Remodel Projects Photos by Marvin Dodge

Lucy Phillips Classroom Building Highlights:

• All new heating and air conditioning systems – ducts, air

handler, VAV boxes, pumps, etc.

• All new electrical/data wiring, panels and service

• Addition of fire sprinkler system throughout building

• Virtually complete gutting of the building with all new wall/room construction

• 12 new all-purpose classrooms

• 2 new UEN broadcast classrooms and 1 new conference room

• New and expanded testing center with 125 desks

• Enhanced computer testing with 30 laptop computers complete with lock-down browser

Lucy Phillips Classroom Building Highlights, Cont:

• All classrooms fully enhanced with computer, DVD, projector, 5 point

surround sound, and Elmo

• All new furniture with casters designed to accommodate arranging classrooms for various teaching methods and preferences

• 4 additional faculty offices

• Expanded Information Technology Office space with enhanced security options

• 2nd Floor entrance/exit on the building’s East side

• Modern datacenter with raised floor, state-of-the-art Liebert cooling system, data cabinets, and space for future expansion

• New energy efficient exterior window systems

• New exterior doors with electronic security locks

• Anticipated opening date for classes beginning January 4, 2011

Lucy Phillips – 1st Floor South Wall Demolition

Lucy Phillips – 1st Floor- can you say conduit-new UEN rooms

Lucy Phillips – 1st Floor-Final heating and cooling ducts

Lucy Phillips – 1st Floor-Framing new testing center entrance

Lucy Phillips – 1st Floor-Looking through windows into new testing center

Lucy Phillips – 1st Floor-New testing center-125 seat capacity

Lucy Phillips – 1st Floor-New testing center main entrance and reception area

Lucy Phillips – 2nd Floor-Classroom wall construction

Lucy Phillips – 2nd Floor-North classroom framing

Lucy Phillips – 3rd Floor-Ceiling grid being installed (classroom)

Lucy Phillips – 3rd Floor-Classroom ceiling grid and lighting

Lucy Phillips – 3rd Floor-Datacenter new cabinets

Lucy Phillips – 3rd Floor-Datacenter-new Liebert cooling system

Lucy Phillips – 3rd Floor-hallway ceiling grid and mechanical system

Lucy Phillips – 3rd Floor-installation of light fixtures (classroom)

Lucy Phillips – 3rd Floor-IT Offices-open space with new exterior windows and sprinklers

Lucy Phillips – 3rd Floor-Main Hallway

Lucy Phillips – 3rd Floor-Move in day! New datacenter-server cabinets

Lucy Phillips – 3rd Floor-Move in day! New datacenter

Lucy Phillips – Mechanical Room-New air handler

Lucy Phillips – New ductwork and heat-cool units

Lucy Phillips – New energy efficient exterior windows (north side)

Lucy Phillips – New energy efficient exterior windows (south side)

Lucy Phillips – New main entrance doors

Lucy Phillips – New mechanical systems and fire sprinklers

Richfield Nursing and Business Remodel highlights:

• New registration/student services offices in the Administration

building

• Expanded and remodeled nursing classroom/lab facilities with new counters, sinks, bathroom, observation room, and nurse’s station

• Addition of new nursing classroom

• Consolidation of nursing offices in the Washburn building

• Creation of science lab including gas, air, water, electric and data at each student station

• Creation of lab storage area to include a cadaver for anatomy classes

Richfield Nursing and Business Remodel highlights, continued:

• Remodeled business classrooms including carpet, desks,

chairs, and teaching stations

• Created business conference room for professional student training/presentations

• New offices for business faculty

• Replaced carpeting in all remodeled areas

• Yet to be completed a new student lounge/game room space including offices for student leaders and support staff

SCR-Business classroom remodel

SCR-Faculty office remodel

SCR-New biology and chemistry lab

SCR-New biology and chemistry lab

SCR-New biology and chemistry lab

SCR-New biology and chemistry lab

SCR-New biology and chemistry lab

SCR-New biology and chemistry lab

SCR-New nursing classroom lab

SCR-New nursing classroom lab

SCR-New registration and student services offices

SCR-Nursing classroom remodel

SCR-Nursing lab space

SCR-Nursing lab space