Data UkuranUtamaKapal :

Type Kapal : General Cargo

Length Between Perpendicular ( LPP ) : 96,00 m

Breadth ( B ) : 16,20 m

Depth ( H ) : 7,80 m

Draught ( T ) : 5,60 m

Coefficient Block ( CB ) : 0,67 m

Data Penunjang

z(vertical distance of the structure's load centre above base line ): 7,80 muntuk menghitung

beban geladak cuaca

CRW( service range coefficient ) : 1 ( for unlimited service range )

Co ( Wave Coefficient ) for 90 ≤ L ≤ 300 m : [ 10,75 – (300−𝐿

100 )1,5 ] . CRW

:[ 10,75 – (300−96

100 )1,5 ] . 1

:[ 10,75 – (204

100 )1,5 ] . 1

: [ 10,75 – ( 2,04 )1,5 ] . 1

: [ 10,75 – ( 2,91 )] . 1

: 7,83

CL( Length Coefficient ) : 1 ( for L ≥ 90 m )

CD : 1 ( In Midship )

CF : 1 ( In Midship )

PERHITUNGAN MENGGUNAKAN SISTEM KONSTRUKSI MELINTANG

I. PERHITUNGAN BEBAN (Design Loads )Section IV Rules for Hull BKI 2014

1. Perhitungan Beban Geladak Cuaca (Load on Weather Decks) Pada Tengah

Kapal

( Section IV A,B Rules for Hull Biro Klasifikasi Indonesia 2014 )

PD = Po 20 .𝑇

( 10+𝑧−𝑇)𝐻CD[kN/m2]

Sebelum menghitung semua perhitungan maka harus menentukan Po (basic

external dynamic load ) terlebih dahulu karena nilaif setiap Po berbeda

karena tergantung penggunaannya

Po 1[use f = 1 for plate panels of the outer hull (shell plating, weather

decks)]

Po 1 = 2,1 . ( CB + 0,7 ) . Co CL f

= 2,1 . ( 0,67 + 0,7 ) . 7,83 .1 .1

= 2,1 . 1,37 . 7,83

= 22,53[ kN/m2]

Po 2[use f=0,75 for secondary stiffening members of the outer hull

(frames, deck beams) ]

Po 2 = 2,1 . ( CB + 0,7 ) . Co CL f

= 2,1 . ( 0,67 + 0,7 ) . 7,83 .1 .0,75

= 2,1 . 1,37 . 7,83 . 0,75

= 16,89[ kN/m2]

Po 3[0,60 for girders and girder systems of the outer hull

(web frames, stringers, grillage systems) ]

Po 3 = 2,1 . ( CB + 0,7 ) . Co CL f

= 2,1 . ( 0,67 + 0,7 ) . 7,83 .1 .0,60

= 2,1 . 1,37 . 7,83 . 0,60

= 13,51[ kN/m2]

a. Bebangeladakcuacauntukmenghitung plat geladak ( deck plate )

PD1= Po120 .𝑇

( 10+𝑧−𝑇)𝐻 CD [ kN/m2]

PD1=22,53 . 20 . 5,60

( 10+7,80−5,60)7,8. 1 [ kN/m2]

PD1=22,53 . 112

95,16. 1 [ kN/m2]

PD1=22,53 . 1,17. 1 [ kN/m2]

PD1=26,51 [ kN/m2]

b. Beban geladak cuaca untuk menghitung balok geladak ( deck beam)

PD2= Po2 20 .𝑇

( 10+𝑧−𝑇)𝐻 CD [ kN/m2]

PD2=16,89 . 20 . 5,60

( 10+7,80−5,60)7,8. 1 [ kN/m2]

PD2=16,89 . 112

95,16. 1 [ kN/m2]

PD2=16,89 . 1,17. 1 [ kN/m2]

PD2=19,76 [ kN/m2]

c. Beban geladak cuaca untuk menghitung balok geladak kekuatan

(strong beam) dan Penumpu ( girder )

PD3= Po320 .𝑇

( 10+𝑧−𝑇)𝐻 CD [ kN/m2]

PD 3 =13,51 . 20 . 5,60

( 10+7,80−5,60)7,8. 1 [ kN/m2]

PD3=13,51 . 112

95,16. 1 [ kN/m2]

PD3=13,51 . 1,17. 1 [ kN/m2]

PD3=15,80 [ kN/m2]

2. Bebansisi ( load on ship side ) Section IV B Rules for Hull BKI 2014

2.1 Perhitungan bebansisidibawahgaris air pada tengah kapal

(For elements the load centre of which is located below load waterline )

