30
The WindFloat Project WindFloat 2 MW Floating Offshore Wind Coimbra, 19 th of November, 2013 Pedro Valverde EDP Inovação

Fórum Portugal Energy Power: The WindFloat Project - EDP

Embed Size (px)

Citation preview

Page 1: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project

WindFloat 2 MW Floating Offshore Wind

Coimbra, 19th of November, 2013

Pedro Valverde

EDP Inovação

Page 2: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 2

1. Why Floating Offshore Wind?

2. WindFloat Technology

3. The WindFloat Project

4. Preliminary performance analysis

5. Conclusions

Agenda

Page 3: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 3

Why Floating Offshore Wind?

Why Offshore Wind?

• Higher wind resource and less turbulence

• Large ocean areas available

• Best onshore wind locations are becoming scarce

• Offshore wind, including deep offshore, has the capacity to deliver large amount of energy

Why Floating Offshore Wind?

• Limited locations with shallow waters (mostly in the North Sea)

• Most of the offshore wind resource is in deep waters

• Unlimited installation sites available

• Less restrictions for offshore deployments and reduced visual impacts

• Enormous potential around the world: PT, Spain, UK, France, Norway, Italy, the Americas, Asia …

Page 4: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 4

1. Why Floating Offshore Wind?

2. WindFloat Technology

3. The WindFloat Project

4. Preliminary performance analysis

5. Conclusions

Agenda

Page 5: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 5

The main characteristics of the WindFloat leads to High Stability even in rough seas

The WindFloat Technology

Turbine Agnostic

• Conventional turbine (3-blade, upwind)

• Changes required in control system of the turbine

High Stability Performance

• Static Stability - Water Ballast

• Dynamic Stability - Heave Plates and active ballast system

- Move platform natural response above the wave excitation (entrained water)

- Viscous damping reduces platform motions

• Efficiency – Closed-loop Active Ballast System

Depth Flexibility (>40m)

Assembly & Installation

• Port assembly – Reduced risk and cost

• No specialized vessels required, conventional tugs

• Industry standard mooring equipment

Page 6: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project6

The WindFloat…

… requires NO PILLING

…is structurally decoupled from seadbed

…is independent from depth

…is assembled and commissioned quayside

…does NOT require high lift capacity vessels

Due to the features of the WindFloat, the risk and cost of offshore works is significantly reduced

The WindFloat Technology

Reduced Risk and Cost

Page 7: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 7

Total displacement of the WindFloat is 2.750 ton. Total weight of the hull is 1.200 ton

The WindFloat Technology

Structure Dimensions

Page 8: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 8

WindFloat technology development – derived from an O&G concept and is now being tested full scale at sea

The WindFloat Technology

May

20

09

July

20

09

Wave tank testing of 1:67th

scale WindFloat model at University of California, Berkeley tow tank

EDP initiates the WindFloat Project with the demonstration of a WindFloat unit with 2MW wind turbine generator grid connected to be installed in Aguçadoura

Sep

tem

ber

20

08 Wave tank

testing of 1:96th scale WindFloat model at University of California, Berkeley tow tank

Jan

uar

y 2

00

9

EDP and Principle Power sign MOA for phased development of WindFloat technology and commercial deployment of a wind farm up to 150MW

MI&T performs Minifloat proof of conceptmodel tests

Jan

uar

y 2

00

3

Jun

e 2

00

3

MI&T files Minifloat patent 1

Wave tank testing of Minifloat I & II concept

Jan

uar

y 2

00

4

Jun

e 2

00

4

Wave tank testing of 1:96th scale Minifloat IV concept at University of California, Berkeley tow tank

Minifloat patent 1 issued US7086809, Minifloat patent 2 filed

Au

gust

20

06

Au

gust

20

06

Wave tank testing of 1:80th scale Minifloat III concept at Oceanic

Minifloat patent 2 isssued US7281881

Mar

ch 2

00

7

Jun

e 2

00

8

Principle Power exclusively licenses WindFloat intellectual property from MI&T

Ap

ril 2

00

9 Principle Power purchases outright all intellectual property for WindFloat from MI&T

Dec

emb

er 2

01

1

First electron at Aguçadoura

Page 9: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 9

1. Why Floating Offshore Wind?

2. WindFloat Technology

3. The WindFloat Project

4. Preliminary performance analysis

5. Conclusions

Agenda

Page 10: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project

Phase 1 – Demonstration

Capacity: 2MW WindFloat prototype

Location: Aguçadoura, grid connected

~6 km of coast, 40 - 50 m water depth

Turbine: 2MW offshore wind turbine

Test period: 24+ months

Phase 2 - Pre-commercial

Capacity: ~27MW (~5 WindFloat units)

