Project ‐ Quarterly Progress Report

Promoter’s Name : RAMKY WAVOO DEVELOPERS PVT.LTD.

Project Name : GRAND CORRIDOR

Project Registration No : No.TN/02/Building/0037/2019

Quarter Ending : JANUARY 2020.

A. Sales

Sl.

No.

Description No. Total Area

1. Plots/Flats Booked size wise (As given in Carpet Area

Statement while registering)

49 5684.362 Sq.m

2. Parking Slots 49

3. UDS Registered in Sq.m. 3 143.349

B. Construction

C. Details of Clearances

1. Completion Certificate No. ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (only CC No. in Text Format)

2. Compliance Report, if any (Kindly Specify) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)

3. Annual Audit Report of Special Account in Form 7 ‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)

D. Latest Photo with Date (Atleast from 2 angles) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)

Note: Report the above particulars under “Registered Projects” in www.tnrera.in

Sl.No. Description Block/Tower

No. Status

1

Compound Wall &

Foundation

ABC

Compound Wall :- 100 % of work has been completed,

Foundation :-

Pile Foundation Work 40 % has been Completed,

Balance Work In Progress

Reg. No.TN/02/Building/0037/2019

PROJECT STATUS REPORT

JANUARY 20

Views

TYPE Area in Sq.ft No of Apt’s

No. of Apt’s Booked

A BLOCK

3 BHK /2T 1359-1436 566

3 BHK/3T 1491-1606 5615

TOTAL 11221

Project Details

Car park Details No. of Lots Booked

Total No. of Car Park Provided - A BLOCK

126 Nos

Covered Car Park 126 14

TYPE Area in Sq.ftNo of

Apt’s

No. of Apt’s Booked

B BLOCK

3 BHK /2T 1343 - 1418 563

3 BHK/3T 1528 - 1558 565

TOTAL 112 8

Project Details

Car park Details No. of Lots Booked

Total No. of Car Park Provided – B BLOCK

126 Nos

Covered Car Park 126 9

TYPE Area in Sq.ft No of Apt’s

No. of Apt’s Booked

C BLOCK

2 BHK /2T 1051 - 1159 132 20

TOTAL 132 20

Project Details

Car park Details No. of Lots Booked

Total No. of Car Park Provided – C BLOCK132 Nos

Covered Car Park 34 11

Open Car Park 98 6

Total No. of Car park Provided for Club House / Visitors 19 Nos 17

Project Status,.

Compound Wall -100 % Completed

Pile foundation Works 40 % Completed, Balance Work in Progress

Project Status,.

Compound Wall -100 % Completed

Pile foundation Works 40 % Completed, Balance Work in Progress

Project Status,.

Compound Wall -100 % Completed

Pile foundation Works 40 % Completed, Balance Work in Progress

Project Status,.

Compound Wall -100 % Completed

Pile foundation Works 40 % Completed, Balance Work in Progress

Project Status,.

Compound Wall -100 % Completed

Pile foundation Works 40 % Completed, Balance Work in Progress

Project Status,.

Compound Wall -100 % Completed

Pile foundation Works 40 % Completed, Balance Work in Progress