View
275
Download
4
Category
Preview:
Citation preview
Copyright @ 2011. All rights reserved
Forensic Delay Analysis The Ul2mate Test for Project Controls
Project Controls Expo -‐ 31st Oct 2012 Twickenham Stadium, London
Copyright @ 2011. All rights reserved
About the Speaker
Ewen Maclean, Managing Director, FTI Consul2ng Eur Ing MEng (Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
Ewen is an experienced and renowned expert in the field of programming; delay and disrupAon; and associated prolongaAon costs in relaAon to construcAon and engineering projects. In parAcular, he has worked for both internaAonal consultants and contractors and has first-‐hand experience of assisAng and represenAng clients in liAgaAon, arbitraAon, mediaAon and adjudicaAon, both for the claimant and respondent. He has prepared numerous expert witness reports; draIed standard forms of contract and lectured on various commercial and contractual subjects within the construcAon industry. Ewen has also acted in commercial negoAaAons and seJlements, resolving potenAal disputes as well as providing advice on contract procurement. Ewen is well versed in many of the standard forms of construcAon contract including the NEC, JCT, ICE, GC Works CondiAons as well as bespoke forms of contracts including PFI contracts and has worked on contracts that span, inter alia, major building, civil engineering, oil and gas, mechanical and electrical, pharmaceuAcal, infrastructure including highways and rail as well as fit-‐out works.
Copyright @ 2011. All rights reserved
Introduc2on
1. Why is forensic delay analysis the ulAmate test for project controls? 2. Methods of delay analysis 3. Choice of method of delay analysis 4. DemonstraAon of methods of delay analysis 5. Project controls, data and records for delay analysis
Copyright @ 2011. All rights reserved
1. The Ul2mate Test?
Why is forensic delay analysis the ul2mate test for project controls?
• If you have got to the stage where a forensic delay analysis is required then the project may no longer be under control and may be ulAmately tested in formal dispute resoluAon.
• Forensic delay analysis will also ulAmately test how good controls have
been during a project as it will require detailed and appropriate records for that analysis to be undertaken.
• The quality of the records can dictate the quality of the forensic delay analysis.
Copyright @ 2011. All rights reserved
2. Forensic Delay Analysis Methods
Common methods of delay analysis
• As-‐planned versus as-‐built analysis • Impacted as-‐planned • Collapsed as-‐built • Time impact analysis (windows/snapshot analysis)
Copyright @ 2011. All rights reserved
3. Choice of Method of Delay Analysis
Parameters
• Relevant condiAons of contract • Nature of causaAve events • Value of the dispute • Time available • Records available • Programme informaAon available • Programmer’s skill level
Copyright @ 2011. All rights reserved
3. Choice of Method of Delay Analysis
Parameters (SCL Delay and Disrup2on Protocol)
Type of analysis
As-‐planned programme without network
Networked as-‐planned programme
Updated as-‐planned
networked programme
As-‐built records
As-‐planned vs. as-‐built
X Or X And X Or X
Impacted as-‐planned
X
Collapsed as-‐built
X
Time impact analysis
X Or X And X
Copyright @ 2011. All rights reserved
4.1. ‘As-‐planned’ vs ‘As-‐built’
Essen2als
• Good base programme (ideally agreed at start) • Programme as closely as possible reflects project logic • As-‐built informaAon to establish as-‐built comparison • May be chosen where issues are simple and liability is clear • No CPA required
Steps
• Determine baseline programme • Determine as-‐built programme and plot against planned
Copyright @ 2011. All rights reserved
4.1. ‘As-‐planned’ vs ‘As-‐built’
As-‐built
Claim
As-‐planned
Copyright @ 2011. All rights reserved
4.1. ‘As-‐planned’ vs ‘As-‐built’
Summary
• Only retrospecAve • No cause and effect • Takes no account of concurrency • Assumes fault lies with others • Unreliable in dispute resoluAon
Copyright @ 2011. All rights reserved
4.2. Impacted ‘As-‐planned’
Essen2als
• Good base programme (ideally agreed at start) • Programme reflects project logic • Likely choice where programme not updated and limited/no as-‐built
informaAon available Steps
• Impact all events on planned programme • Can be done in steps of Ame intervals -‐ cross checked with key as-‐built
milestones
Copyright @ 2011. All rights reserved
4.2. Impacted ‘As-‐planned’
Summary
• ProspecAve/retrospecAve • Limited cause and effect • Takes no account of:
• Progress • Resources • Changing logic
• Unreliable in dispute resoluAon
Copyright @ 2011. All rights reserved
4.3. Collapsed ‘As-‐built’
Essen2als • Detailed as-‐built records • Detailed understanding of construcAon logic • Access to site team • Basis for measuring and idenAfying the extent of delays
Steps
• Reconstruct as-‐built programme & determine logic • IdenAfy delay periods & responsibility for delays • Carry out delay analysis • Explain approach and results
Copyright @ 2011. All rights reserved
4.3. Collapsed ‘As-‐built’
• IdenAfy Employer delays
Contract period
As-‐built
Project CompleAon
Actual CompleAon
• Reconstruct as-‐built programme & determine logic
Copyright @ 2011. All rights reserved
4.3. Collapsed ‘As-‐built’
Contract period
Contract CompleAon
As-‐built
Actual CompleAon ‘but for’ Employer Delays
Actual CompleAon
• Zero the Employer Delays
Copyright @ 2011. All rights reserved
4.3. Collapsed ‘As-‐built’
Contract period
As-‐built
Contract CompleAon
Contractor culpable delays Contractor EoT
enAtlement
Actual CompleAon
• EnAtlement
Copyright @ 2011. All rights reserved
4.3. Collapsed ‘As-‐built’
Summary • RetrospecAve (limited prospecAve) • Factually based • If done properly: • Demonstrates cause and effect • Takes account of concurrency
