7
© 2006, Sheikh Nisar Ahmed 1 / 7 From Chaos to Success: An Experience of a Lifetime on Citizen Registration Project in Pakistan. Author: Sheikh Nisar Ahmed, CEO, MSCL Background With a current population of 180 million, Pakistan has faced many challenges and problems since its birth in 1947. One of the key problems has been the influx of refugees and illegal immigrants . Whatever happened around it, whether it’s war in Afghanistan, or revolution in Iran, or change of government in Burma, the displaced population always found in Pakistan a safe heaven, got themselves registered as locals and acquired Pakistani ID Cards and Passports. Many of them adopted Pakistan as permanent home. This has placed an additional burden on Pakistan’s already weak economy and has created many social and sec urity problems. Realizing the seriousness of this problem, The Government of Pakistan (GoP) decided to launch a project of electronic registration of the whole population of Pakistan. In 1994, the Ministry of Interior (MoI), GoP visualized a project with a mission to eliminate forgery in the issuance of National ID cards (NICs) and passports, and bring illegal immigration under control. The project was conceptualized and scoped as the largest IT project to be handled in the history of Pakistan and was perceived as a great technical and Project Management challenge. Many countries with better economies and environments have still not ventured to take up such projects. The project was initially awarded to IBM Pakistan in September 1996. However with the change of government the contract with IBM was terminated in September 1997 and it was decided that MoI should deliver the project. For this purpose the National Database & Registration Authority (NADRA) was established with the objective of introducing a new, improved and modernized registration system for the entire population. Culminating, among other things, was the issuance of secured National Identity Cards (NICs) to all adult citizens (70 million) backed by the Citizens' National Data Warehouse (NDW). Initially NADRA failed and the project turned into chaos. This chaotic phase lasted for more than two years. At one stage the project was on the verge of collapse. However, NADRA was reorganized at the right time and the right people were assigned right jobs. Dedicated work with commitment was put in to convert this RED project to GREEN. The project is now out of chaos. The symptoms of success are visible. The project has become highly visible both within and outside Pakistan. This paper discusses project scope, goals and objectives. It also analyzes what went Wrong, what went Right and Project Management principles that were violated. A discussion on Lessons learnt is also included. Authentic registration of citizens is the need of the time, those interested in implementing similar project in public sector can benefit from this paper. Project Goals and Objectives The overall project goal was to eliminate illegal immigration by timely detection of errors and forgery in the registration of citizens. To achieve this goal the following objectives were outlined. a. Redefine the processes for citizen registration and issuance of NICs to eliminate registration of aliens. b. Establish facilities and implement systems across the country to register the entire population. c. Create a National Data Warehouse (NDW) ensuring that this NDW can be used for future implementation of modern passport, border control, driving license, taxation and other related applications. d. Issue NICs that can not be tampered with, to all registered adult population. e. Establish nation wide networks that will enable access of NDW to authorized applications and users. f. Train government staff to ensure efficient use of new systems. g. Generate mass awareness among the population on the benefits and importance of getting themselves registered. The Project Scope The project entailed logistics of information management and control that were unprecedented for IT projects ever done in Pakistan. It required a complete range of services from voluminous historical data capture to

From chaos to success

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: From chaos to success

© 2006, Sheikh Nisar Ahmed 1 / 7

From Chaos to Success: An Experience of a Lifetime on Citizen Registration Project in

Pakistan. Author: Sheikh Nisar Ahmed, CEO, MSCL

Background

With a current population of 180 million, Pakistan has faced many challenges and problems since its birth in

1947. One of the key problems has been the influx of refugees and illegal immigrants. Whatever happened

around it, whether it’s war in Afghanistan, or revolution in Iran, or change of government in Burma, the

displaced population always found in Pakistan a safe heaven, got themselves registered as locals and acquired

Pakistani ID Cards and Passports. Many of them adopted Pakistan as permanent home. This has placed an

additional burden on Pakistan’s already weak economy and has created many social and security problems.

Realizing the seriousness of this problem, The Government of Pakistan (GoP) decided to launch a project of

electronic registration of the whole population of Pakistan.

In 1994, the Ministry of Interior (MoI), GoP visualized a project with a mission to eliminate forgery in the

issuance of National ID cards (NICs) and passports, and bring illegal immigration under control. The project

was conceptualized and scoped as the largest IT project to be handled in the history of Pakistan and was

perceived as a great technical and Project Management challenge. Many countries with better economies and

environments have still not ventured to take up such projects.

