Chaska High School Facility Improvements Summer 2012

Preview:

DESCRIPTION

A showcase of photos of the facility improvements made to Chaska High School in Chaska, Minnesota, in the summer of 2012. More than $3 million in "alternative facilities" levy funds is being invested at Chaska over three years.

Citation preview

CHS Facilities

Improvements

Softball Field - Practice Infield

Softball Field - Practice Infield

CHS – Tennis Courts

CHS – Tennis Courts

CHS – Long Jump

CHS Pole Vault

CHS – Running Track

CHS – Running Track

CHS – East Entrance

CHS – East Parking Lot

New Sidewalk and Bus Lane

New FLC Access Sidewalk

New FLC Fenced Play Area

FLC

FLC

FLC

Locker Painting and Lock Repair

New Cardio Room Floor

New Cardio Room Floor and Mirrors

Auxiliary Gym Lighting

New Wall Paint and Lighting

New Mirrors in Auxiliary Gym

FLC

FLC

FLC

Deferred Maintenance of Boilers

Water Softener Replacement

New Lighting in Band Room

New Lighting in Choir Room

CHASKA HIGH 2012 DEFERRED MAINTENANCE AND IMPROVEMENT PROJECTS

Install new walks and bus loading zone on east side for FLC summer '12 $44,000

Renovate East entrance Drive and East Lot, West side drive lanes summer '12 $202,000

Repaint aux gym summer '12 $8,600 Replace interior ADA required signage

pending '!2 $10,000

Replace tennis courts summer '12 $404,500 Replace aux. gym and main gym exterior doors pending '12 $65,000

Replace metal halide lighting in aux gymsummer '12 $7,200

Replace water softener system spring "12 $15,900 Choir & Band rooms lighting replacement

summer '12 $9,700

Running track repair and resurface summer '12 $135,000 Paint Purple House Lockers summer '12 $5,750 Replace Purple House Locker Locks summer '12 $16,000 Fitness Room Wood Aerobics Floor Installation

January '12 $21,900

Softball dugouts installed and baseball dugout expanded - Booster initiative coordinated by B&G Spring '12 $12,500

Family Learning Center Build - out summer '12 $46,000

Total Estimated Investment $1,004,050