PS= 10 ( T – z ) + Po . CF( 1 + 𝑧

𝑇 )[ kN/m2]

Use z = 1

3 T m

= 1

3 . 5,6 m

= 1,86 m

a. Beban sisi dibawah garis air untuk menghitung tebal pelat sisi

(side plate)

PS 1= 10 .( T – z ) + Po 1 . CF( 1 + 𝑧

𝑇 ) [ kN/m2]

PS 1= 10 .( 5,6 – 2,6 ) + 22,53 . 1 ( 1 + 1,86

5,6 ) [ kN/m2]

PS 1= 10 . 3 + 22,53 .1 . 1,33 [ kN/m2]

PS 1= 30 + 29,96 [ kN/m2]

PS 1 = 59,96 [ kN/m2]

b. Beban sisi dibawah garis air untuk menghitung gading-gading utama

(mainframe)

PS2= 10 .( T – z ) + Po 2 . CF( 1 + 𝑧

𝑇 ) [ kN/m2]

PS2= 10 .( 5,6 – 2,6 ) + 16,89 . 1 ( 1 + 1,86

5,6 ) [ kN/m2]

PS2= 10 .3 + 16,89 .1 . 1,33 [ kN/m2]

PS 2= 30 + 22,46 [ kN/m2]

PS 2= 52,46 [ kN/m2]

c. Bebansisidibawahgaris air untukmenghitunggadingbesar (web frame)

dansentasisi ( side stringer )

PS 3= 10 .( T – z ) + Po 3 . CF( 1 + 𝑧

𝑇 ) [ kN/m2]

PS 3= 10 .( 5,6 – 2,6 ) + 13,51 . 1 ( 1 + 1,86

5,6 ) [ kN/m2]

PS 3= 10 .3 + 13,51 .1 . 1,33 [ kN/m2]

PS 3= 30 + 17,96 [ kN/m2]

PS 3 = 47,96 [ kN/m2]

2.2 Perhitungan beban sisi diatas garis air pada tengah kapal

(For elements the load centre of which is located above load waterline )

PS= Po .CF.20

10+ 𝑧 − 𝑇[ kN/m2]

use z = T + 1

2 ( H – T ) m

= 5,6+ 7,8−5,6

2 m

= 5,6 + 1,1 m

= 6,7 m

a. Beban sisi diatas garis air untuk menghitung tebal plat sisi (side plate)

PS1= Po 1 . CF.20

10+ 𝑧 − 𝑇 [ kN/m2]

PS1= 22,53 . 1.20

10 + 6,7 − 5,6 [ kN/m2]

PS 1 = 22,53 . 1 . . 20

11,1 [ kN/m2]

PS1= 22,53 . 1.1,80 [ kN/m2]

PS1=40,59 [ kN/m2]

3. Perhitungan Beban(Load on the ship’s bottom) Section IV B BKI 2014

3.1 Perhitungan beban alas pada tengah kapal

PB = 10 . T + Po . CF[ kN/m2]

a. Beban alas untuk menghitung plat alas ( bottom plate )

PB 1 = 10 . T + Po 1 . CF [ kN/m2]

PB 1 = 10 . 5,6 + 22,53 . 1 [ kN/m2]

PB 1 = 56 + 22,53 [ kN/m2]

PB 1 = 78,53 [ kN/m2]

b. Beban alas untuk menghitung gading alas ( bottom frame )

dan Penegar ( stiffner )

PB 2 = 10 . T + Po 2 . CF [ kN/m2]

PB 2 = 10 . 5,6 + 16,89 . 1 [ kN/m2]

PB 2= 56 + 16,89 [ kN/m2]

PB 2 = 72,89 [ kN/m2]

3.2 Beban alas dalam pada daerah tengah kapal

PI= 10 .( T – hDB ) [ kN/m2]

hDB = 350 + ( 45 . B ) mm

hDB = 350 + ( 45 . 16,2 ) mm

hDB = 350 + 729 mm

hDB = 1079 mm ≈ 1080 mm

hDB = 1,08 m

a. Beban alas dalam untuk menghitung plat alas dalam (inner bottom plate)

PI1= 10 .( T – hDB ) [ kN/m2]

PI 1 = 10 .( 5,6 – 1,08 ) [ kN/m2]

PI 1 = 10 . 4,52 [ kN/m2]

PI 1 = 45,2 [ kN/m2]

b. Beban alas dalam untuk menghitung gading balik (reserved frame )

PI2= 10 .( T – hDB ) [ kN/m2]

