Today we “earned” this much BCWP, compared to our planned BCWS
BCWP
BCWSACWP
In EV terms “we’re late” by this much –SV – measured in $’s
Earned Value View of Schedule Variance (SV)
Today is when we actually “earned” the planned BCWP, that we planned to “earn” in the past
BCWP
BCWSACWP
A date in the past when we had planned to “earn” the current
BCWP
In ES terms “we’re late by this much, measured in Time
Earned Schedule View of Schedule Variance (SV)