The project was initially awarded to IBM Pakistan in September 1996. However with the change of government

the contract with IBM was terminated in September 1997 and it was decided that MoI should deliver the project.

For this purpose the National Database & Registration Authority (NADRA) was established with the objective

of introducing a new, improved and modernized registration system for the entire population. Culminating,

among other things, was the issuance of secured National Identity Cards (NICs) to all adult citizens (70 million)

backed by the Citizens' National Data Warehouse (NDW).

Initially NADRA failed and the project turned into chaos. This chaotic phase lasted for more than two years. At

one stage the project was on the verge of collapse. However, NADRA was reorganized at the right time and the

right people were assigned right jobs. Dedicated work with commitment was put in to convert this RED project

to GREEN. The project is now out of chaos. The symptoms of success are visible. The project has become

highly visible both within and outside Pakistan.

This paper discusses project scope, goals and objectives. It also analyzes what went Wrong, what went

Right and Project Management principles that were violated. A discussion on Lessons learnt is also

included. Authentic registration of citizens is the need of the time, those interested in implementing

similar project in public sector can benefit from this paper.

Project Goals and Objectives

The overall project goal was to eliminate illegal immigration by timely detection of errors and forgery in the

registration of citizens. To achieve this goal the following objectives were outlined.

a. Redefine the processes for citizen registration and issuance of NICs to eliminate registration of aliens.

b. Establish facilities and implement systems across the country to register the entire population.

c. Create a National Data Warehouse (NDW) ensuring that this NDW can be used for future

implementation of modern passport, border control, driving license, taxation and other related

applications.

d. Issue NICs that can not be tampered with, to all registered adult population.

e. Establish nation wide networks that will enable access of NDW to authorized applications and users.

f. Train government staff to ensure efficient use of new systems.

g. Generate mass awareness among the population on the benefits and importance of getting themselves

registered.

The Project Scope

The project entailed logistics of information management and control that were unprecedented for IT projects

ever done in Pakistan. It required a complete range of services from voluminous historical data capture to

Page 2: From chaos to success

© 2006, Sheikh Nisar Ahmed 2 / 7

intelligent data entry, scanning, image capture, software development, system integration, documentation, mass

training, procurement, process re-engineering to project management services.

Initially the project envisaged the establishment of Computer Centers at 113 districts for registration of citizens

and NIC distribution, Card Production Centers (CPCs) in 18 Divisional head quarters, Regional Computer

Centers (RCCs) in four Provincial Headquarters, National Computer Center in Islamabad for housing the NDW.

A project management approach, which will ensure timely and effective implementation of this project, was

required. The scope included implementation of networking and related systems across the country.

Figure -1 below depicts the infrastructure to be created.

Figure – 1: Infrastructure to be created across the country.

The Project Stages

The whole project (i.e. work already done and work to be done) can be presented as three Staged project. See

figure 2 below.

T I M E

Figure - 2: The project lifecycle depicting three stages of the project

Stage 1: “Project definition”

In March 1996 GoP invited IBM Pakistan to define the project inline with defined goals and objectives and

present solution. IBM submitted the proposal in May 1996. The proposal was accepted as a proprietary solution.

After initial Project Assurance and Risk Assessment by IBM Global Services, IBM submitted the contract in

June 1996.The contract was accepted and signed on 12th

September 1996 as a single sourced, without

following GoP’s tendering process. This was considered a big success for IBM Pakistan’s marketing unit.

IBM appointed the Project Manager who created a project organization within one month. We call this stage a

“Project Definition” Phase because during this stage detailed project plan including all subsidiary plans were

prepared, project framework was confirmed, most of the project management processes were defined,

Page 3: From chaos to success

© 2006, Sheikh Nisar Ahmed 3 / 7

agreement was reached to use existing operational processes, responsibility metrics were finalized, complete

solution including process model, database model and network model were defined and pilot tested. In other

words all work necessary to define a project in detail was accomplished by IBM and accepted by the Client.

The IBM project team adopted its proven “MMaannaaggiinngg tthhee IImmpplleemmeennttaattiioonn ooff tthhee TToottaall PPrroojjeecctt

(MITP)”methodology for managing this project. The project initiation was very well planned and effective. The

project was soon visible to all concerned and tremendous interest was generated among stakeholders.

The project sponsor was no less than the Prime Minister of the country. Her commitment was driving the client

(i.e. GoP) organization to support this project. The opponents of the project had no option but to keep quiet.