• RelaAvely quick • Reliable in dispute resoluAon
Copyright @ 2011. All rights reserved
4.4. Time Impact Analysis
Essen2als
• Good base programme (ideally agreed at start) • Programme reflects project logic • Reliable and consistent progress data, in sufficient detail and at small
enough intervals to make the analysis meaningful
Steps
• Verify base programme and correct for errors • IdenAfy delay events and periods • Input progress up to start of first window period or first delay • Reschedule and check compleAon • Impact delay and record any logic changes to deal with miAgaAon • Reschedule and check compleAon and record any further delay
Copyright @ 2011. All rights reserved
4.4. Time Impact Analysis
• Master Programme
AcAvity 1
AcAvity 2
AcAvity 3
Project compleAon
Copyright @ 2011. All rights reserved
4.4. Time Impact Analysis -‐ illustrated
• Step 2, Enter progress & record effect
AcAvity 1
AcAvity 2
AcAvity 3
Project compleAon Time Now
Delay to Project compleAon
Copyright @ 2011. All rights reserved
4.4. Time Impact Analysis -‐ illustrated
• Step 3, Analyse the delaying event
AcAvity 1
AcAvity 2
AcAvity 3
Project compleAon Time Now
Delaying Event
Delay to Project compleAon
Period of EoT
Copyright @ 2011. All rights reserved
4.4. Time Impact Analysis
Summary
• ProspecAve/RetrospecAve • Cause and effect • Takes account of progress/resource/logic • Reliable in dispute resoluAon • Preferred method of SCL Protocol • Complicated (and therefore slow) • Difficult to communicate (Skanska v Egger [2004])
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
Programmes
• Allow comparison of what would have happened with what actually happened
• Need to: • Meet contract requirements • Be a workable management tool • Be current • Be shared • Be the Contractor’s
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
Programme Data Generally 1
• Requirements: • The acAviAes in all work packages • The earliest and latest start and finish dates for every acAvity in
each work package • Access dates for each phase or secAon • Milestone and key dates • Holiday periods • Dates by which design work or drawings to be produced plus
allowances for approval periods and re-‐submiJals • Dates by which samples are to be produced plus allowances for
re-‐submiJals • Procurement periods and delivery dates
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
Programme Data Generally 2
• Requirements: • Dates by which work will be ready for tesAng by the Employer • The work contained in defined Provisional Sums • AcAviAes represenAng the likely work content of undefined
Provisional Sums • Commissioning periods • Provisions for float, Ame risk allowances, quality control
procedures, health and safety requirements • Be resourced and costed • Be coded to build in intelligence
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
Records
• Allow comparison of what would have happened with what actually happened
• Need to: • Meet contract requirements • Be expressed by reference to a programme • Be quanAtaAve • Be accurate • Be regularly kept • Be public • Be consistent • Record context
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
• Requirements: • Meet the contract requirements • Start and finish dates of acAviAes • Degree of compleAon of acAviAes • Labour resources by trade, acAvity and locaAon • OperaAng plant/equipment with hours worked, idle or down Ame
for repair • Key procurement acAviAes • Any delays encountered • Weather condiAons encountered • A list of instrucAons given and received and any conflicts in plans
and/or specificaAons
Records Generally 1
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
• Requirements: • A list of noAces served regarding progress • InformaAon required from and by the Employer/CA • Intervals at which each of these types of records should be
submiJed • The reports should be signed and dated by the CA
• Consider: • Marked up drawings • Photographs • Videos • More sophisAcated techniques such as BIM
Records Generally 2
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
a) Reference number b) Cause and effect of delay or
disrupAon c) Period of delay to secAon or
part of works d) Period of delay to
compleAon date
e) Contract clause relevant to delay f) Contract clause relevant to loss
and expense or contract clause breached
g) Date of delay noAce and parAculars
h) Date of loss and expense noAce and parAculars
Delay Schedule
• A delay schedule requires compleAon of informaAon in respect of each delaying event under the following columns which should be set out in schedule format:
Copyright @ 2011. All rights reserved
5. Project Controls, Data and Records
a) Reference number b) InstrucAon, late issue of
drawing, V.O. and the like which caused disrupAon
c) Part or secAon of work affected
d) Manner in which part or secAon of work was affected
e) Correspondence relaAng to disrupAon
f) AddiAonal hours of labour (or sub-‐contractor’s addiAonal Ame)
g) Hourly rate h) AddiAonal plant, hours/days/
weeks i) Hourly/daily/weekly rate j) Total cost of disrupAon
Disrup2on Schedule
• A disrupAon schedule requires compleAon of informaAon in respect of each disrupAng event under the following columns which should be set out in schedule format:
Copyright @ 2011. All rights reserved
Summary
• A forensic delay analysis is likely to be the ulAmate test to see whether the project controls have been operated successfully
• The choice of method of delay analysis can be dictated by the quality, appropriateness and consistency of project records
• Forensic delay analyses are more reliable if based upon factual as-‐built records rather than theoreAcal assessments
• Use schedules to record delay and disrupAon or any potenAal enAtlement
• Thank you and any quesAons?
Recommended