PI 2 = 10 .( 5,6 – 1,08 ) [ kN/m2]

PI 2 = 10 . 4,52 [ kN/m2]

PI 2 = 45,2 [ kN/m2]

II. PERHITUNGAN TEBAL PLAT (Shell Plating ) Rules for Hull BKI Section VI

Tebal plat geladak kekuatan (streng deck plating) dan plat kulit (shell plating)

pada0,4 L tengah kapal

Jarak gading standart a0= 𝐿

500+ 0,48 m

a0= 96

500+ 0,48 m

a0= 0,19 + 0,48 m

a0= 0,67 m

a0= 670 mm

1. Tebal plat geladak kekuatan tidak boleh kurang dari :

(Section 7 A Rules for Hull 2014 )

tD =1,21 . a .√𝑃𝐷1. 𝐾 + tKmm

tD =1,21 . 0,67 . √26,51. 1 + 1,5 mm

tD =1,21 . 0,67 . 5,14 + 1,5 mm

tD =4,16 + 1,5 mm

tD =5,66 mm

tmin=√𝐿 . 𝑘 mm

tmin=√96 . 1 mm

tmin=9,79 mm

Direncanakan :tmin+ 1,0 mm

:9,79+ 1,0 mm

: 10,79 mm ≈ 11 mm

2. Tebal plat alas ( bottom plate) tidak boleh kurang dari :

(Section 6 B Rules for Hull 2014 )

tB = 1,21 . a .√𝑃𝐵1. 𝐾 + tK mm

tB = 1,21 . 0,67 . √78,53 . 1 + 1,5 mm

tB = 1,21 . 0,67 . 8,86 + 1,5 mm

tB = 7,18 + 1,5 mm

tB = 8,68 mm

tmin=√𝐿 . 𝑘 mm

tmin=√96 . 1 mm

tmin=9,79 mm

Direncanakan :tmin+ 1,5 mm

:9,79+ 1,5 mm

: 11,29 mm ≈ 12 mm

3. Tebal plat bilga (bilge strake)

(Section 6 Rules for Hull 2014 )

tBS= tB = 12 mm

Lebar plat bilga :

b =800 + 5 . Lmm

b = 800 + 5 . 96 mm

b = 800 + 480 mm

b = 1280 mm

4. Tebal plat lunas (flat plate keel)

(Section 6 B Rules for Hull 2014 )

tFK= tB+ 2,0 mm

tFK= 12+ 2,0 mm

tFK= 14 mm

Lebar plat lunas :

b = 800 + 5 . L mm

b = 800 + 5 . 96 mm

b = 800 + 480 mm

b = 1280 mm

5. Tebal plat alas dalam (inner bottom plate) tidak boleh kurang dari :

(Section 6 Rules for Hull 2014 )

ti= 1,21 . a .√𝑃𝑖. 𝐾 + tK mm

ti = 1,21 . 0,67 . √45,2 . 1 + 1,5 mm

ti = 1,21 . 0,67 .6,72 + 1,5 mm

ti =5,45+ 1,5 mm

ti = 6,95 mm ≈ 10 mm

6. Tebal plat sisi (side plate) dibawah garis air tidak boleh kurang dari :

(Section 6 Rules for Hull 2014 )

ts= 1,21 . a .√𝑃𝑠1. 𝐾 + tK mm

ts = 1,21 . 0,67 . √59,96 . 1 + 1,5 mm

ts = 1,21 . 0,67 . 7,74 + 1,5 mm

ts = 6,27 + 1,5 mm

ts = 7,77 mm

tmin=√𝐿 . 𝑘 mm

tmin=√96 . 1 mm

tmin=9,79 mm

Direncanakan :tmin+ 1,5 mm

:9,79+ 1,5 mm

: 11,29 mm ≈ 12 mm

7. Tebal plat sisi diatas garis air

ts 1 = 1,21 . a .√𝑃𝑠1. 𝐾 + tKmm

ts 1 = 1,21 . 0,67 . √40,59 . 1 + 1,5 mm

ts 1 = 1,21 . 0,67 . 6,37 + 1,5 mm

ts 1 = 5,16 + 1,5 mm

ts 1 = 6,66 mm

tmin=√𝐿 . 𝑘 mm

tmin=√96 . 1 mm

tmin=9,79 mm

Direncanakan :tmin+ 1,0 mm

:9,79+ 1,0 mm

: 10,79 mm ≈ 11 mm

8. Tebal plat sisi lajur atas (sheer strake)

tSS =0,5 . ( tD + tS ) mm

= 0,5 . ( 11+ 12 ) mm

= 0,5 . ( 23 ) mm

= 11,5 mm ≈ 12 mm

Lebar plat sisilajuratas:

