49

E09 How to complete the incurred cost proposal with success!

Embed Size (px)

Citation preview

Page 1: E09 How to complete the incurred cost proposal with success!
Page 2: E09 How to complete the incurred cost proposal with success!

How To Complete the Incurred Cost Proposal with Success!

Breakout Session # E09Robert E Jones Advisor LeftRobert E. Jones, Advisor, Left Brain Professionals Inc.Suzanne Camden, Accounting, gManager, Colonna's Shipyard, Inc.Tuesday, July 29, 20142:30 PM to 3:45 PM2:30 PM to 3:45 PM

Page 3: E09 How to complete the incurred cost proposal with success!

What is the Incurred Cost Proposal?What is the Incurred Cost Proposal?• Annual reconciliation of contractor's cost

incurred including– Direct costs– Indirect costs

3

Page 4: E09 How to complete the incurred cost proposal with success!

How Do I Know If It Applies to Me?How Do I Know If It Applies to Me?• FAR 52.216-7• If you have, have had, or ever intend to

have cost-reimbursable and flexibly priced y pcontracts, this applies to you.

4

Page 5: E09 How to complete the incurred cost proposal with success!

How Do I Know If It Applies to Me?How Do I Know If It Applies to Me?

5

Page 6: E09 How to complete the incurred cost proposal with success!

When Is It Due?When Is It Due?• Six months after the close of the

contractor's fiscal year– For contractor's on a calendar year – June 30

6

Page 7: E09 How to complete the incurred cost proposal with success!

PitfallPitfall• Late Submission!

TipTip• Prior to the due date, contractors can

contact their cognizant DCAA office incontact their cognizant DCAA office in writing to request an extension to file their submission at a later timesubmission at a later time.

7

Page 8: E09 How to complete the incurred cost proposal with success!

When Will It Be Evaluated?When Will It Be Evaluated?• Supposed to evaluated for adequacy

immediately

• It is DCAA policy to audit as promptly as possible after submissionpossible after submission

8

Page 9: E09 How to complete the incurred cost proposal with success!

ResourcesResources• Raytheon ASBCA Case

• http://www.asbca.mil/Decisions/2012/57576_57679%20Raytheon%20Company%2012.17.13%20PUBLISH.pdf

9

Page 10: E09 How to complete the incurred cost proposal with success!

Takeaway #1Takeaway #1• It's never too early to start!

10

Page 11: E09 How to complete the incurred cost proposal with success!

What Types of Contracts?What Types of Contracts?• Cost-reimbursable and flexibly priced

receive the most attention• Fixed price contracts are still documented p

in the submission

11

Page 12: E09 How to complete the incurred cost proposal with success!

Where Is It Submitted?Where Is It Submitted?• Cognizant DCAA Office

12

Page 13: E09 How to complete the incurred cost proposal with success!

How Is It Submitted?How Is It Submitted?• Preferred method is electronic• Submit in both softcopy Excel and pdf

format

13

Page 14: E09 How to complete the incurred cost proposal with success!

How Is the ICP Used?How Is the ICP Used?• To determine your final indirect rates for

true-up of billings used in interim billing rates (or forward pricing rate agreements)

• FAR 42.1701 provides for systematic review and monitoring of rates.g

14

Page 15: E09 How to complete the incurred cost proposal with success!

What Kind of Information is Required?What Kind of Information is Required?• Financial and contract data.• Contractor format is acceptable, though

DCAA does provide the ICE Model, as an p ,example.

15

Page 16: E09 How to complete the incurred cost proposal with success!

How Are You Going to Help ME?How Are You Going to Help ME?• We cannot cover everything in an hour, but

we will give a brief explanation of each schedule and provide practical tips and tricks you can use in your organization.

16

Page 17: E09 How to complete the incurred cost proposal with success!

Takeaway #2Takeaway #2• Avoid the pitfalls and pay attention to

common deficiencies• Missing or unidentifiable schedules• Missing documentation

17

Page 18: E09 How to complete the incurred cost proposal with success!

Start FreshStart Fresh• Download the ICE model from the DCAA

website• Use the Quick Start instructions tab to

complete the Setup tab• Click the “Run Setup” buttonClick the Run Setup button• Compare the set-up version with last

year’s submission to ensure that theyear s submission to ensure that the correct pools are accumulating

18

Page 19: E09 How to complete the incurred cost proposal with success!

