Vacuum Vessel supported and in position to receive left MCWF. Left MCWF moved into position by overhead crane. Left support cart moved into position. Load supported and crane removed. Right MCWF moved into position by overhead crane. - PowerPoint PPT Presentation
Citation preview
Vacuum Vessel supported and in position to receive left
MCWF
Left MCWF moved into position by overhead crane
Left support cart moved into position. Load supported and
crane removed
Right MCWF moved into position by overhead crane
Right support cart moved into position. Load
supported and crane removed. Shim
measurements taken.
Right MCWF supported by crane. Right support cart
removed and MCWF backed off 13” (position #38).
Right cart support posts removed and posts for position #38 location installed on cart.
Cart positioned and load supported. Crane removed and
shim installed on left MCWF
Load supported by crane and right support
cart removed.
Right MCWF moved into final position by crane. Right cart supports exchanged and initial supports reinstalled. Cart repositioned under MCWF. Load supported by cart, crane removed and final bolting of interface joint occurs
AirLoc Wedgemount bolt on spherical seat precision leveler