A Case Study

Showing how Western University Canada is utilizing Primavera P6

and Contract Manager to deliver Capital and Infrastructure Projects.

Session xxxxx

Presentation by:

Fred Janzen B.E.S PMP

Facilities Management

Western University

Capital Project Delivery Using Primavera

Page 2: 204380 capital project delivery using primavera
Page 3: 204380 capital project delivery using primavera

This presentation will :

1) Present background information on Western University

Canada projects.

2) Discuss how P6 is used to deliver projects.

3) Discuss how CM is used to deliver projects.

4) Discuss integration to ERP systems.

5) Illustrate how Western uses UPK to assist in the delivery

of projects.

6) Illustrate the reporting tools that Western uses.

7) Show Western’s Roadmap for Primavera evolution and

lessons learned.

Page 4: 204380 capital project delivery using primavera

Research Intensive University

• 35,000+ Students

• 3500+ Staff and Faculty

• Operating Budget - $555 M

• Research Budget - $208 M

• Located in London, Ontario, Canada

Western University Organization

Page 5: 204380 capital project delivery using primavera

Campus Facilities

Richard Ivey School of Business (under construction)

University College ca. 1920

Page 6: 204380 capital project delivery using primavera

Campus Geography

Main campus - 155

hectares/380 Acres

Land Holdings – 480

Hectares/1175 Acres

15 KM (9.5 Miles) Roadway

93 Buildings

9 Residences/ almost 5000

beds

Growing

Page 7: 204380 capital project delivery using primavera

• 200 – 300 capital & Infrastructure projects

• $10,000 to $3 Million

• Infrastructure, Classroom and Lab enhancements

• 10 – 15 medium projects

• $5 to $15 Million

• Renovations, Major Infrastructure

• 4 – 5 major projects

• $15 to $100 million

• New Building

• Major retrofit old buildings to new standards

• $150 to $300 million budget

Projects

Page 8: 204380 capital project delivery using primavera

Facilities Engineering Staff

Internal staff

• 20 Project coordinators, Managers and Engineers

• 100 Trades persons (includes 6 person project crew)

• 5 Design persons

•External

• 30 to 40 General contractors

• 20 to 35 Consultants and Architects

Page 9: 204380 capital project delivery using primavera

P6 Dashboards

Page 10: 204380 capital project delivery using primavera

P6 Dashboards

Page 11: 204380 capital project delivery using primavera

P6 Dashboards

Page 12: 204380 capital project delivery using primavera

P6 Dashboards

Page 13: 204380 capital project delivery using primavera

P6 Dashboards

Page 14: 204380 capital project delivery using primavera

P6 Enterprise Project Structure

Page 15: 204380 capital project delivery using primavera

P6 Enterprise Project Structure

Page 16: 204380 capital project delivery using primavera

P6 Scheduling

Page 17: 204380 capital project delivery using primavera

P6 Scheduling

Page 18: 204380 capital project delivery using primavera

P6 Scheduling

Page 19: 204380 capital project delivery using primavera

P6 Scheduling

Page 20: 204380 capital project delivery using primavera

Primavera Contract Manager

Page 21: 204380 capital project delivery using primavera

Facilities Management

CM Control Center

Page 22: 204380 capital project delivery using primavera

CM Western Control Center

Page 23: 204380 capital project delivery using primavera

Facilities Management

CM Workflow

Page 24: 204380 capital project delivery using primavera

Facilities Management

CM Workflow

Page 25: 204380 capital project delivery using primavera

CM Submittals

Page 26: 204380 capital project delivery using primavera

CM Submittals

Page 27: 204380 capital project delivery using primavera

CM Submittals

Page 28: 204380 capital project delivery using primavera

CM Submittals

Page 29: 204380 capital project delivery using primavera

CM Information

Page 30: 204380 capital project delivery using primavera

CM Daily Reports

Page 31: 204380 capital project delivery using primavera

CM Site Meetings

Page 32: 204380 capital project delivery using primavera

CM RFI's

Page 33: 204380 capital project delivery using primavera

CM Costs

Page 34: 204380 capital project delivery using primavera

CM Costs

Page 35: 204380 capital project delivery using primavera

CM Costs

Page 36: 204380 capital project delivery using primavera

CM Costs

Page 37: 204380 capital project delivery using primavera

Primavera Reports

Page 38: 204380 capital project delivery using primavera

Primavera and ERP

Primavera P6 P.S. Financials Primavera CM

Vendor Records One Time upload into

Implementation Project

Update manually

Purchase Order Purchase Order Input

P.O. or Contracts

Work flow Approval

Vouchers

Nightly Build

Payment Requisition

Input

Workflow Approval

Purchase Order

Changes

Change Order Input

Workflow Approval

Project WBS

Summary Cost Activity

Activity Expense Tab

GL Information

Project Level

Encumbered and Actuals

GL Information

Detailed Information

Cost Worksheet

Actuals

Voucher

Nightly Build

Invoice Input

Workflow Approval

EDI

XML File

Manual

Entry

XML

Flat File

EDI

XML File

DB

Link

XML

Flat File

DB

Link

Page 39: 204380 capital project delivery using primavera

UPK and Primavera

Page 40: 204380 capital project delivery using primavera

UPK and Primavera

Page 41: 204380 capital project delivery using primavera

Western's Roadmap

Projects

CM 14

PS –P6

PS –CM

UPK

New User

Training

Cost

Modules

Page 42: 204380 capital project delivery using primavera

Questions