Site Report Poroton Home

Preview:

DESCRIPTION

Site Report Poroton Home. to Building shell – in record time. In record time to the complete building shell. Location: Trier Outside wall: ThermoPlan T10 Inside wall: Planziegel Hlz Incl. special bricks Team: 3 workers (1 master craftsman, 2 assistant ) - PowerPoint PPT Presentation

Citation preview

Site ReportPoroton Home

to Building shell – in record time

In record time to the complete building shell

•Location: Trier•Outside wall: ThermoPlan T10•Inside wall: Planziegel Hlz•Incl. special bricks

•Team: 3 workers (1 master craftsman, 2

assistant)•Constr. period: 5 days for the complete

building shell.

The bottom slab is casted

The first delivery

Professional discharging

The second delivery... Everything has to be at it‘s place.

The first layer

After 4 hours , the first layer is ready

Now, the plan-bricks have to be worked up

Brick after brick

Some hours later-The building is growing fast

The result of one day

The next day - The inside walls

Nearly ready

After 30 hours with 3 workers

After 30 hours with 3 workers

During the time lag of ceiling delivering – the garage was

built

Bricks for the top floor

Again – the first layer is ready

Exact plans allowed the preparation of the bricks for the pitch

Usage of U-Blocks for the ring armature

The ring armature encloses the masonry

Some details

Working with concrete is finished

Inside walls in top floor

Now, the truss can be constructed

Craftsmanship – just great

Insulation at the ring armature....

Finished

The result of 120 hours work

FinallyThe complete building shell was finished after 5 days.

-With 1 craftsman and 2 helpers -Top quality, 100% brick

A brickhouse makes you happy