10
New Audenried High School Originally Opened in 1931 New School Opened in 2008

Audenried High School

Embed Size (px)

DESCRIPTION

PSIT Project.

Citation preview

Page 1: Audenried High School

New Audenried High School

Originally Opened in 1931 New School Opened in 2008

Page 2: Audenried High School

Project Specifics

• School District Capital Improvements Project• Multi-Prime Contract• 211,515 s.f. Building Budgeted at $62.5 Million

Dollars• Project included the demolition of the existing

structure, land enhancement, construction of two gyms, cafeteria, auditorium, three story classroom wing, library, diesel academy, six science labs, music academy, and a culinary school.

Page 3: Audenried High School

Earth Works/ Reconditioning the Land

Page 4: Audenried High School

Architectural Plans

Page 5: Audenried High School

Steel and Foundation Work

Page 6: Audenried High School

Concrete Progress and Steel Erection Process

Page 7: Audenried High School

Concrete Arch Work Main Gym

Page 8: Audenried High School

Exterior Façade Work

Page 9: Audenried High School

Interior Finish Work

Page 10: Audenried High School

Project Responsibilities

• QA/QC throughout the design, shop drawing, and construction process

• RFI, COR, and RFP recommendations and review.• Overall Coordination of the Project• Maintaining all project correspondences• Ensured Site Safety with owner supplied policy• Ensured schedule compliance• Reviewed and processed payment applications• Ensured Contact compliance throughout the projects

duration.• Provided monthly reports on progress.