Gemasolar a thermal solar power plant with 15 hours, Ignacio Burgaleta (Torresol Energy)

Preview:

DESCRIPTION

Gemasolar a thermal solar power plant with 15 hours, Ignacio Burgaleta (Torresol Energy)

Citation preview

11 June 2013, Madrid © Torresol Energy

GEMASOLAR: A THERMAL SOLAR POWER PLANT WITH

15 HOURS OF THERMAL STORAGE SYSTEM

WORKSHOP ON APPLICATIONS OF SOLAR FORECASTING

Juan Ignacio Burgaleta

Director of Technology

© Torresol Energy 2 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

INDEX

1. Torresol Energy

2. The GEMASOLAR Plant

3. Innovations

4. Operation

5. Construction

6. Commercial operation

7. Conclusions

© Torresol Energy 3 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

1. Torresol Energy

• Engineering, consulting, and systems inte-

gration company. Founded in 1956.

• Very active in Solar Energy since 2000. – Technology developer: SENERtrough collector system, Sensol

software, heliostats, heliostat axis drive mechanisms, molten salt

technology (as storage system and as heat transfer fluid) central

tower receiver… amongst many other innovations.

– PSA Tower Prototype

– Turn Key Projects: Andasol 1 & 2, in Granada; Extresol 1, 2

& 3, in Badajoz; one plant in La Garrovilla (Badajoz); one

plant in Alvarado (Badajoz); and two plants in Navalvillar de

Pela (Badajoz).

60% 40%

• 100% “Mubadala Development

Company” stockholding.

• Mubadala Development Company”

belongs to the Abu Dhabi Emirate.

• Goal: development and commer-

cialization of innovative technologies

in renewable, alternative and sus-

tainable energies.

A STRONG ALLIANCE

© Torresol Energy 4 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

1. Torresol Energy

GEMASOLAR

(Tower)

VALLE 1

(PTC)

VALLE 2

(PTC)

© Torresol Energy 5 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

2. The GEMASOLAR Plant

© Torresol Energy 6 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

2. The GEMASOLAR Plant

• Storage system

Solar energy Solar field and

central tower receiver Molten salts

storage system

• Generation system

Molten salts

storage system

Steam

generation

system

Turbine/generator

system Grid

© Torresol Energy 7 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

2. The GEMASOLAR Plant

• High thermal storage capacity (24 hours).

• The same fluid is used for heat transfer and storage.

• The molten salts reach highest temperatures (565ºc) maximizing thermodynamic efficiency.

• The whole piping system is contained in an small area, reducing the heat losses, the

maintenance costs and minimizing the possibility of leaks.

• Lower operation risk (No mobile piping system. No swivel joints. No thermal oil).

• Highest cycle efficiency.

Advantages of Central Tower with Molten Salt Technology

© Torresol Energy 8 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

2. The GEMASOLAR Plant

© Torresol Energy 9 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

3. Innovations (Heliostats)

• High surface (115 m2).

• High optic quality and precision.

• Integrated facet mirror-structure.

• Innovative system of facets union.

• Reduced manufacturing, assembly and

maintenance costs.

Developed by SENER

© Torresol Energy 10 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

3. Innovations (Receiver)

• Optimize size to minimize thermal losses.

• High flow of incident radiation.

• Optimize the design to the maximum temperature

of the metal.

• Thermal maximum efficiency.

• Designed for 25 years of operation.

Solar receiver

Prototype receiver testing in

the PSA of Almería

Receiver Developed by SENER with

PSA-CIEMAT colaboration

© Torresol Energy 11 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

3. Innovations

Solar Field Control System

• Innovative Control system of solar

field composed by 2650 heliostats,

positioned at north, south, east and

west of the tower.

• Optimize the electricity consumption

of the heliostat actuation system.

• Development of a new pointing

strategy that guarantees the good

distribution of the solar flow incident

in the receiver.

• Reduce the time of heliostats de-

focusing. Developed by SENER

© Torresol Energy 12 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

3. Innovations

Molten Salt Storage System

– Tranference fluid and thermal

storage: Nitate molten salts 60%

Na NO3 y 40% KNO3.

– 15 hours of thermal storage

capacity, operating with turbine in

nominal conditions.

– Operatoin tempeature 565.

