State Route 58 Hinkley Expressway Project
Project Overview
Batch Plant Location:
For more information about this project, please go to cal-trans8.info for news release/commuter alerts.
Follow us on Twitter at www.twitter.com/caltrans8.
California Department of Transportation San Bernardino County, California District 8 — SBD — SR58 — Post Mile 22.2 to 31.1 March 2016
The California Department of Transportation (Caltrans) project to widen a portion of State Route 58 from a two-lane conventional high-way to a four-lane expressway, is now in the construction phase. The improvements to State Route 58 extend from approximately 2.8 miles west of Hidden River Road to approxi-mately 0.7 miles east of Lenwood Road, in and around the unincorporated Community of Hin-kley, in San Bernardino County. The express-way would include: 12-foot standard trav-eled way lanes; 10-foot standard shoulder widths; and a 78-foot-wide median.
Two interchanges will be constructed; one at Hinkley Road and the other at Lenwood Road. This realigned roadway would be con-structed on a fill section (elevated sections of a roadway).
Start Concrete Paving New Hwy 58 - April 2016
New Batch Plant - April 2016
Complete import of fill - April 2016
Open Hinkley Road - Mid-July 2016
Open Lenwood Road - February 2017
Open New Hwy 58 Expressway - November 2016
Permanent Closure of Existing Hwy 58 to Through Traffic (W/o Valley View Rd) - November 2016
Start Asphalt Overlay on Existing Hwy 58 - November 2016
Finish Asphalt Overlay on Existing Hwy 58 - December 2016
Open Lenwood WB Exit Ramp - February 2017
Planned Construction Duration - Early 2017
Public Information Officer
Philip Havins
(909) 383-6799
philip.havins@dot.ca.gov
Resident Engineer
Shaine Shahidi
Project Manager
Jim Robinson
http://www.dot.ca.gov/dist8/Project-SR-58-Hinkley.html
Project Construction Schedule*
Project Contacts
*Please note that the above dates are initial estimates and subject to change through out the duration of construction. Project schedule
updates will be available from Caltrans project contacts.