b = 800 + 5 . L mm

b = 800 + 5 . 96 mm

b = 800 + 480 mm

b = 1280 mm

III. PERHITUNGAN KONSTRUKSI ALAS GANDA (Bottom Structures )

Rules for Hull BKI Section VIII

1. Penumpu Tengah ( Centre Girder ) Section VIII

a. TinggiPenumputengahtidakbolehkurangdari :

h = 45 . B + 350 mm

h = 45 . 16,2 + 350 mm

h = 729 + 350 mm

h = 1079 mm ≈ 1080 mm

b. TebalPenumpu Tengahtidakbolehkurangdari( untuk h ≤ 1200 mm ) :

tm = ℎ

ℎ𝑎 (

100 + 1 ) √𝐾 mm

tm = 1080

1080 (

1080

100 + 1 ) √1 mm

tm = 1 (10,8 + 1 ) 1 mm

tm = 11,8 mm ≈ 12 mm

2. PenumpuSamping ( side girder )

Untuk ½ B ≥ 8 metermenggunakan 2 side girder

a. TebalPenumpusampingtidakbolehkurangdari :

t = ℎ2

120 .ℎ𝑎 . √𝑘mm

t = 1080 2

120 .1080 . √1mm

t = 1166400

129600 . 1 mm

t = 9,0 mm

3. Wrang alas penuh ( solid floor )

a. Tebalwrang alas penuhtidakbolehkurangdari : sec 8

tPF = ( tM– 2,0 ) . √𝑘mm

tPF = ( 12,0– 2,0 ) . √1mm

tPF = ( 10,0 ) . 1 mm

tPF = 10 mm

Karenatidakadakem

iringanpada alas

( rise of floor ) maka

h = ha

Karenatidakadakem

iringanpada alas

( rise of floor ) maka

h = ha

b. Ukuran lubang orang (man hole) dan lubang peringan (lightening hole) pada

wrang alas penuh BKI

Panjang max. l = 0,75 . h mm

= 0,75 . 1080 mm

= 810 mm≈ 750 mm

Tinggi max t = 0,5 . h mm

= 540 mm≈ 500 mm

Diameter =1

3h mm

= 1

3 1080 mm

= 360 mm≈ 300 mm

4. Wrang kedap air (water tight floor)

a. Tebal plat wrang kedap air tidak boleh kurang dari tebal pelat wrang penuh

tWF = tPF = 10 mm

b. Modulus penampang penegar (stiffner) wrang kedap air tidak bolek kurang

dari :

W = 0,55 . a .l2 .P .k cm 3

Dimana :

a = 0,625 m (jarak antara penegar)

P = PB2= 72,89 kN/m2

k = 1

l = hDB = 1,08 m

W = 0,55 . 0,625 .1,082 . 72,89 . 1 cm 3

W = 29,22 cm 3

Ukuran profil penegar direncanakan : L75 x50x 7

5. Wrang terbuka (open floor) BKI Sec. 8

a. Modulus penampang gading alas (bottom frame) tidak boleh kurang dari :

W = n . c .a .l2.p. k cm3

Dimana :

a = jarak antara wrang terbuka = jarak gading = 0,67 meter

P = PB2= beban alas = 72,89 kN/m2

c = 1

l = 3,125 – [ 1,5 ( 0,75.hDB ) ] m

= 3,125 – [ 1,5 ( 0,75 . 1.08 ) ] m

= 3,125 – [ 1,5 ( 0,81 ) ] m

= 3,125 – 1,215 m

= 1,91 m

n = 0,70

k = 1

W = 0,70 . 1 . 0,67 . 1,912. 72,89. 1 cm3

W = 124,71 cm3

Ukuran profil yang direncanakan : L 130x 65x 10

b. Modulus penampang gading balik (reversed frame) tidak boleh kurang dari :

W = n . c .a .l2.p. k cm3

Dimana :

a = jarak antara wrang terbuka = jarak gading = 0,67 meter

P = Pi2= beban alasdalam= 45,2kN/m2

c = 1

l = 3,125 – [ 1,5 ( 0,75.hDB ) ] m

= 3,125 – [ 1,5 ( 0,75 . 1.08 ) ] m

= 3,125 – [ 1,5 ( 0,81 ) ] m

= 3,125 – 1,215 m

= 1,91 m

n = 0,55

k = 1

W = 0,55 . 1 . 0,67 . 1,912.45,2. 1 cm3

W = 60,76 cm3

Ukuran profil yang direncanakan : L 100x 65x 7

IV. PERHITUNGAN GADING-GADING (BKI Sec. 9)

1.Gading-gading Utama (main frames)

