Deconstruct UK case study for Dangerous Structures.
Client: LinbrooksLocation: Habidashers School, Deptford
Contractor: Deconstruct UK LtdCompletion Date: April 2011Sector: Dangerous Structures
About the Project:
Deconstruct make safe structures following catastrophic fire at a Deptford school.
This structure had suffered a catastrophic fire duringa construction refurbishment package.
Deconstruct were required to retain as much of the structure as possible whilst ensuring structures were made safe over external public footpaths and roadways, and to permit safe access for surveys and the eventual re-building programme.
These works took two weeks to safely complete.
Project Challenges:
Ensuring all cordons and points of access protected operatives involved in the works and pedestrians external to the works.
Removing high level structures from within man riders suspended from mobile cranes.
Temporarily supporting un-safe structures to enable safe access. Clearing significantlevels of built up internal debris via 2000 litreboat skips into waiting bulk containers.
Ensuring controlled collapses do not effect structures to be retained. Managing the environmental effect of the works on the surrounding properties.
Services provided by Deconstruct UK:
Our services:
Deconstruction Services ✓
Demolition Services ✓
Enabling Works ✓
Asbestos Removal Services
Asbestos Surveying Services
Ground Works Services
Piling Services
Steelwork Installations
Builders Works
Emergency Dangerous Structures ✓Temporary Works ✓
Contact Details:
Deconstruct (UK) LimitedSilver House, 31-35 Beak StreetLondonW1F 9DPTel: 020 7734 6655Fax: 020 7734 6626
Email [email protected] Address www.deconstructuk.com
For more information about this case study, visit our case studies page here: www.deconstructuk.com