PCAPP Update
28 May 2014
Presented to:
Citizens’ Advisory Commission
Presented by:
Paul DentOperational Readiness Review (ORR) Manager
What is an ORR?
Per ACWA Policy Statement 26, “ORRs will be conducted to verify the readiness of the ACWA Pilot Plants to safely begin operations involving chemical agents, explosives, or other highly hazardous materials.” The ORR process is used to validate
that PCAPP “plant, paper, and people” collectively meet the required criteria to allow a new operation to begin.
PCAPP ORR process is led by the system-contractor (SC) to support a declaration of readiness.
ACWA provides ORR oversight; independent validation is used to support the SC’s declaration of readiness.
Stakeholders are invited to observe the ORR process.
2
Plant
People Paper
Achieve Readiness – by Responsible Managers
Validate Readiness – by ORR Board
Declare Readiness – by Project Manager
Accept Readiness – by ACWA
5
ORR Major Milestones
NOT YET STARTED
IN PROGRESS
COMPLETE
* Major Milestones per the PCAPP Baseline IMS.
PCAPP goal is to declare readiness 60 days sooner
* Incremental Readiness Assessments will overlap –
they are not strictly sequential
1
7
9
8
4
3
2
6
14
15
16
Lab Dilute Agent Operations Mini-ORR OCT 2013 – 52 Criteria
Boiler Ignition Readiness Assessment DEC 2012 – 19 Criteria
* Mile
stones
for Incre
mental R
eadiness
Assessm
ents
Leading to
Initia
l Agen
t Opera
tions
Integrated Operations Demonstrations (IODs) JUN 2015 – 11 Criteria
Agent Entry Readiness and Agent Containment and Confinement Controls SEP 2014 – 49 Criteria
ERB Provisional Operations SEP-2014 – 75 Criteria
APB Provisional Operations NOV 2014 – 32 Criteria
Contingency Training Readiness/Crew Certification JAN 2015 – 59 Criteria
Security/Surety (Soft-Lockdown) Readiness Review FEB 2015 – 16 Criteria
BTA Provisional Operations NOV 2014 – 13 Criteria
Yard Provisional Operations JUL-2014 – 111 Criteria
Initial Agent Operations - Readiness Declared JUL 2015 – 6 Criteria
ACWA Readiness Endorsement SEP 2015
Training Facility Available for Practical Factors – Readiness Check JUN 2014 Forecast
Pre-Systemization Complete NOV 2013
Training Facility Available for TAT – Readiness Check JAN 2014
10
11
13
12Environmental Readiness FEB 2015 – 14 Criteria
3
Scope of ORR for Initial Agent Operations
Criteria are defined in the Initial Agent Operations ORR procedure
― Defines ORR criteria that reflect project requirements
― Summarizes proposed Integrated Operations Demonstrations (IODs)
― Include normal and off-normal exercises to be performed
― Evaluation teams will observe and critique each demonstration
4
# Functional Area # of criteria
1 Acquisitions 102 Emergency Preparedness 143 Engineering 264 Environmental 145 Government Interfaces 136 Human Resources 37 Information Systems & Technology 58 Laboratory 219 Maintenance 11
10 Medical 2111 Office and Administrative Services 612 Operations 4913 Operations Support 2214 Pilot Test Preparedness 315 Plant Support (Treaty) 816 Project and Plant Management 1517 Quality Assurance/Quality Control 718 Safety 3819 Security 1320 Start-up/ Systemization 5021 Surety 722 Training 1523 Work Control 15
386
Each of the four shifts will perform IODs for readiness validation.
Upon successful completion of IODs and closeout of required findings, System Contractor will declare readiness.
Criteria Review Resources Engaged
Chris Midgett – Chair of Executive Board:― Brings extensive experience in managing chem-demil work
― Liaison to ACWA and stakeholder executive functions
Sierra Lobo, Inc. – Independent engineering resource― Testing & evaluation expertise
― Clients include NASA & Department of Defense
Blue Grass Subject Matter Experts (SMEs): ― Will use BGCAPP SMEs for independent review
― Bring an excellent understanding of standards & recent operating experience
― ORR experience provides benefits to both projects
5
IAO ORR Status
ORR work will be paced by Systemization work.
Data as of 22-May-2014
ORR Documents TotalRequired
Issued for Completion
Board Reviewed Board Accepted
Affidavits 386 135 55 34
CRADS 386 15 0 0
6
ORR Oversight
Review ORR documents, attend Board meetings, and observe demonstrations
Provide immediate feedback on ORR issues, process, and documentation
Provide independent validation of 20% of ORR criteria in accordance with their oversight procedure
Coordinate stakeholder involvement in ORR process
Lead a monthly meeting with representatives from the Blue Grass project, Pueblo Chemical Depot, and stakeholders to communicate ORR status, schedule, issues, and lessons learned
ACWA representatives also assess the System Contractor’s readiness for initial agent operations:
7
Questions?
8