Modulus penampang gading utama tidak boleh kurang dari :

WR = n . a .c .l2 .p .cr .k cm3

Dimana :

n = 0,9 – 0,0035 . L = 0,9 – 0,0035 . 96 = 0,57

a = 0,67 m

c = 0,6

l = 0,5 . (H - hDB) = 0,5 . (7,8 - 1,08) = 0,5 . 6,72 = 3,36 m

p =PS2 = beban sisi dibawah garis air untuk gading utama = 52,46kN/ m2

cr = 0,75

k = 1

WR = n . a .c .l2 .p .cr .k cm3

WR = 0,57 . 0,67 . 0,6 . 3,362 .52,46 . 0,75 . 1 cm3

WR = 101,78 cm3

Ukuran profil direncanakan : L 100 x 75 x 11

2. Gading besar (web frame)

Modulus penampang gading besar tidak boleh kurang dari :

W = 0,55 . e. l2 .Ps .n .k cm3

Dimana :

e = 4.a = 4. 0,67 = 2.68 m

11

6720

3360

3360

l = 0,5 . (H - hDB) = 0,5 . (7,8 - 1,08) = 0,5 . 6,72 = 3,36 m

P = Ps3 = 47,96 kN/m2

n = 0,5 ( karena dipasang satu senta sisi )

k = 1

W = 0,55 . e. l2 .Ps .n .k cm3

W = 0,55 . 2,68. 3,362 . 47,96 .0,5 .1 cm3

W = 399,04cm3

Koreksi modulus :

W = 399,04 cm3

tS = 12 mm

Keterangan :

Lebar pelat pengikat atau pelat sisi = ( 40 sampai 50 ) x 𝑡𝑠

Saya ambil 41 x 𝑡𝑠 = 48 x 1,2 = 49,2 mm

Ukuran pelat hadap = 12 x 1

Ukuran pelat bilah = 24 x 1

Ukuran pelat pengikat = 49.2 x 1,2

Koreksi modulus :

Luas pelat hadap (f) = 12 x 1 = 12 cm2

Luas pelat bilah (fs) = 24 x 1 = 24 cm2

Luas pelat pengikat (F) = 49.2 x 1,2 = 59.04 cm2

Koreksi :

f/F = 12/59,04 = 0,2

fs/F = 24/59,04 = 0,4

Maka profil tersebut mempunyai modulus penampang

W = w x f x h cm3

W = 0,288 x 59,04 x 24 = 408,08 cm3

W koreksi > W Perhitungan( 5 ~ 10 )

408,08 cm3 > 399,04 cm3

Ukuran profil direncanakan : T 240 x 10 FP 120 x 10

Dari diagram koordinasi didapatkan w = 0,288

240

120

10

10

V. SENTA SISI (side stringer)

Modulus penampang senta sisi tidak boleh kurang dari :

W = 0,55 . e . l2. Ps . n. k cm3 (BKI Sec. 9)

Dimana :

e = jarak pembebanan =0,5 . (H - hDB) = 0,5 . (7,8 - 1,08) = 0,5 . 6,72 = 3,36 m

l = 4.a = 4. 0,67 = 2.68 m

n = 1

k = 1

P = Ps3 = 47,96 kN/m2

W = 0,55 . 3,36 . 2,682 . 47,96 . 1 . 1 cm3

W = 636.57 cm3

Koreksi modulus :

W = 636,57 cm3

tS = 12 mm

Lebar pelat pengikat atau pelat sisi = ( 40 sampai 50 ) x 𝑡𝑠

Saya ambil 50 x 𝑡𝑠 = 50 x 12 = 600 mm

Ukuran pelat hadap = 14 x 1,2 mm

Ukuran pelat bilah = 28 x 1,2 mm

Ukuran pelat pengikat = 60 x 1,2 mm

3360

3360

e

Koreksi modulus :

Luas pelat hadap (f) = 14x 1,2 = 16,8 cm2

Luas pelat bilah (fs) = 28 x 1,2 = 33,6 cm2

Luas pelat pengikat (F) = 60 x 1,2 = 72 cm2

Koreksi :

