.
Enhancement of Tanshelf Walk and Colonels Walk to improve site accessibility.
Discussions with local stakeholders on location of local centre prior to plans being worked up.