Initial milestones were achieved within schedule and within budget. It seemed the project was heading towards

great success.

The government changed in November 1997. The new government stalled most on-going projects, including

this project. IBM managed to meet new Interior Minister after great difficulty. In the first meeting it was

obvious that the project had lost the sponsorship. The IBM project manager reported the fact to IBM System

responsible for managing IBM Global Services projects worldwide. The System turned the project status from

GREEN to RED. The project assurance and risk assessment sessions were repeated. As a part of risk

containment, IBM requested GoP to reconfirm its commitment to this project. GoP first asked IBM to suspend

all work on this project and then started renegotiating the scope, terms and conditions. IBM Marketing (the same

team involved till contracting) took over the renegotiations from the project team. Fearing that refusal to accept

GoP’s position will result in the termination of the contract, IBM accepted almost all changes asked by the

Client without price increase. For almost two months there was a complete breakdown of communication

between the performing organization (i.e. IBM Project Team) and the Client (i.e. GoP Team). In the mean time

ministry of Legal Affairs started looking at the contract. Ultimately GoP terminated the contract in November

1997. The reasons given for termination were:

a. The contract was awarded bypassing GoP tendering process without any valid reasons.

b. The sensitive asset like the National Data Warehouse cannot be handed over to a foreign entity like IBM.

c. The project as defined by IBM required new legislation and constitutional changes which were not

possible within time allocated.

IBM, after legal review, accepted the termination without invoking the Dispute Resolution clause. With this

termination the Stage –1 of the project ended.

What went wrong:

IBM did not perform formal stakeholder analysis, primarily because the contracting phase was led by marketing.

The Project Manager’s appointment was delayed till signing of the contract. A tough delivery schedule and

other constraints did not allow the Project Manager to challenge and correct the over commitments. In spite of

very sound processes used, the risk assessment was conducted by experts coming from IBM headquarters with

no exposure to Pakistani public sector environment. The whole contracting process, including business case

preparation, project qualification, costing and budgeting were handled by the marketing team. Instead of using

them as a tool to develop a risk free plan; well-defined IBM Project Management processes were rushed through

to complete the formality. At that time IBM Pakistan was a small IBM unit. It was functionally organized with

marketing and finance controlling the whole business. The project organization, specially created to handle this

project was scattered. The Project Manager was not empowered to take all decisions. He was dependent on

decision makers in Headquarters in Dubai, Paris and Johannesburg.

At the Client end, no impact analysis was performed to assess what termination of the project contract would

mean in financial and business terms. Such an analysis would have saved the project from termination and thus

prevented loss to the taxpayers.

The termination of this project resulted in loss of significant revenue to IBM Pakistan. However actual loss was

restricted to less than half million US $, which was the spent cost of the project when terminated. The bigger

loser was the Client i.e. government and people of Pakistan. The project, which was to be completed in 2001,

would now be completed in 2006 at a much higher cost.

What went right?

The project offered a great learning opportunity to both IBM and the Client. The Client did not adopt any post

termination learning process and failed to gain benefits of experience. On the other hand, IBM Global Services

went through a major learning process, refined its business strategy for the Middle East region, and thus took

Page 4: From chaos to success

© 2006, Sheikh Nisar Ahmed 4 / 7

full advantage of its experience on this project. The project team, which was built and developed on this project,

was used on other IBM projects and in Middle East, Europe and Australia. This resulted in cost reduction and,

thus, business gains for IBM Global services. Such timely actions by Project Management supported by well-

defined PM processes minimized the loss to IBM.

Another major benefit to emerge from the experience was that GoP was convinced that the project was needed

and was do-able. Although the contract with IBM had been terminated, the project was kept alive and was

reinitiated through NADRA. Without the experience gained in this Stage, clarity in the requirements of the

project would not have been possible.

Stage 2: “The Chaos”

GoP established National Database Organization (NDO) in March 1998 within MoI. This organization was later

named as National Database & Registration Authority (NADRA) in March 2000. NADRA was conceived as a

huge organization of more than 3000 personnel headed by a General from armed forces. The top management

also came from armed forces, most of them IT literate but with no experience of modern project management.

NADRA was a rigid functional organization. All work that was planned was to be carried out as operational

work. NADRA managers had no clue of project management. Project planning was restricted to schedule

preparation. Project baselines, even schedules were not protected, and Change Management was missing. No

quality plan was put in place. No accurate performance evaluation and progress measurement processes existed.

