Visualize Project Success!Using TILOS for the linear planning and controlling
of projects.
Characteristics of a linear project
� Repetition of each activity along the length of the project
� The goal is to optimize the productivity rates thus minimizing the
total time of crews on the ROW thereby reducing project duration
and overall cost
� Continuous movement of activities and crews along right-of-way
� Typical projects include: rail, tunnel, highway, pipeline, bridge and
high voltage transmission line projects
The graphical representation of linear projects
Road project Rail project
Building projectPipeline project
� TILOS connects the geography and constructability issues of a project with the schedule (what is built, when and where)
� Traditional CPM schedules and network diagrams fail to provide a visual connection between the project plan and the project itself
� Present your project on a single page using TILOS!
TILOS vs. traditional CPM and Gantt charts
40-page Primavera schedule
represented on one page using linear
planning
TILOS in Linear Construction Projects
Top soil
Stabilisation
Grading
Bridge
Cut
Fill
- How it works
- The Gantt Chart features
� Natural working with interactive Gantt chart - Milestone symbols can be defined free and put to 1 task line
- Multiple tasks on one line
- Task steps to monitor micro tasks or extra work to happen before, during and after the task execution time
� Multiple Windows support- Move or copy tasks across the windows by mouse
- Create links across the windows
- Railway Project
o Pictures from site
o Scale with side map
o Main construction windows
o Detailed work
� High quality layouts keep attraction
� Be one step ahead of your completion
- Railway Project
� Realistic scheduling using site data that influences construction progress
� Full integration of logistic and train rides
o Generated sitemap and grid
from sector table
o Track renewal with hindrance
and setup times
o Full calculated ballast trains
incl. train setup
o Train runs for drive in and out
o Rock classification
table with drilling
speed for tasks
o Connector tunnels
o Tunnel lining
(1 task based on
work profile)
o Water draw down
zone
- Metro tunnel building
o Bend and Coordinates based
on station table
o Pile works generated based
on station table incl.
relationships
o Deck works generated by
station table
o Elevated station
� Quick plan creation based on station tables with quantity values
� Ideal overview on the construction program
- Metro project: Elevated line
- Metro Rail Project in South Africa
� First basic construction program in TILOS with later detailing in Primavera
� Update of TILOS schedule done every 1 month using link to Primavera
o 8 zones with different station
numbering (non linear axis)
o Left part build as underground
o Cut and fill sections
o Evaluation phase
- Industry sample: Pipeline
� Pipeline project planned in 2 spreads to cover weather conditions
� Rainfall is shown in colors in the background of the schedule
o Elevation profile
o Strong rain fall
o Pump stations
o Linear works
- Highway Project
- Highway Project
o Exits and crossings
o Cut & Fill
o Bridges
o Tunnels
o Preparation
o Bridges
o Cut & Fill
o Black tops
o Monitoring
o Handover
- Highway Project
� Progress always contains distance information, not just % completed
� Enter progress directly into TILOS for an immediate evaluation
� Record progressImport progress (Clipboard or XML) Analyse progressApply progress
TILOS progress reporting
� Description of the track including GPS co-ordinates
Project description in XLS
� Description of the project complexities
Planning result in Google Maps
� Track renewal activity sliced into 3 hour working and reporting steps
� 06:00 – 09:00
� 03:00 – 06:00
� 00:00 – 03:00
@ 3am
Progress in Google
@ 6am @ 9am
� XML Export with time sliced data shows progress status along the ROW
� Comparison: planned (thick line) � actual (thin line)
Integration models
XML
- Tasks- Links- Profiles
- Resources- Costs- Progress
- XML: Data Exchange concept
TILOS XML
Microsoft Project
ASTA Power Project
Other programsExcel
ASCClipboard / File
o Library data- Resources and accounts- Categories (Codes)- Distance and time profile data
o Tasks
o Task data- Resource and cost data- Actual resource data- Links- Progress
o XLS Exchange- Same items as for ASC- Each object in a separate data sheet
o XLS Report- Export of task list with resources assignments - Summary of resource consumption at the end- Time sliced values (Days / Week / Month / Years)- Empty lines for collect actual data
Oracle Primavera
- XML: Export from TILOS
o Select Action - File / Import- File / Export
o Select format- ASC- XML- Excel
o Data source- Select Clipboard or File
o Select profile- Data exchange rules
o Select project- Select sub projects- Set a filter
o Start exchange
- XML Exchange with Primavera
o Log in - Standard Primavera Log in
o Select action- Import or Export- Create user fields
o Data source- Select profile to use
(Contains exchange rules)- Select data file
(Contains exchange data)
o Projects and filters- Select project- Select a filter for export
o Start Import
- Primavera Master Project
o Task ID from TILOS (alternatively GUID)
o WBS code
o Location data (UDF fields)
o TILOS Template as code assignment
� A tool that connects schedule and site
information in a single chart. Site
constraints are integrated into the plan
from the beginning
� Is used in any project phase: FEED,
Tendering and Estimating, Execution
and Claim analysis.