Start FreshStart Fresh

19

Page 20: E09 How to complete the incurred cost proposal with success!

Schedule ASummary of Indirect Expense Rates• No data entry is required on this schedule• This schedule completes itself with

information populated in other tabsp p• Final rates are developed by formulas

embedded in the spreadsheetembedded in the spreadsheet

20

Page 21: E09 How to complete the incurred cost proposal with success!

Schedule ASummary of Indirect Expense Rates

21

Page 22: E09 How to complete the incurred cost proposal with success!

Schedule B, C, DIndirect Cost Pools• B – G&A Pool Costs• C – Overhead Pool Costs (up to 5)• D – Intermediate Pool Costs (up to 6)D Intermediate Pool Costs (up to 6)• It will all keep coming back to your trial

balancebalancePitfall• Missing disclosure of intermediate pools and

R&D and B&P not fully burdened

22

Page 23: E09 How to complete the incurred cost proposal with success!

FringegSpecial Use Tab

• Used to allocate fringe costs• Used to allocate fringe costs • Enter all fringe accounts and costs on the

h d lschedule

23

Page 24: E09 How to complete the incurred cost proposal with success!

Schedule EClaimed Allocation Bases• How you allocate your indirect pools

• Total Labor• Direct LaborDirect Labor• Square Footage

# f t k d• # of network drops• No data entry on this schedule.

Common deficiency - unallowable costs not

24

yincluded in G&A base

Page 25: E09 How to complete the incurred cost proposal with success!

Schedule FCost of Money

• Federal agencies are required to use interest rates computed under the criteria established by the Renegotiation Act of 1971 (P.L. 92-41).

• Contract Dispute Act of 1978 (P.L. 95-563) and the Prompt Payment Act (P.L. 97-177) p y ( )provide for interest due on claims at a rate established by the Secretary of the Treasury y y ypursuant to 31 U.S.C. 3902(a).

25

Page 26: E09 How to complete the incurred cost proposal with success!

Schedule FCost of Money• Rates are published in the Federal Register

• http://www.fms.treas.gov/prompt/rates.html• COM rate posted twice a year. Use the p y

average for the FCOM calculation• Average NBV of assets * COM / allocationAverage NBV of assets COM / allocation

base = FCOM• Optional Add an F 1 tab to include the• Optional – Add an F-1 tab to include the

NBV calculations and detail

26

Page 27: E09 How to complete the incurred cost proposal with success!

Schedule GBooked and Claimed Direct Costs• Direct labor• Materials• TravelTravel• ODC

S b t t• Subcontracts

27

Page 28: E09 How to complete the incurred cost proposal with success!

Schedule HDirect Costs by Contract at Claimed Rates• Direct costs by contract type. Spreadsheet

applies OH and G&A based on your claimed amounts.

TipTip• Populate your database with task name,

contract or PO number and company taskcontract or PO number, and company task during set up.

28

Page 29: E09 How to complete the incurred cost proposal with success!

Schedule H-1Government Participation by Pool• The purpose of this schedule is to provide

a general overview of the extent that cost-type and flexibly priced contracts participate in the absorption of indirect expenses.

• Populated by data from other schedules.

29

Page 30: E09 How to complete the incurred cost proposal with success!

Schedule ICumulative Allowable Cost Worksheet• All claimed and unsettled direct and

indirect costs for contracts that cross years.

PitfallPitfall• Government participation not calculated

for all indirect ratesfor all indirect rates

30

Page 31: E09 How to complete the incurred cost proposal with success!

Schedule JSubcontract Information• Detailed information on all subcontracts

PitfallPitfall• Physically complete contracts not listed

31

Page 32: E09 How to complete the incurred cost proposal with success!

Schedule KHours and Amounts on T&M Contracts Pitfall• Invoiced hours do not add up and/or

balanceTip• Institute an invoicing format for T&M• Institute an invoicing format for T&M

invoices that includes cumulative totals for both hours and amounts for each laborboth hours and amounts for each labor category for the period, contract, and year

32

Page 33: E09 How to complete the incurred cost proposal with success!