There was focus on procurement and infrastructure setup, but no proper budget allocation process was put in

place. Instead “Learning from Vendors Bids” approach was adopted. Thus each Request for Proposal (RFP) was

repeated several times. As a result key solution providers lost confidence in NADRA’s bidding process. Barring

initial bids, most of the bid responses were non serious. This chaotic phase lasted almost two years. The project

faced many upheavals; it faced budget overruns, schedule slippage and mismanagement in almost all project

activities.

As the project failed to deliver, stakeholders in the government lost interest and withdrew their support. The

project was labeled as “white elephant”. The project had high visibility. Approximately data for 64 million

citizens was received for registration and 20 million applications for issuance of NICs. When they were not

delivered what was promised, opposition to the project became more vocal. The project was almost on the

verge of collapse.

Pakistan once again experienced a change in the government. The new government decided to continue all

projects, which were in the national interest. In spite of its initial failure, the NADRA project was categorized as

a project of national importance. GoP decided to continue with the project but with new management.

In October 2002, a major change in NADRA management was directed and a new chairman with full support

from GoP was appointed. With this appointment Stage 2 ended and project entered Stage 3.

What went wrong?

NADRA of Stage 2 was a Rigid Functional Organization; all powers were with the departmental head. There

was little emphasis on project management and the role of project manager was non-existent. NADRA

considered itself as a system integrator, not a project management body. Tasks involving large volumes were

initiated without pilots and without ensuring that quality control processes were in place.

Because of a lack of definition of roles and responsibilities and documentation, the accurate performance

evaluation and accountability was not possible. Progress measurement was not possible as no accurate process

was adopted for this. Nobody actually knew how much project has progressed. Whatever was achieved, failed

to meet even basic quality standards. There was no communication between IBM and NADRA. This deprived

NADRA of the advantage of IBM‘s experience on this project.

Because of NADRA’s inability to manage the project, the control fell in the hands of subcontractors and

external consultants, who had their own vested interests. This led to the division of a single well-defined project

into 5 ill-defined sub projects with no effective central organization to manage the integration of this complex

project. The stakeholders in GoP lost confidence in NADRA’s ability to deliver and the project became a bad

reference.

Page 5: From chaos to success

© 2006, Sheikh Nisar Ahmed 5 / 7

What went right?

In spite of all the chaos, some achievement was made during Stage 2 in the area of infrastructure setup. The

National Center at Headquarters in Islamabad was setup. The completely automated central NIC production

facility was created, thanks to some good work done by a select group of subcontractors. NADRA offices were

setup in all four provincial capitals with modern facilities. Facilities for mass Data Entry and Scanning were

created. A nationwide physical network was established. This infrastructure was effectively used during Stage

3.

Stage 3: “The Turnaround”

The new chairman brought with him experience of managing complex projects. He understood both the

technical and management aspects of this huge project. Initially he spent time in understanding the past

mistakes, their causes and impacts. He changed the nature of NADRA organization from rigid functional to

balanced matrix. Project Management skills were acquired through re-hiring and training. New, strong project

teams with well-defined roles and responsibilities were built. Subcontractors with good record of delivering on

this project in the first two Stages were involved. Processes for team building and Project Human Resource

management were implemented with focus on performance evaluation. Efforts were made to ensure that only

good performers were rewarded.

A basic change in the overall project strategy was made. The Central Data Warehouse strategy was adopted in

stead of Distributed Databases. In stead of “Form Filling”, it was decided to facilitate applicants to directly

provide data to the system.

More importantly, the project got the sponsor no less than President, the most powerful person in the country.

For the first time the whole adult population of the country (i.e. approximately 70 million) was accepted as

stakeholder and project plan was adjusted accordingly. Swift Registration Centers (SRCs) were established

through out the country where applicants could personally come and provide the required information, including

their signatures, fingerprints and photographs directly to the system. A Customer Relationship Management

(CRM) system was implemented where the applicants could see the status of their applications including

reasons for which the processing could not be completed. The applicants could also register the complaints

using this system. The CRM was further supplemented by Call Centers in three major cities covering most of

the urban population. A MIS was implemented which took direct input from operational systems. This helped

the management in enforcing effective control over operations.

All these resulted in a great turnaround. The project is now on the road to success. The successful completion of

this project will result in the National Data Warehouse, which will be used by not only registration and

immigration authorities but also by the taxation department, police, issuance of driving licenses, land revenue,

election commission and other government departments. This development is likely to lead Pakistan towards

Good Governance. Though long journey but seems achievable now as a result of this Turnaround.