� A tool that can be used by any
participant in the construction process:
Owners, Engineers and Construction
company.
TILOS – professional linear project management solution
� TIME DISTANCE is superior to GANTT CHARTS for
linear projects.
� Rapid creation of repetitive tasks in different locations
saves time and effort for detailed planning. Easy clash
detection and avoiding errors saves money during
construction phase.
� Powerful progress measurement tool to monitor
construction exactly as it was done in the field ( move-
arounds, work stoppages and out of sequence
progress).
� Flexible integration methods allow usage of TILOS
along with other software and also if the project has
already started.
"TILOS transformed our engineers' attitude
towards project scheduling from something
extra they never had time for to a tool they
"owned" and wouldn't go to a meeting without.”
James Lyon - HDR Inc. in USA
What one of our clients is saying
Cityringen project in Kopenhagen, Length: 15.2 km Finish: in 2018
TILOS was used in early design phase to schedule
TBM and the work in stations. We got the following
remark on TILOS from :
“TILOS is being used as the strategic planning tool for
the Copenhagen Cityringen Project. Early in the
project it was used to assess the impact of different
TBM sequences and number of TBM’s on both the
overall programme and the interfaces with the
individual station construction. As the project has
developed the tool has been invaluable in quickly
assessing the affects of changes, possible delays and
determining suitable mitigation measures, for both
the TBM drives and the station constructions. Not
only has TILOS been great as an analysis tool, but the
easy to understand graphical output provides a simple
tool for explaining the planning to all members of the
project team.”
This from :
Steen Nielsen
Head of Planning
Metroselskabet I/S
Metrovej 5
DK - 2300 Copenhagen S More info about project and contracts: http://intl.m.dk/Cityringen-en.aspx
Pipeline project Alberta Clipper, Canada
Enbridge Pipelines Inc. operates, in Canada and the U.S., the
world’s longest crude oil and liquids pipeline system. These
pipeline systems have operated for over 55 years and now
comprise approximately 13,500 kilometres (8,500 miles) of
pipeline, delivering more than 2 million barrels per day of crude oil
and liquids. Alberta Clipper is a crude oil pipeline that will provide
service between Hardisty, Alberta, and Superior, Wis. This 1,000-
mile / 1,607-km pipeline will have an initial capacity of 450,000
barrels per day (bpd), with ultimate capacity of up to 800,000 bpd
available.
Enbridge Pipelines Inc. used TILOS as their best in class linear
scheduling tool for managing the Alberta Clipper Mainline
Construction for this immense project in Canada. The software
was used in the field, and in the main offices to bring together
stakeholders to greatly enhance planning, and reporting making
the project a huge success.
More info about pipeline projects: http://linearproject.com/pipeline-construction.html
TILOS (TIme LOcation System)
� Railway companies: Saudi Archirodon, DB, SNCF, Network Rail, Herzog, Nurol Construction,
Dogus, Larsen & Toubro Ltd., Qatar Railway Company, MMC Gamuda
� Railway equipment: Alstom, Bombardier, Siemens, IJM Corporation-
� Building companies: Bilfinger Berger, Hochtief, Strabag, Skanska, Bouygues, Vinci, Hill
International, Kiewit, Flatiron, Enka, Parsons-UAE
� Engineering: Bechtel, Fluor, HDR Inc, Drees & Sommer, Lahmeyer, DB Consult,
SNC Lavalin, Gulf Interstate, Worley Parsons, Engineers India Ltd. Indian
Institute of Technology, Leighton Contractors Asia Limited, AECOM
� Pipeline: TransCanada, Enbridge, Willbros, Henkels & McCoy, Techint, Repsol, Rel.Gas
Transport. Infra.LTD, NABUCCO Consortium, Stroytransgaz, Punj Lloyd Oil & Gas
� Power: ATCO Electric, Balfour Beatty
� Road: Mota-Engil, Hess. Straßenbauamt, Hermann Kirchner, DMRC
� Metro / light rail: Kopenhagen, Dallas, Toronto Transit, Houston Rapid Transit, Astaldi,
Gulermak