Schedule L Payroll Reconciliation • Reconciles all labor accounts to 940/941

filings• Make sure all labor accounts are marked

as such to allow easy identification for this reconciliation.

33

Page 34: E09 How to complete the incurred cost proposal with success!

Schedule LPayroll ReconciliationPitfall• Most difficult of all the schedules to

balance• Accounts that do not balanceTipTip• Make sure accounts that are not labor are

l k d th t th t t l blocked so that they cannot accept labor.

34

Page 35: E09 How to complete the incurred cost proposal with success!

Schedule MAccounting/Organization Changes• Significant changes to accounting

organization or system such as new or redefined cost pools, implementation of new software, mergers and acquisitions, approved billing rates, etc.

35

Page 36: E09 How to complete the incurred cost proposal with success!

Schedule N Certificate of Indirect Costs• Certification by VP or CFO• This page has to be printed, signed, and

added to the scanned copy of the pysubmission

PitfallMi i tifi ti• Missing certification

36

Page 37: E09 How to complete the incurred cost proposal with success!

Schedule OContract Closing Information• Information on T&M and Cost Type

Contracts• Requires a closing date be established.q g• No links to any other schedules.

Pitfall• Failing to report a contract closed

37

Page 38: E09 How to complete the incurred cost proposal with success!

Supplemental SchedulesSupplemental Schedules• Supplemental Schedules A, B, C, and D

are Optional• They are not required for the submission of y q

the ICE• The information is required to complete theThe information is required to complete the

audit• The schedules are a helpful means to• The schedules are a helpful means to

provide the data in a useful format

38

Page 39: E09 How to complete the incurred cost proposal with success!

Supplemental SchedulesA-1 to A-4• Comparative analysis of indirect expense

pols detailed by account to prior fiscal year and budgetary data

• A-1 Overhead• A-2 G&AA 2 G&A• A-3 Indirect Cost Pools

A 4 Di t C t• A-4 Direct Costs

39

Page 40: E09 How to complete the incurred cost proposal with success!

Supplemental B

• General organizational information and executive compensation for the five most highly compensated executives

• Not required for public companies as it fallsNot required for public companies as it falls under FPDS. FAR 52.204-1

40

Page 41: E09 How to complete the incurred cost proposal with success!

Supplemental C

• Identification of prime contracts under which the contractor performed as a subcontractor

• Lists of ACOs and PCOs for each flexibly priced contractp

41

Page 42: E09 How to complete the incurred cost proposal with success!

Supplemental OContract BriefingsTip• Consider adding this schedule to the

contract kick-off process. It will greatly aid p g yin completing this process at year end.

• Good standard information for a contractGood, standard information for a contract folder in a consolidated format

42

Page 43: E09 How to complete the incurred cost proposal with success!

PenaltiesFAR 42.709• Claiming expressly unallowable items

43

Page 44: E09 How to complete the incurred cost proposal with success!

Takeaway #3Takeaway #3• Start with the end in mind!

44

Page 45: E09 How to complete the incurred cost proposal with success!

Resources

• DCAA ICE Model • http://www.dcaa.mil/ice_model.html• DCAA Guidelines for ICE AdequacyDCAA Guidelines for ICE Adequacy• http://www.dcaa.mil/Guide_for_Determin

ing Adequacy of Contractor Incurred Coing_Adequacy_of_Contractor_Incurred_Cost_Proposal.pdf

45

Page 46: E09 How to complete the incurred cost proposal with success!

ResourcesContinued• Help for Small Businesses• http://www.dcaa.mil/small_business/Incu

rred Cost Submissions.pdf_ _ p• DCAA Memo - Treatment of Delinquent

Final Indirect Rate ProposalsFinal Indirect Rate Proposals• http://www.dcaa.mil/mmr/14-PPD-

002 pdf002.pdf

46

Page 47: E09 How to complete the incurred cost proposal with success!

3 Takeaways3 Takeaways• It's never too early to start• Avoid the pitfalls and pay attention to

common deficiencies• Start with the end in mind

47

Page 48: E09 How to complete the incurred cost proposal with success!

QuestionsQuestions

Robert E. [email protected](513) 728-1163( )

Suzanne Camdensuzannecamden@hotmail [email protected](757) 572-1716

48

Page 49: E09 How to complete the incurred cost proposal with success!

49