Some experiences in power plants with RT-LAB BERTA Test Bench
Citation preview
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
1
Marc LangevinOPAL-RT TECHNOLOGIES
marc.langevin@opal-rt.com
Some experiences in power plants with
RT-LAB BERTA Test Bench
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
2
A Real-Time Regulator, Turbine and Alternator Test Bench for Ensuring Generators Under Test Contribute to Whole
System Stability and Facilitating Model Identification
Marc Langevin, eng., Ph.D.
OPAL-RT TECHNOLOGIES, Montréal
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
3
The Needs of the Industry
• Better understanding of generator behaviors in case of major system frequency disturbance;
• Better modeling of turbines and speed governors, for improved accuracy of transient stability studies;
• Better speed governor settings for improved frequency stability.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
4
Requirements
• Transmission system owner’s requirements for power plant operation:
• NERC’s Standard Mod-027;
• IEC’s international standard 60308;
• Hydro-Québec’s transmission system;
• Dynamic model identification and validation;
• Frequency stability improvement
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
5
NERC’s Standard Mod-027
• Requirement #2 of 5:
• "Each Generator Owner shall provide, for each applicable unit, a verified turbine/governor and load control or active power/frequency control model, including documentation and data ... to its Transmission Planner in accordance with the periodicity specified in MOD-027 Attachment 1"
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
6
IEC`s International Standard on Testing of Control Systems for Hydro Turbines
• "The principle of the simulator can be described as follows: a signal, representing the speed/frequency variations which would occur if the unit were supplying an isolated load, is developed by calculation from the measured electrical power output of the generator. This simulated speed/frequency signal is then delivered to the controller in place of (or in addition to) the actual speed/frequency signal."
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
7
Hydro-Québec’s transmission system requirements
• As a member of NPCC (Northeast Power Coordinating Council), Hydro-Québec Production needed to provide to Hydro-Québec TransÉnergie, the Québec transmission grid owner, the required models and parameters for the hydraulic turbine and speed governors. These models must be in accordance with IEEE standard “Dynamic Models for Steam and Hydro Turbines in Power System Studies” and “Hydraulic Turbine and Turbine Control models for System Dynamic Studies".
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
8
What is BERTA?
• A test bench specially designed for testing speed/power control on site and/or in laboratory;
• Driven by a real-time simulator capable of generating frequency signals to be injected in the speed governor:
• Open loop tests with pre-programmed frequency signals;
• Closed loop tests using a frequency signal computed in real time according to the generator power variations resulting from a load disturbance in a simulated islanded mode of operation.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
9
Standard Operation Set up in a Power Station
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
10
Test Set up in a Power Station
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
11
RT-LAB BERTA Test Bench
• Experimentation in hydro power plant
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
12
Model Validation: open loop test• Simulated
• frequency
• deviation
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
13
The speed governor block diagram
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
14
Model Validation: open loop test
Equivalent gate
set point variation
and actual gate
displacement:
∆ 𝑆𝑃 = −∆𝐹𝐵𝑝
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
15
Model Validation: open loop test
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
16
Model Validation: the importance of closed loop tests
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
17
Model Validation : the importance of closed loop tests
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
18
Model Validation : the importance of closed loop tests
-5%
load
ste
p
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
19
Closed loop test: the PSS emulator
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
20
RT-LAB BERTA Test Bench
• Experimentation in gas power plant
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
21
Closed loop test: detection of instability in islanded operation
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
22
Closed loop test: after new settings
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
23
RT-LAB BERTA Test Bench
• Experimentation in a diesel power plant.
• Some test sessions can be very arduous.
• There is no miracle. You need to be very well prepared.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
24
Open loop test: frequency signal
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
25
Open loop test at speed no load
• A first test to validate the speed pick-up modeling
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
26
Open loop test
• Description:
• P0 = 135 kW
• Delta F simulated = +0.001 p.u.
• Dead-band = ±0.2 Hz
•Expected result:
• Valve will close by 0.025 p.u. because of 4% droop value
• Power will decrease according to the valve opening
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
27
Open loop test
•Actual result:
• Valve first closed by 0.015 V, but came back to its initial value;
• Power first dropped by 0.02 p.u. and finally went back to its initial value
•Possible explanation:
• A limitation on minimum power?
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
28
Steady state characteristics: very important to know before tests
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
29
Open loop test
• Description:
• P0 = 1289 kW
• Delta F simulated = +0.002 p.u.
• No dead-band
•Expected result:
• Valve will close by 0.05 p.u. because of 4% droop value
• Power will decrease according to the valve behavior
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
30
Open loop test
•Actual result:
• Valve closed by 0.03 V;
• Power decreased by 0.03 p.u.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
31
Open loop test
•Actual result:• Valve closed by 0.03 V;
• Power decreased by 0.03 p.u.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
32
Closed loop test
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
33
Closed loop test
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
34
Closed loop test
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
35
Closed loop test
• Simulated mechanical power
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
36
Test conditions not good enough
• Mechanical power model hard to estimate because:
• The tested unit is relatively large compared to the whole power system;
• The power system frequency is continuously oscillating. This means that the tested unit speed is also oscillating;
• The electric power oscillates against all the other units in the power system. Hard to tell what comes from where;
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
37
Closed loop: Fourier analysis
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
38
Closed loop: Fourier analysis
• Zoom at lower frequencies
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
39
Example of recommendations
• Following a hard test session:• All the missing information regarding the speed governor and the diesel prime
mover characteristics should be requested from the manufacturer. This information is necessary for building an accurate model of the speed governor and the prime mover;
• Other tests should be conducted at higher power values;
• Some frequency sweep tests in open loop should be conducted;
• Power system stabilizers should be implemented and carefully tuned for frequencies between 0.2 Hz and 6 Hz;
• New speed controller settings should be implemented in order to avoid the use of the speed control derivative gain. Close loop tests should be conducted with these new settings.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
40
Example of recommendations
• Following a good test session in a hydro power plant:
• Use the speed controller model of figure XX;
• Use the non linear model of the Francis turbine with the following parameters:• Tw = 3.2 s;
• Phi = 0.045;
• Gross head = 1.045 p.u.
• And the following polynomials:• 𝑄 = 0,0071 𝐺3 − 0,588 𝐺2 + 1,8467 𝐺 − 0,268
• 𝑃 = −1,0296 𝑄3 + 1,523 𝑄2 + 0,5685 𝑄 − 0,0658
• The current speed governor settings seem appropriate (or do not seem appropriate) for ensuring the unit to contribute adequately to the power system frequency stability.
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
41
Frequency Behavior in a Multi-Machine System
• The synchronous interconnection transfers the stabilizing energy from the stable units to the unstable units
• But does not stabilize a power system where most of the units would be unstable in an islanded system
• Conclusion: each unit should be set to be stable in islanded operation mode. That’s the speed governor job
• Please, do not resort to load shedding to make up for the inefficiency of your frequency control systems
The 7th International Conferenceon Real-Time Simulation TechnologiesMontreal | 9-12 June, 2014
42
Three Important Principles to Consider when Adjustinga Speed Governor
• Speed governor should be set to ensure the generating unit stability in an islanded power system, even if it is synchronized to a powerful grid;
• Control parameters should be set for quick and stable frequency recovery;
• Speed governor must avoid contributing to natural electro-mechanical power oscillations.