  • Portal RATOL & Rates PreMoCAWANGAN KONTRAK DAN UKUR BAHAN 02.03.2015

    Work Item Unit Overall Average (RM)PAVEMENT WORKSCarriageway and Paved ShoulderRoadbaseSpread, grade and compact roadbase materialcomplying with Type I or Type II grading limits of Table4.3 of the standard specifications.Wet Mix Macadam - 300mm thick

    m2 Location Range (RM) Average (RM) RM 28.96F 28.96 - 28.96 28.96

    PAVEMENT WORKSTREATMENT TO EXISTING PAVEMENTMillingMilling of existing pavement including clean andremove all debris to receive new surface inlay . mmthick.50mm thick

    m2 Location Range (RM) Average (RM) RM 1.00C 1.00 - 1.00 1.00

    PAVEMENT WORKSCarriageway and Paved ShoulderSubbaseSubbase material (CBR > 30 %) complying with TypeC or Type D grading limits of Table 4.1 of the standardspecifications.Cement-Bound Granular Material - 100mm thick

    m2 Location Range (RM) Average (RM) RM 42.57F 42.57 - 42.57 42.57

    PAVEMENT WORKSCarriageway and Paved ShoulderSubbaseSubbase material (CBR > 30 %) complying with TypeC or Type D grading limits of Table 4.1 of the standardspecifications.Granular Material - 250mm thick

    m2 Location Range (RM) Average (RM) RM 7.00F 7.00 - 7.00 7.00

    PAVEMENT WORKSCarriageway and Paved ShoulderRoadbaseSpread, grade and compact roadbase materialcomplying with Type I or Type II grading limits of Table4.3 of the standard specifications.Crushed Aggregate - 250mm thick

    m2 Location Range (RM) Average (RM) RM 16.26C 16.26 - 16.26 16.26

    1 / 5

  • Portal RATOL & Rates PreMoCAWANGAN KONTRAK DAN UKUR BAHAN 02.03.2015

    Work Item Unit Overall Average (RM)PAVEMENT WORKSCarriageway and Paved ShoulderSubbaseSubbase material (CBR > 20%) complying withgrading limits of Table 4.5 of the standardspecificationsSand Sub-base (CBR > 20%) - 200mm thick

    m2 Location Range (RM) Average (RM) RM 12.00F 12.00 - 12.00 12.00

    PAVEMENT WORKSCarriageway and Paved ShoulderSurfacingBituminous MacadamBinder Course BMB 28 - 80 mm thick

    m2 Location Range (RM) Average (RM) RM 35.50F 35.50 - 35.50 35.50

    PAVEMENT WORKSFLEXIBLE PAVEMENTTREATMENT TO EXISTING PAVEMENTRegulationAsphaltic concrete wearing course

    m3 Location Range (RM) Average (RM) RM 473.75C 473.75 - 473.75 473.75

    PAVEMENT WORKSFLEXIBLE PAVEMENTTREATMENT TO EXISTING PAVEMENTRegulationBituminous macadam roadbase

    m3 Location Range (RM) Average (RM) RM 443.88C 443.88 - 443.88 443.88

    PAVEMENT WORKSFLEXIBLE PAVEMENTTREATMENT TO EXISTING PAVEMENTMatch PointScarify of existing pavement including clean andremove all debris to receive new pavement

    m2 Location Range (RM) Average (RM) RM 4.43C 4.43 - 4.43 4.43

    PAVEMENT WORKSFLEXIBLE PAVEMENTTREATMENT TO EXISTING PAVEMENTRegulationAsphaltic concrete binder course

    m3 Location Range (RM) Average (RM) RM 456.73C 456.73 - 456.73 456.73

    PAVEMENT WORKSFLEXIBLE PAVEMENT

    m2 Location Range (RM) Average (RM) RM 0.75

    2 / 5

  • Portal RATOL & Rates PreMoCAWANGAN KONTRAK DAN UKUR BAHAN 02.03.2015

    Work Item Unit Overall Average (RM)NEW PAVEMENTPreparation of FormationPreparation of formation as specified and as directedby the S.O/P.D* for receiving road pavement.

    F 0.75 - 0.75 0.75

    PAVEMENT WORKSCarriageway and Paved ShoulderSubbaseSubbase material (CBR > 20%) complying withgrading limits of Table 4.5 of the standardspecificationsSand Sub-base (CBR > 20%) - 350mm thick

    m2 Location Range (RM) Average (RM) RM 26.60F 26.60 - 26.60 26.60

    PAVEMENT WORKSCarriageway and Paved ShoulderSurfacingAsphaltic ConcreteAsphaltic concrete binder course (ACB-28) - 60mmthick

    m2 Location Range (RM) Average (RM) RM 27.45C 27.45 - 27.45 27.45

    PAVEMENT WORKSNEW PAVEMENTCarriageway and Paved ShoulderSurfacingBituminous Tack Coat

    m2 Location Range (RM) Average (RM) RM 1.22C 1.18 - 1.18 1.18F 0.82 - 1.70 1.26

    PAVEMENT WORKSCarriageway and Paved ShoulderSurfacingAsphaltic ConcreteAsphaltic concrete binder course (ACB-28) - 75mmthick

    m2 Location Range (RM) Average (RM) RM 32.38F 32.38 - 32.38 32.38

    PAVEMENT WORKSCarriageway and Paved ShoulderSurfacingAsphaltic ConcreteAsphaltic concrete binder course (ACB-28) - 70mmthick

    m2 Location Range (RM) Average (RM) RM 33.50F 33.50 - 33.50 33.50

    PAVEMENT WORKS m2 Location Range (RM) Average (RM) RM 26.21

    3 / 5

  • Portal RATOL & Rates PreMoCAWANGAN KONTRAK DAN UKUR BAHAN 02.03.2015

    Work Item Unit Overall Average (RM)Carriageway and Paved ShoulderSurfacingAsphaltic ConcreteAsphaltic concrete wearing course (ACB-28) - 50mmthick

    C 23.71 - 23.71 23.71F 28.70 - 28.70 28.70

    PAVEMENT WORKSNEW PAVEMENTCarriageway and Paved ShoulderSurfacingBituminous Prime Coat

    m2 Location Range (RM) Average (RM) RM 1.72C 1.67 - 1.67 1.67F 1.74 - 1.80 1.77

    4 / 5

  • Portal RATOL & Rates PreMoCAWANGAN KONTRAK DAN UKUR BAHAN 02.03.2015

    NotaSekiranya anda mempunyai sebarang pertanyaan, sila hubungi: Ketua Penolong Pengarah KananBahagian Perolehan dan Khidmat KosCawangan Kontrak dan Ukur BahanIbu Pejabat JKR MalaysiaTingkat 19, Menara Tun Ismail Mohamed AliNo 25, Jalan Raja Laut50582 Kuala Lumpur

    u.p: En Husnan HusinTel: 03-26161111Email: husnan@jkr.gov.my