Project ‐ Quarterly Progress Report

Promoter’s Name : RAMKY WAVOO DEVELOPERS PVT.LTD.

Project Name : LEMONGRAZ

Project Registration No : TN/02/BUILDING/0036/2017

Quarter Ending : JANUARY 2020.

A. Sales

Sl.

No.

Description No. Total Area

1. Plots/Flats Booked size wise (As given in Carpet Area

Statement while registering)

114 144780.0 Sq.m

2. Parking Slots 114

3. UDS Registered in Sq. m. 81 2715.46 Sq. m

B. Construction

Sl.No. Description Block/Tower

No. Status

Structure – Stilt to Terrace Floor Completed.

Block Work – 1st to 12th floor block work completed.

Internal Plastering ‐ 1st to 12th floor plastering work completed.

External Plastering ‐ East, West & South and North side of the

building Plastering work completed.

Water Proofing Work ‐ 1st to 12th floor water proofing work

Completed.

1

Stage of

construction

of each

Block/Tower,

Floor wise

Single Block

Corridor Tiling Work ‐ 1st to 12th floor corridor tiling work completed.

Handrail ‐ Staircase ‐ 1, 2, 3 & 4 ‐ Stilt to Terrace Floor Work

Completed

Kitchen Platform ‐ Completed

Joineries ‐ Upto 11th floor completed

Plumbing ‐ Toilets water supply works ‐ 1st to 12th floor work

Completed.

Sewerage Ling Works ‐1st to 12th floor work completed.

Electrical ‐ Fixing of Conduits ‐ 1st to 12th floor completed.

Shaft 1, 2, 3 – Hydrant Valve riser work - Completed

Staircase Fire door Upto 12th floor completed

PA System & Fire alarm conduits Completed

External Hydrant Pipe line 100 % Completed

2nd Putty ‐ 1st to 12th floor 1st coat putty work completed.

Out of 4 lift, 1 Lift 100 % Completed , 1 Test &

Commissioning Pending , balance 2 lift Work In Progress

2

Status of

common

Amenities for

each

Block/Tower,

Item wise

Single

Block

Swimming Pool & Club House ‐ Structural & Block work

completed, Finishing work is in progress.

Stilt floor Plumbing Work Completed, Electrical 75 %

Completed

Stilt floor Fire Fighting – 100 % Completed

Compound Wall – Completed

East Side Security Room- 100% Completed

South Side Security Room 70 % Completed Balance Work

in Progress

West Side Road Work - Completed

North Side Road Work – 80 % Completed

South Side Road Work - Work In Progress

East Side Road Work - Work In Progress

C. Details of Clearances

1. Completion Certificate No. ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (only CC No. in Text Format)

2. Compliance Report, if any (Kindly Specify) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)

3. Annual Audit Report of Special Account in Form 7 ‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)

D. Latest Photo with Date (Atleast from 2 angles) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)

Note: Report the above particulars under “Registered Projects” in www.tnrera.in

Reg. No.: TN/02/Building/0036/2017

PROJECT STATUS REPORT

JANUARY- 2020

Lemongraz @ Ambattur

Type Area in Sq ft No of Apt’sNo. of Apt’s

Booked

2BHK 1047 to 1053 61 Nos 56

3BHK (Medium) 1263 to 1295 30 Nos 22

3BHK (Large) 1493 to 1498 28 Nos 25

Duplex 2120 to 2567 6 Nos 3

2BHK with PT 1203 to 1914 4 Nos 1

Total 129 107

Car park Details No. of Lots

Booked

Total No Of Car Park Provided 136 Nos 100

Covered Car Park 49 Nos 42

Surface Car Park 80 Nos 67

Visitor Car Park 7 Nos -

Project Details

FLOOR STRUCTURAL BLOCKWORK PLASTERING (Internal)

STILT 100% 100% 100%

1ST FLOOR 100% 100% 100%

2ND FLOOR 100% 100% 100%

3RD FLOOR 100% 100% 100%

4TH FLOOR 100% 100% 100%

5TH FLOOR 100% 100% 100%

6TH FLOOR 100% 100% 100%

7TH FLOOR 100% 100% 100%

8TH FLOOR 100% 100% 100%

9TH FLOOR 100% 100% 100%

10TH FLOOR 100% 100% 100%

11TH FLOOR 100% 100% 100%

12TH FLOOR 100% 100% 100%

TERRACE FLOOR 100% 100% 100%

Progress Status

FLOOR STRUCTURAL BLOCKWORK FINISHES REMARKS

CLUB HOUSE 100% 100% 85%

SWIMMING POOL 100% 100% 70%

AMENITIES

Progress Status

ACTIVITY PROGRESS STATUS

STRUCTURE WORK (PERGOLA): Pergola 5, 6, 7 – 100 % Completed

Pergola 3, 4 – 100 % Completed

Pergola 1, 2 – 100 % Completed

PARAPET WALL: Pour 1 – 100 % Completed

Pour 2 – 100 % Completed

PLASTERING (External): East, South & West sides of the building – 100 % Completed

