ROUTE 630 DIVERGING DIAMOND INTERCHANGE

Virginia Department of Transportation

Contract Value and DatesContract Value:$99,949,969.50

Start of Construction:Summer 2017

Final Completion Date: July 31, 202090 Day Incentive of $12,000/day

Virginia Department of Transportation

5

Project LocationNorth

South

WIDENING

INTERCHANGE

Project Highlights

• Interstate 95 at Exit 140 (Courthouse Road) • Diverging Diamond Interchange design• Moves Courthouse Road and Route 1 intersection south to

Hospital Center Boulevard• Wider Courthouse Road with more vehicle capacity• Commuter lot moves east of I-95

• Courthouse Road Widening• Widens road to 4 lanes from Cedar Lane to Ramoth Church

Road and Winding Creek Road• New traffic signals at:

• Ramoth Church and Winding Creek roads• Colonial Forge High School and Liberty Knolls entrance

Traffic Counts in 2017I-95 at Exit 140: 134,000 vehicles a dayRt. 1 traffic: 14,000 vehicles a day

7

Courthouse Road from Rt. 1 to I-95:17,000 vehicles a dayCourthouse Road from I-95 to Shelton Shop Road:10,000 vehicles a day

Typical Section:Courthouse Road after

Widening

• Median may be grass or concrete • 5 foot sidewalk to be built south of Courthouse Road near Colonial

Forge High School

9

Exit 140 Diverging Diamond Interchange

10

New Park & Ride Lots

11

Overall Project ScheduleMilestone Date

Courthouse Road 4-lane section

complete

December 20, 2019

Courthouse Road widening complete

July 2020

Final Park & Ride commuter lots open east of I-95

July 2020

New Exit 140 diverging diamond interchange complete

July 2020

I-95 SOUTHBOUND RAPPAHANNOCK RIVER CROSSING

UPC 101595 – Design Build Contract with Wagman Heavy Civil

Virginia Department of Transportation

Contract Value and DatesContract Value:$101,608,779.00

Planned Start of Construction:September 28, 2018

Final Completion Date: May 26, 2022 w/90 Day Incentive of $20,000/day

Interim Completion Milestone for Bridges over Route 17: September 15, 2021 w/30 Day Incentive of $16,666/day

Virginia Department of Transportation

• Approx. Exit 133 to Exit 130

• Rappahannock River Crossing in Median

• Three new GP lanes in median with interchange ramp modifications.

• Replaces existing Structural deficient SB and NB I-95 Bridges over Route 17.

Virginia Department of Transportation

Project Limits and Scope

VTCA DISTRICT DIALOG 2018MICHELLE A. SHROPSHIRE, P.E.ADE - PROJECT DEVELOPMENT

Develop a corridor wide transportation solution that:• Reduces congestion• Provides additional travel choices• Improves travel predictability• Improves roadway safety

Virginia Department of Transportation

I-95 Express Lanes Fredericksburg Extension (Fred Ex) -Purpose and Need

Virginia Department of Transportation

I-95 Express Lanes Fredericksburg Extension (Fred Ex)

Virginia Department of Transportation

I-95 Express Lanes Fredericksburg Extension (Fred Ex) -Scope

• Fully funded by Transurban• Extends I-95 Express Lanes 10 miles south to

Route 17 interchange• Two reversible lanes – tolled facility• Connects with I-95 Rappahannock River Crossing

projects• Replaces American Legion and Truslow Road

overpasses• New access at Route 17, Courthouse Road, and

Russell Road at Quantico interchanges

Virginia Department of Transportation

I-95 Express Lanes Fredericksburg Extension (Fred Ex) -Typical Section

Virginia Department of Transportation

I-95 at US Route 17 (Exit 133)

Virginia Department of Transportation

I-95 at Courthouse Road (Exit 140)

Virginia Department of Transportation

I-95 at Russell Road (Exit 148)

Virginia Department of Transportation

I-95 Express Lanes Fredericksburg Extension (Fred Ex) –Schedule

Milestone DateIssue RFQ January 17, 2018Issue RFP March 27, 2018Anticipated Technical Proposal Due Date

September 2018

Anticipated Price Proposal Due Date October 2018Anticipated Design-Build Contract Execution

January 2019

Anticipated Service Commencement October 2022Anticipated Final Completion April 2023

Virginia Department of Transportation

I-95 Rappahannock River Crossing - Northbound

Type:Design-Build Procurement

Project Budget:$132,000,000

Anticipated RFQ Advertisement:Fall 2018

Recommended