CHEC 270 FIRE DRILL 13.3.2012 11:40 – 12:30

CHEC HK TKO Site Fire Drill

Embed Size (px)

DESCRIPTION

Fire Drill

Citation preview

Page 1: CHEC HK TKO Site Fire Drill

CHEC 270FIRE DRILL13.3.2012

11:40 – 12:30

Page 2: CHEC HK TKO Site Fire Drill

Pre-drill MeetingExplaining the purpose and procedure of the drill to all sub-contractor, staff, and client representatives.

Page 3: CHEC HK TKO Site Fire Drill

On-spot indication of Fire muster point with sub-contractors , staff and client.

Fire MusterPoint

Page 4: CHEC HK TKO Site Fire Drill

FIRE ALARM RANG (IN VARIOUS LOCATIONS) &STAFFS START TO EVACUATE

Page 5: CHEC HK TKO Site Fire Drill

After checking all staffs had left, safety officer closed the entrance before he left the site office.

Page 6: CHEC HK TKO Site Fire Drill

Workers & staffs from different locations rushed to the muster-point .

Page 7: CHEC HK TKO Site Fire Drill

Appointed Fire warden arrived earlier and waiting for their workers.

Workers arrived and sign for

their attendance

Page 8: CHEC HK TKO Site Fire Drill

BRIEFING ABOUT THE PROCEDURES & IMPORTANCE OF THE DRILL

Page 9: CHEC HK TKO Site Fire Drill

Workers, staffs & client listened very carefully.

Page 10: CHEC HK TKO Site Fire Drill

RESCUE DRILL STARTED after FIRE DRILL Section.Explaining the scenario of the drill:A staff hurt her forearm during evacuation. First aider was called to provide First treatment before sending the injured to hospital for further medical treatment.

Page 11: CHEC HK TKO Site Fire Drill

FIRST AID TREATMENT WAS CONDUCTED

Page 12: CHEC HK TKO Site Fire Drill

After first-aid treatment, the injured was waiting for delivery to hospital; while the contract car arrived in 3 minutes and take the injured for further medical treatment.

Page 13: CHEC HK TKO Site Fire Drill

After Q/A section, the HSE manager thanks everybody’s participation and announced the completion of the drill. All attendees were released. The time was: 12:30

Page 14: CHEC HK TKO Site Fire Drill

FINDING & RECOMMENDATIONS The ‘fire’ started at 11:40 and all workers /staffs / clients

gathered at 11:56 upon their signing of attendance. (143 had signed for their attendance)

The timing can be controlled better, it was expected to be under 10 minutes as the site area is not that big and muster point is not remote.

Recommended by Mr. Matthew Lau that more manual alarm should be set up in site area.

Demonstration of using fire extinguisher can be arranged next time.

Page 15: CHEC HK TKO Site Fire Drill

THE END

Thanks forwatching

Prepared by: Anson Wong & Herman Cheung