– Pumping of salts to the receiver

placed in the tower at 140 m.

Power block, molten salt storage system of

the GEMASOLAR Plant

Developed by SENER

© Torresol Energy 13 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

4. Operation

GEMASOLAR Flow Diagram

© Torresol Energy 14 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

4. Operation

GEMASOLAR Daytime Operation

© Torresol Energy 15 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

4. Operation

GEMASOLAR Daytime Operation during Cloudy Periods

© Torresol Energy 16 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

GEMASOLAR Nightime Operation

4. Operation

© Torresol Energy 17 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

5. Construction

Aerial view of the GEMASOLAR Power Block

© Torresol Energy 18 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

5. Construction

© Torresol Energy 19 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

5. Construction

Aerial view of the GEMASOLAR Plant

© Torresol Energy 20 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

© Torresol Energy 21 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

• Commissioning activities started November 2010:

− Heliostats calibration.

− Salt molten in a temporary installation and stored in the cold tank (November –

December 2010)

• End of April 2011 plant synchronized.

Start up and Commissioning

© Torresol Energy 22 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

• From early May 2011 providing electricity to the grid.

• End June, 24 hours of uninterrupted electricity production.

• On July 6 2011 performance test, result exceeded theoretical prediction.

• Excellent hourly production predictions.

6. Commercial Operation

© Torresol Energy 23 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

Starting & Shutting Down the Receiver

• Every day the receiver temperature changes quickly from the environmental conditions till

operation conditions (565ºC)

• Procedures to control all the parameters-components which affect the receiver filling and

drainage developed by Torresol Energy to secure the efficiency and the security (delicate

operation)

• Complex system: Sincronization between Solard Field (heliostats) and the Central

Receiver System (CRS)

• Thermography cameras are part of the control tool for the radiation flow onto the receiver

and are synchronized with the solar field software (heliostats pointing)

© Torresol Energy 24 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

Starting & Shutting Down the Receiver

• Importance of a good reciever drainage

• The molten salt must be between 260ºC and 565ºC.

• Operational improvements extend the daily

production

• Calibration of the heliostats: Targets located below

the receiver to calibrate the heliostats

© Torresol Energy 25 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

Actual Guarantee

– Receiver Thermal Power 135 MWTh 120 MWTh

– Net Electrical Production 414.3 MWh 302 MWh

– Receiver Outlet Salts Temp. 565 ºC 565 ºC

– Gross Power 19.9 MW 19.9 MW

– Net Power 17.0 MW 17.0 MW

24 h Overall Performance Test passed on July 6th, 2011

6. Commercial Operation

© Torresol Energy 26 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

Production dates. From 16-08-2011, 00:00 hour to 17-08-2011, 00:00 hour

© Torresol Energy 27 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

Non-stop operation in Winter time

© Torresol Energy 28 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

6. Commercial Operation

Turbine continuously running at nominal power in summer

© Torresol Energy 29 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

12 DAYS OF CONTINUOUS PRODUCTION

6. Commercial Operation

© Torresol Energy 30 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

7. Next Steps

• We, and most of the analysts, consider that the

technology of Central Tower Plants with Molten Salts

has higher opportunities to achieve the grid parity in

a shorter period of time due to:

− Larger future cost reduction.

− Size to be increased.

− New equipment yet to be developed.

− Affordable construction materials.

• Next Tower Plant with Molten Salt Storage System:

− + 500 MWt receiver ( +12.000 heliostats)

− Storage System capacity depending on Market

requirements

© Torresol Energy 31 11 June 2013, Madrid

GEMASOLAR: A THERMAL SOLAR POWER PLANT

WITH 15 HOURS OF THERMAL STORAGE SYSTEM

7. Conclusions

• GEMASOLAR is the first commercial-scale plant featuring a central tower

molten salt receiver with thermal storage capabilities supplying electricity

to the grid from May 2011.

• The molten salt thermal storage system helps avoid fluctuations in power

supply and enables to produce electricity during 15 hours in the absence

of solar radiation.

• The 19.9 MWe GEMASOLAR Plant became the first CSP ever to

generate uninterrupted electricity for 24 hour at full capacity.

• Next Tower Plant and Molten Salt System with increased power

11 June 2013, Madrid © Torresol Energy

Thank you

Recommended