𝑓

𝐹 =

16,8

72 = 0,23

𝑓𝑠

𝐹 =

33,6

72 = 0,46

Maka profil tersebut mempunyai modulus penampang

W = w x f x h cm3

W = 0,32 x 72 x 28 = 645,12 cm3

W koreksi > W Perhitungan( 5 ~ 10 )

645,12 cm3 > 636,57 cm3

Ukuran profil direncanakan : T 280 x 12 FP 140x 12

280

12

12

Dari diagram koordinasi didapatkan w = 0,32

140

VI. PERHITUNGAN KONSTRUKSI GELADAK (BKI Sec. 10)

1. Balok geladak (deck beam)

Modulus penampang balok geladak tidak boleh kurang dari :

Wd = c .a .PD2 .l2 .k cm3

Dimana : c = 0,75 untuk beams, girder, dan transverse

a = jarak gading = 0,67 m

p = PD2 = 19,76 [ kN/m2]

L 1 = panjang tak ditumpu = 3,125 M

k = 1,0 faktor material baja

Wd = c .a .PD2 .l2 .k cm3

Wd = 0,75 . 0,67 . 19,76 . (3,125)2 . 1 cm3

Wd = 96,96 cm3

Ukuran profil direncanakan : L 130 x 65 x 8

8

8100

2. Balok geladak kekuatan (strong beam)

Modulus penampang balok geladak kekuatan tidak boleh kurang dari :

W = c x e x l2 x P x k cm³ (BKI Sec.10)

Dimana = c = 0,75 untuk beams, girder, dan transverse

e = 4 x a = 4 x 0,67 = 2,68 M

l = panjang tak ditumpu = 3,125 M

P = PD3= 15,8 [ kN/m2]

K = 1,0faktor material baja

W = c x e x l2 x P x k cm³

W = 0,75 x 2,68 x (3,125 )2 x 15,8 x 1,0 cm³

W = 310,13 cm³

Koreksi modulus :

W = 310,13 𝑐𝑚3

td = 11 mm

Lebar pelat pengikat atau pelat sisi = ( 40 sampai 50 ) x 𝑡𝑑

Saya ambil 40 x 𝑡𝑑 = 40 x 11 = 440 mm

Ukuran pelat hadap =100 x 11 mm

Ukuran pelat bilah =200 x 11 mm

Ukuran pelat pengkat = 440 x 11 mm

Luas pelat hadap (f) = 10cm x 1,1 cm = 11 cm2

Luas pelat bilah (fs) = 20 cm x 1,1 cm = 22 cm2

Luas pelat pengikat (F) = 48 cm x 1,1 cm = 48.4 cm2

Koreksi :

𝑓

𝐹 =

11

48,4 = 0,22

𝑓𝑠

𝐹 =

22

48,4 = 0,45

Sehingga didapatkan W koreksi

W koreksi = w .F .h

= 0.33 . 48,4 cm2 . 20 cm

= 319,44 cm3

W koreksi > W Perhitungan( 5 – 10 )

319,44 cm3 > 310,13 𝑐𝑚3

Ukuran profil direncanakan : T 200 x11 FP 100 x 11

3. Penumpu geladak tengah (center deck girder) dan penumpu geladak samping (side

deck girder)

a. Penumpu geladak tengah

Modulus penampang penumpu geladak tengah tidak boleh kurang dari :

W =c x e x l2 x P x k (cm³)(BKI Sec.10.. .)

Dimana : c = 0,75 untuk beams, girder, dan transverse

l = 4 x a = 4 x 0,67 = 2,68 M

e = lebar pembebanan = 3,125 m

200

11

11

Dari diagram koordinasi didapatkan w = 0,33

100

P = PD3= 15,8 [ kN/m2]

K = 1,0 faktor material baja

W = c x e x l2 x P x k cm³

W = 0,75 x 3,125 x (2,68)2 x 15,8 x 1,0 cm³

W = 265,97 cm³

Koreksi modulus :

W = 265,97 𝑐𝑚3

tD = 11 mm

Lebar pelat pengikat atau pelat sisi = ( 40 sampai 50 ) x 𝑡𝐷

Sayaambil 40 x 𝑡𝐷 = 40 x 11 = 440 mm

Ukuran pelat hadap = 100 x 11 mm

Ukuran pelat bilah = 200 x 11 mm

Ukuran pelat pengkat = 440 x 11 mm

Luas pelat hadap (f) = 10 cm x 1,1 cm = 11 cm2

Luas pelat bilah (fs) = 20 cm x 1,1 cm = 22 cm2

Luas pelat pengikat (F) = 44 cm x 1,1 cm = 48,4 cm2

f/ F = 11cm2/48,4cm2 = 0.22

fs/ F = 22 cm2/48,4 cm2 = 0.45

Sehingga didapatkan W koreksi

W koreksi = w .F .h

= 0.28 . 48,4 cm2 . 20 cm

= 271,04 cm3

W koreksi > W Perhitungan( 5 – 10 )