North side of the building – 100 % Completed

PLASTERING (Ceiling): 1st to Terrace Floor – 100 % Completed

WATERPROOFING WORKS: 1st to 12th Floor – 100% Completed

PUTTY – 2nd COAT 1st to 12th Floor – 100% Completed

TILING WORKS 1st to 12th Floor – 100% Completed

HANDRAILING Staircase 1,2,3 & 4 – 1st to 12th Floor – 100 % Completed

KITCHEN PLATFORM FIXING: 1st to 12th -100 % Completed

Progress Status

ACTIVITY PROGRESS STATUS

UG SUMP – COVER SLAB Completed

FIXING OF DOORS 1 to 11th Floor – 100 % Completed, 12TH Floor 90 % Completed

EXTERNAL WORKS

Compound Wall Completed

Security Room East Side Security Room- 100% Completed

South Side Security Room 70 % Completed Balance Work in Progress

Road Work • West Side Road Work - Completed

• North Side Road Work – 80 % Completed

• South Side Road Work - Work In Progress

• East Side Road Work - Work In Progress

Progress Status

ACTIVITY PROGRESS STATUS

PLUMBING:

Toilet Water supply Works Upto 12th Floor - Completed

Sewerage line works Upto 12th Floor - Completed

ELECTRICAL:

Fixing of Conduits Upto 12th Floor - Completed

Wiring Work Upto 4th Floor - Completed

FIRE FIGHTING: Shaft 1, 2, 3 – Hydrant Valve riser work - Completed

Staircase Fire door Upto 12th floor completed

PA System & Fire alarm conduits Completed

Terrace – Fire Hydrant pipe line Completed

Pump Room- Erection Completed, Testing & Commissioning Work In Progress

External Hydrant Pipe line 100 % Completed

INSTALLATION OF LIFTS: Out of 4 lift, 1 Lift 100 % Completed , 1 Test & Commissioning Pending , balance 2 lift Work In Progress

STILT FLOOR Plumbing Work Completed, Electrical 75 % Completed

Fire Fighting – 100 % Completed

Progress Status

East Side Elevation

Structural work up to 12th

floor has been completed.

Block work up to 12th floor Completed

Internal Plastering work up to 12th floor Completed

External plastering 100 % completed.

Electrical/Plumbing works Completed

West Side Elevation

Structural work up to 12th

floor has been completed.

Block work up to 12th floor Completed

Internal Plastering work up to 12th floor Completed

External plastering 100 % completed.

Electrical/Plumbing works Completed

North Side Elevation

Structural work up to 12th

floor has been completed.

Block work up to 12th floor Completed

Internal Plastering work up to 12th floor Completed

External plastering 100 % completed.

Electrical/Plumbing work Completed

South Side Elevation

Structural work up to 12th

floor has been completed.

Block work up to 12th floor Completed

Internal Plastering work up to 12th floor Completed

External plastering 100 % completed.

Electrical/Plumbing works in progress.

1st FLOOR

1st FLOOR :

Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has been

completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed

2nd FLOOR

Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been

completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has

been completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed

2nd FLOOR :

3rd FLOOR

Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been

completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has

been completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed

3rd FLOOR :

4th FLOOR

Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been

completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has

been completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed .

4th FLOOR :

5th FLOOR

Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been

completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has

been completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed

5th FLOOR :

6th FLOOR

Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has been

completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed

6th FLOOR :

Upto 12th FLOOR

Structural work has been completed.

Block work has been completed. Plastering work has been

completed. Ceiling plastering has been

completedWaterproofing work has been

completed Tiling work has been completed.Water supply pipeline works has

been completed. Kitchen Platform work has been

completed. Hand railing has been completed. Putty 2nd has been completed

7th FLOOR :

TERRACE FLOOR

Terrace FLOOR :

Block work has been completed

Parapet block work has been completed

Plastering work has been completed

Pergola Work has been completed .

Waterproofing work has been completed

MEP has been completed

TERRACE FLOOR

Terrace FLOOR :

Block work has been completed

Parapet block work has been completed

Plastering work has been completed

Pergola Work has been completed .

Waterproofing work has been completed

MEP work has been completed

TERRACE FLOOR

Terrace FLOOR :

Block work has been completed

Parapet block work has been completed

Plastering work has been completed

Pergola Work has been completed .

Waterproofing work has been completed

MEP work has been completed

AMENITIES

AMENITIES - Swimming Pool :

Structural work has been completed.

Block work has been completed.

Water proofing work is in progress.

AMENITIES

AMENITIES - Swimming Pool :

Structural work has been completed.

Block work has been completed.

Water proofing work is in progress.

AMENITIES

AMENITIES – CLUB HOUSE :

Structural work has been completed.

Block work has been completed.

Plastering work has been completed.

Primer painting work has been completed.

Interior Work in Progress

AMENITIESExternal Development Work

Compound Wall – Completed

East Side Security Room- 100% Completed

South Side Security Room 70 % Completed Balance Work in Progress

West Side Road Work - Completed

North Side Road Work – 80 % Completed

South Side Road Work - Work In Progress

East Side Road Work - Work In Progress

AMENITIESExternal Development Works

Compound Wall – Completed

East Side Security Room- 100% Completed

South Side Security Room 70 % Completed Balance Work in Progress

West Side Road Work - Completed

North Side Road Work – 80 % Completed

South Side Road Work - Work In Progress

East Side Road Work - Work In Progress