PROSSER PUMP

Long Beach Fire Department

BASIC SET-UP

ComponentsMain dewatering pumpJunction boxAttached power cordAdditional extention cord

BASIC SET-UP

Main unitThe pump can move 300gpm and pump to a height of 50 feet.3” hose with 2 1/2 couplings are used to move water.A knotted rope is used for lowering lowering unit.

BASIC SET-UP

Junction boxHas a handle for the on/ off switch.The junction box also has a 10 ‘ cord to plug in to the outlets on the fireboat and a 50’ cord that is attached to the main power unit.Operations extending past 50’, the 100’ extension cord can be used.

BASIC SET-UP

100’ extension cord is separate from the main pump and is hung in the equipment room.

Basic Set-up

The port outlet and circuit breaker panel are located on the portside bulkhead behind the door leading to the engine room.

Proser Pump Panel

Once the breaker is turned on, the test light will blink red and must be reset. You must hit the reset button and the light will switch and show a solid green light and the pump can be activated.

The 30A 240V outlet is only used for our prosser pump connector. Note the 4-pronged system...

30A 125V will not work...

The starboard outlet is located just outside the pilot house

Once the breaker is turned on, the test light will blink red and must be reset. You must hit the reset button and the light will switch and show a solid green light and the pump can be activated.

The circuit breaker for the starboard connection it located in the pilot house, on the electrical panel.