= 271,04 cm3 > 265,97 cm³

Ukuran profil direncanakan : T 200 x11 FP 100 x 11

Dari diagram didapatkan w = 0.28

200

100

11

11

b. Penumpu geladak samping yang paling dekat dengan CDG( S.D.GD 1)

Modulus penampang penumpu geladak 1 tidak boleh kurang dari :

W = c x e x l2 x P x k (cm³) (BKI Sec.10.. .)

Dimana :c = 0,75 untuk beams, girder, dan transverse

l = 4 x a = 4 x 0,67 = 2,68 M

e = (0,5 . 3,125) + (0,5 . 2,5) = 2,8125 m

P = PD3= 15,8 [ kN/m2]

K = 1,0 faktor material baja

W = c x e x l2 x P x k cm³

W = 0,75 x 2,8125 x (2,68)2 x 15,8 x 1,0 cm³

W = 239,37 cm³

Koreksi modulus :

W = 239,37 cm³

tD= 11 mm

Lebar pelat pengikat atau pelat sisi = ( 40 sampai 50 ) x 𝑡𝐷

Saya ambil 40 x 𝑡𝐷 = 40 x 11 = 440 mm

Ukuran pelat hadap = 80 x 11 mm

Ukuran pelat bilah = 180 x 11 mm

Ukuran pelat pengkat = 440 x 11 mm

1

2

1

2

Luas pelat hadap (f) = 8 cm x 1,1 cm = 8,8 cm2

Luas pelat bilah (fs) = 18 cm x 1,1 cm = 19,8 cm2

Luas pelat pengikat (F) = 44 cm x 1,1 cm = 48,4 cm2

f/ F = 8,8cm2/48,4cm2 = 0.18

fs/ F = 19,8 cm2/48,4 cm2 = 0.40

Sehingga didapatkan W koreksi

W koreksi = w .F .h

= 0.285 . 48,4 cm2 . 18 cm

= 248,29 cm3

W koreksi > W Perhitungan( 5 – 10 )

248,29 cm3 > 239,37 cm³

Ukuran profil direncanakan : T 180 x11 FP 80 x 11

c. Penumpu geladak samping yang paling dekat dengan lambung( S.D.GD 2)

Modulus penampang penumpu geladak 2 tidak boleh kurang dari :

W = c x e x l2 x P x k (cm³) (BKI Sec.10.. .)

Dimana :c = 0,75 untuk beams, girder, dan transverse

l = 4 x a = 4 x 0,67 = 2,68 M

e = 0,5 . 2,5 + 0,5 . 2,475 = 2,4875 m

Dari diagram didapatkan w = 0.285

180

80

11

11

2

2

1

1

P = PD3= 15,8 [ kN/m2]

K = 1,0 faktor material baja

W = c x e x l2 x P x k cm³

W = 0,75 x 2,4875 x (2,68)2 x 15,8 x 1,0 cm³

W = 211,71 cm³

Koreksi modulus :

W = 211,71 cm³

tD= 11

Lebar pelat pengikat atau pelat sisi = ( 40 sampai 50 ) x 𝑡𝐷

Sayaambil 40 x 𝑡𝐷 = 40 x 11 = 440 mm

Ukuran pelat hadap = 80 x 11 mm

Ukuran pelat bilah = 160 x 11 mm

Ukuran pelat pengkat = 440 x 11 mm

Luas pelat hadap (f) = 8 cm x 1,1 cm = 8,8 cm2

Luas pelat bilah (fs) = 16 cm x 1,1 cm = 17,6 cm2

Luas pelat pengikat (F) = 44 cm x 1,1 cm = 48,4 cm2

f/ F = 8,8cm2/48,4cm2 = 0.18

fs/ F = 17,6 cm2/48,4 cm2 = 0.36

Sehingga didapatkan W koreksi

W koreksi = w .F .h

= 0.28 . 48,4 cm2 . 16 cm

= 216,83 cm3

W koreksi > W Perhitungan( 5 – 10 )

216,83 cm3 > 211,71 cm³

Ukuran profil direncanakan : T 180 x11 FP 80 x 11

Dari diagram didapatkan w = 0.28

160

80

11

11

VII. PERHITUNGAN BRACKET

Tebal bracket tidak boleh kurang dari :

