RSRDC
UNIT-IV, JAIPUR
ORGANISATION CHART OF RSRDC UNIT –IV, JAIPUR
Financial Work Load in Unit-IV, JaipurS. No.
Name of Work Client Deptt. A& F Sanction Expenditure till date
Balance Work
1. ARE –Sh.R. K. Vijay
1 ROB Dausa PWD Raj. 1000.00 129.00 871.00
2. ARE –Sh. S.K. Shukla
1 ROB Gangapur PWD Raj. 1000.00 653.24 346.76
2 Police line & ADM Block Karauli Home deptt 295.50 158.50 137.00
3 Jail Building Karauli Home deptt 311.11 247.79 63.32
3. ARE –Sh. M.K. Saini
1 112 LSQ at RPA Home deptt 654.00 549.10 104.90
4. ARE- Sh. S.S. Mathur
1 24 LSQ & 12 USQ Banipark Home deptt 288.76 84.63 204.13
2 12 USQ Pratapnagar Home deptt 120.58 103.57 17.01
5. ARE-Sh. Surendra Singh
1 12 USQ Mansarovar Home deptt 119.57 97.42 22.15
Total 3789.52 2023.25 1766.27
Rs. In Lacs
Corporate Bhawan, JAIPUR
Completion Cost – Rs. 10.00 Crs.
Inaugurated by Hon’ble Minister of Corporate Affairs on 22.02.09.
Important Works Completed during last 5 years
New Hospital Block,Chark Bhawan, JAIPUR
Completion Cost – Rs. 9.10 Crs.
Inaugurated by Hon’ble Chief Minister Rajasthan on 30.03.2008
Important Works Completed during last 5 years
Double storey Basement Parking, SMS hospital, JAIPUR
Completion Cost – Rs. 5.90 Crs.
Inaugurated by Hon’ble Chief Minister Rajasthan on 08.12.2007
Important Works Completed during last 5 years
12 nos LSQ at Shiprapath Thana, JAIPUR
Completion Cost – Rs. 70.24 lacs
Important Works Completed during last 5 years
POLICE HOUSING SCHEME
No. of Quarters : 112 Nos. LSQ
Total Cost : Rs. 654.00 lacs
Location : RPA Shastri Nagar
Date of Start : 01.03.08
Stipulated Date of Completion : 31.01.09
Expenditure till Date : 549.10 lacs
Likely Completion date : 15.12.09
Bottlenecks if any : Electric work & water supply from sousce to be connected
POLICE HOUSING SCHEME
No. of Quarters : 24 Nos. LSQ & 12 Nos USq
Total Cost : Rs. 288.76 lacs
Location : Banipark Thana campus, Jaipur
Date of Start : 19.09.08
Stipulated Date of Completion : 18.06.09
Expenditure till Date : 84.63 lacs
Likely Completion date : USQ will completed 31.12.09 12 nos LSQ 31.03.03
Bottlenecks if any : Land for 12 nos USQ allotted on 23.10.08 & order of 12 nos LSQ given on 03.06.09 and land for 12. LSQ still awaiting
POLICE HOUSING SCHEME
No. of Quarters : 196 Nos. LSQ
Total Cost : Rs.311.11 lacs
Location : Jail Building Karauli
Date of Start : 7.12.06
Stipulated Date of Completion : 06.11.07
Expenditure till Date : Rs. 247.79 lacs
Likely Completion date : 30.12.09
Bottlenecks if any : water supply line to be provided & water supply shall be provided by PHED after laying 4.00 Km length pipe line from Karauli so revised estimate submitted for Rs. 428.00 lacs by PHED
POLICE HOUSING SCHEME
No. of Quarters : Adm Block, 100 men barracks, 4 nos LSQ & 2 nos USQ
Total Cost : Rs. 258.50 lacs
Location : Police line and Adm Block Karauli
Date of Start : 29.12.07
Stipulated Date of Completion : 28.11.08
Expenditure till Date : Rs. 158.50 lacs
Likely Completion date : 30.01.10
Bottlenecks if any : water supply shall be provided by PHED after laying 4.00 Km length pipe line from Karauli
POLICE HOUSING SCHEME
No. of Quarters : 12 nos USQ
Total Cost : Rs 119.57 lacs
Location : Mansarovar Thana, Jaipur
Date of Start : 07.07.08
Stipulated Date of Completion : 06.04.09
Expenditure till Date : Rs. 97.42 lacs
Likely Completion date : 15.12.09
Bottlenecks if any :
POLICE HOUSING SCHEME
No. of Quarters : 12 Nos. USQ
Total Cost : Rs. 120.58 lacs
Location : Pratapnagar Thana campus, Jaipur
Date of Start : 10.09.08
Stipulated Date of Completion : 09.06.09
Expenditure till Date : Rs. 103.51 lacs
Likely Completion date : 15.12.09
Bottlenecks if any :
1. Name of Work : ROB DausaTotal Cost : 10.00 CroresLocation : Dausa cityDate of Start : 2.09.08Stipulated Date of Completion : 24.09.10Expenditure till Date : 129.00 lacsLikely Completion date : December -10Bottlenecks if any : Estimate was Revised due to increasing number of
viaduct as per demand of public representative. Revised estimate of Rs. 2020.00 lacs send to
CE PWD vide Addl. Chief PWD Zone – I, Jaipur letter no 2330 dt 5.11.09
Note: Bar Chart for complete work shall be prepared after receiving of Revised A&F sanction
2. Construction of ROB GangapurTotal Cost : 10.00 CroresLocation : Gangapur cityDate of Start : 1.04.08Stipulated Date of Completion : 28.02.09Expenditure till Date : 129.00 lacsLikely Completion date : April -10Bottlenecks if any : Estimate was Revised as bearing capacity is less to
provide masonry retaining wall so RCC wall is proposed. Revised estimate of Rs. 1676.00 lacs send to CE PWD vide Addl. Chief PWD
Zone – II, Jaipur letter no 2689 dt 27.10.09Note: Bar Chart for complete work shall be prepared after receiving of
Revised A&F sanction
Recommended