Page 1: Case study 50 m Steel Structure CSP jamshedpur

50M PEB Erectioncsp-jamshedpur

Page 2: Case study 50 m Steel Structure CSP jamshedpur

Step 1 – Assembly of 2 rafters with bracings on ground

Page 3: Case study 50 m Steel Structure CSP jamshedpur

Step 2 – Erection of columns under suspended rafter

Page 4: Case study 50 m Steel Structure CSP jamshedpur

Step 3 – Lifting of Assembled unit up to 43 mtr height

Page 5: Case study 50 m Steel Structure CSP jamshedpur

Step 3 – cont….Lifting of Assembled unit up to 43 mtr height

Page 6: Case study 50 m Steel Structure CSP jamshedpur

Step 3 – cont….Lifting of Assembled unit up to 43 mtr height

Page 7: Case study 50 m Steel Structure CSP jamshedpur

Step 4 – Swing to Position at 43 mtr height

Page 8: Case study 50 m Steel Structure CSP jamshedpur

Step 5 – Positioning

Page 9: Case study 50 m Steel Structure CSP jamshedpur

Step 6 – Bolting at 36 mtr height

Page 10: Case study 50 m Steel Structure CSP jamshedpur

Step 7 – Releasing load from Crane

Page 11: Case study 50 m Steel Structure CSP jamshedpur

Step 7 – Erection Complete