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

Panjang lengan bracket tidak boleh kurang dari

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct = √𝑡

𝑡𝑎

ta = Tebal bracket yang telah dihitung

c = 1,2 untuk bracket tanpa flange

= 0,95 untuk bracket dengan flange

W = modulus terkecil

k1 = 1,0

k2 = 0,91

tmin = 6,5 ≈ 7 mm

lmin = 100 mm

tk = 1,5

a. Bracket untuk menguhubungkan main frame dengan plat alas dalam

1. Tebal bracket

Modulus yang dipakai : Wmain frame = 101,78 cm3

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

t = 1,2 . √101,78

1

3 + 1,5 (mm)

t = 7,10 Direncanakan ≈ 8 (mm)

2. Panjang Lengan

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct =√𝑡

𝑡𝑎 (t = t main frame = 11)

= √11

8 (mm)

= 1,375 (mm)

l = 46,2 . √101,78

1

3. √0,91 . 1,375 (mm)

l = 282.93 ≈300 mm

BRACKET 300 X 8

300

300

50

b. Bracket untuk menguhubungkan main frame dengan balok geladak

1. Tebal bracket

Modulus yang dipakai : Wdeckbeam = 96,96 cm3

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

t = 1,2 . √96,96

1

3 + 1,5 (mm)

t = 7,012 Direncanakan ≈8 (mm)

2. Panjang Lengan

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct =√𝑡

𝑡𝑎 (t = t balok geladak = 8)

= √8

8 (mm)

= 1 (mm)

l = 46,2 . √96,96

1

3. √0,91 . 1 (mm)

l = 202,46 mm

BRACKET 200 X 8

200

200

50

180 200

c. Bracket untuk menguhubungkan side deck girder yang paling dekat CDG dengan

balok geladak ( S.D. GD 1 )

1. Tebal bracket

Modulus yang dipakai : Wdeckbeam = 96,96 cm3

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

t = 1,2 . √96,96

1

3 + 1,5 (mm)

t = 7,012 Direncanakan ≈8 (mm)

2. Panjang Lengan

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct =√𝑡

𝑡𝑎 (t = t balok geladak = 8)

= √8

8 (mm)

= 1 (mm)

l = 46,2 . √96,96

1

3. √0,91 . 1 (mm)

l = 202,46 mm

BRACKET 200 X 115 X 8

95

160 200

d. Bracket untuk menguhubungkan side deck girder yang dekat lambung dengan balok

geladak ( S. D. GD 2 )

1. Tebal bracket

Modulus yang dipakai : Wdeckbeam = 96,96 cm3

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

t = 1,2 . √96,96

1

3 + 1,5 (mm)

t = 7,012 Direncanakan ≈8 (mm)

2. Panjang Lengan

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct =√𝑡

𝑡𝑎 (t = t balok geladak = 8)

= √8

8 (mm)

= 1 (mm)

l = 46,2 . √96,96

1

3. √0,91 . 1 (mm)

l = 202,46 𝑚𝑚

BRACKET 200 X 95 X 8

135

200 200

e. Bracket untuk menguhubungkan centre deck girder dengan balok geladak

1. Tebal bracket

Modulus yang dipakai : Wdeckbeam = 96,96 cm3

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

t = 1,2 . √96,96

1

3 + 1,5 (mm)

t = 7,012 Direncanakan ≈8 (mm)

2. Panjang Lengan

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct =√𝑡

𝑡𝑎 (t = t balok geladak = 8)

= √8

8 (mm)

= 1 (mm)

l = 46,2 . √96,96

1

3. √0,91 . 1 (mm)

l = 202,46 𝑚𝑚

BRACKET 200 X 135 X 8

280

f. Bracket untuk menguhubungkan side stringer dengan main frame

1. Tebal bracket

Modulus yang dipakai : Wmain frame = 101,78 cm3

t = 𝑐 . √𝑊

𝑘1

3 + tk (mm)

t = 1,2 . √101,78

1

3 + 1,5 (mm)

t = 7,10 Direncanakan ≈ 8 (mm)

2. Panjang Lengan

l = 46,2 . √𝑊

𝑘1

3. √𝑘2 . ct (mm)

ct =√𝑡

𝑡𝑎 (t = t main frame = 11)

= √11

8 (mm)

= 1,375 (mm)

l = 46,2 . √101,78

1

3. √0,91 . 1,375 (mm)

l = 282.93 mm

BRACKET 230 X 150 X 8