Location: Portuguese Pilot Zone

Turbine: Likely Vestas and other, Multi MW

Phase 3 - Commercial

Capacity: 150MW, gradual build-out

Location: TBD

Turbine: TBD

10

The WindFloat project is structured to follow a phased / risk mitigation approach

The WindFloat Project

Page 11: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 11

The Project is promoted by…

…in a joint venture…

…and counts with the support of…

The WindFloat project was structured as a Joint Venture, WindPlus

The WindFloat Project

WindPlus

Page 12: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project

The project followed a risk mitigation approach but…

…the challenges were enormous…

…project being done for the first time

…Lack of offshore know-how in Portugal

…different cultures involved(US, Denmark, Portugal, France)

…Collaboration between two different industries that have never worked together (Oil & Gas and Wind Industry)

… Standards & Rules for design exist but need to adapted

12

The development of the WindFloat project carried enormous challenges due to the lack of know-how in Portugal

The WindFloat Project

Page 13: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 13

The project followed the typical stages of an engineering project

The WindFloat Project

Pre-FEED

Scope Definition

Design Basis

Engineering

Risk Mitigation Activities

Scope and Prel. Eng. Defined?

FEED

Site detailed charact.

Detailed Eng.

Drawings & Philosophy

FEEDDefined?

Project Execution

Detailed Drawings & Construction Drawings

Equipment Procurement

Fabrication & Installation

Project Planning

Page 14: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 14

Effective Risk Management must be embed into the project since the very early beginning

The WindFloat Project

Risk Management methodologies implemented through out the project were key for the success of the project

• HAZID – Hazard Identification Study

• Conducted at an early stage of the project

• Focus in the Project Execution stage

• Provided inputs to the FEED stage

• HAZOP – Hazard and Operability Study

• Several workshops conducted during FEED

• Participants were the teams involved in the activities and engineering team

• Provides input to the FEED stage

• HIRA – Hazard Identification and Risk Assessment

• Workshop conducted prior to execution of the activities

• Plan and procedures of each activities already defined

• Outcome provides inputs to reduce the risk while executing the activities

Page 15: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 15

The project was implemented under a tight scheduled

The WindFloat Project

Task Timeline

Project Start

Pre-FEED

PDR

FEED

Turbine Selection

Final Investment Decision

Project Execution

Detail Design

Fabrication

Offshore Installation

Offshore Commissioning

Testing and Monitoring

Sep, 09

Jan, 10

Sep, 10

Sep, 11 May, 11

Nov, 11

Dez, 11

Ago, 13

Sep, 11

Sep, 11

Project was completed in less than 2,5 yearsFabrication completed in less than 9 months

Significant space to improve project implementation schedule!

Page 16: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 16

Workshop Fabrication of main components

A. Silva Matos was the responsabilbe for the

fabrication of the WindFloat

Page 17: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 17

Pre-assembly of the columns

outside the Dry-dock in Setúbal

Page 18: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 18

Columns moved to Dry-dock

Page 19: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 19

Dry-dock assembly

Page 20: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 20

Mooring Pre-Lay in parallel

with the fabrication

Page 21: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 21

Turbine Installation in the Dry Dock using the

shipyard’s gantry crane

Page 22: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 22

Tow from Setúbal to Aguçadoura (~400 km) using the

same vessel that was used for the mooring installation

Page 23: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 23

Hook-up at final location

Page 24: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 24

Energy delivery since December 2011!

More than 7,9 GWh produced up today!

Page 25: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 25

1. Why Floating Offshore Wind?

2. WindFloat Technology

3. The WindFloat Project

4. Preliminary performance analysis

5. Conclusions

Agenda

Page 26: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 26

The WindFloat is monitored 24 hours a day remotely

Preliminary performance analysis

Page 27: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 27

Survivability and performance proved in normal and extreme conditions

Preliminary performance analysis

22 Oct 2011

Installation complete

01 Nov 2011

15 meters wave

23 Dec 2011

First Electron produced

03 Jan 2012

Operation in Hs=6m and

Hmax=12,6m

Page 28: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 28

1. Why Floating Offshore Wind?

2. WindFloat Technology

3. The WindFloat Project

4. Preliminary performance analysis

5. Conclusions

Agenda

Page 29: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 29

• The fabrication and installation were successfully complete despite all the challenges faced

• The technical results of the first 6 months of operation of the WindFloat are very promising

• The testing and monitoring of the WindFloat will continue during the next years

• WindPlus will start to prepare the Pre-Commercial phase

• One step towards the development of deep offshore wind

Conclusions

Page 30: Fórum Portugal Energy Power: The WindFloat Project - EDP

The WindFloat Project 30

Thank you!