Current Status

The careful progress analysis based on initial scope, indicates that the project is 90% complete. Most of the

infrastructure is ready. Out of an adult population of around 70 million, around 50 million have been registered

digitally. Registration of the entire population is expected to be completed by the end of 2006. Errors in

citizens’ data have been corrected and the NDW can now be used for other applications like Passport (MRP),

Immigration, Taxation, and Driving License etc. The Complaint Management System supported by CRM is

now working and helping NADRA to regain the lost confidence of stakeholders. NICs are being delivered to

applicants on time. At the end of stage 2 no body in GoP wanted to own this project. Now many will feel proud

if their name is associated with this project.

Future Challenges:

The project is not over yet. It still faces unique challenges and risks. The project needs continuous support from

GoP. The greatest risk is continuity of sponsorship. A change in government or a change in priorities at the top

level will have an impact on this project. Riding on its success, NADRA is over committing and initiating new

projects, most of these are unaligned with NADRA’s original mission. This distracts management focus from

the core project.

Page 6: From chaos to success

© 2006, Sheikh Nisar Ahmed 6 / 7

In addition, 60% of the population lives in rural areas, Out of which 25% lives in the areas with inadequate

communication facilities. Registering this population will be a daunting task. Another challenge would be to

register more than 3 million Pakistanis living overseas in more than 50 countries.

One of the basic aims of the project is to eliminate corruption. In a society riddled with the corrupt practices the

project is bound to face resistance. As use of NDW expands in departments like Taxation, Police and

Immigration this resistance will increase. NADRA must be prepared to face such challenges. Also, it must

ensure that the organization is protected from corrupt practices penetrating within its own ranks.

NADRA management is under tremendous pressure to recruit employees recommended by people in power. To

remain an effective organization NADRA must stick to its merit based HR practices.

Post Mortem and Lessons Learnt:

Different organizations have different views of the project. Since NADRA views this project from the day the

new NADRA management took over, for them it is a great success. The finance department in GoP is looking at

total cost incurred. So for them the project has overspent heavily. For IBM, the project could not be completed

successfully and it was terminated without any compensation paid, so it is a failed project. For many vendors

and subcontractors this was a profitable project as they managed to complete their part and got paid. However

as project managers, we will analyze project as a whole i.e. all three stages combined for the purpose of

post mortem and lesson learning. We will discuss the events and facts first and then lessons learnt are

summarized immediately after the discussion.

Stakeholders Analysis: A project of this size fails for multiple reasons. However, the most important

reason for the failure at stage 1 was poor stakeholder analysis by IBM. Too much attention was given to the

stakeholders who would award the contract and provide the budget. Just winning the support of the Prime

Minister in power was not enough. It was important to win support of those in opposition and the government

field staff to be involved in the implementation of the project. The Ministry of Legal Affairs and Armed Forces,

the key influencers, were not identified as stakeholders and ignored during contracting process. The reason for

this poor analysis was that whole contracting process was led by IBM Pakistan Marketing whose view of the

project did not go beyond contracting. When the government changed, all those not involved till now suddenly

occupied the positions of decision-making. The new decision makers in GoP had no interest in the project and

refused to provide support.

Lesson: Never ignore those who can negatively impact progress on the project. Turn resistance into support as

early in the lifecycle as possible.

The Project Manager - Appointment and Authority: In Stage 1, IBM Marketing led the project till the

contract was finalized. Formal project manager appointment was announced after signing of the contract. Very

tough schedule was committed. The project manager was required to act in rush and deliver, leaving no room

for reviewing initial work. The initial project risk assessment took almost all input from people involved in

marketing. The ownership of the project budget was with the CFO. The procurement was heavily dependent on

time consuming operational processes, which failed to address the uniqueness of this project. The IBM project

manager had to work within these processes, which were mostly tuned to handle routine operations. In Stage 3 i.e. the Turnaround phase the new NADRA management reviewed all work done thus far on the

project, revised processes and defined a new organization suitable for project work. They could do this because

the previous NADRA management was a failure and was also perceived as a failure by key stakeholders as well

as project sponsor. In stage 1 i.e. the IBM Phase, work done prior to the appointment of the project manager

was rated and perceived as a great work. It was thus difficult for the project manager to challenge this “great

work”.

Lesson: The project manager must review the work already done before taking over project responsibility. Seek

clarifications and resolve issues. On large projects, operational processes must be customized to suit project

requirements. The Project Manager must be involved in initial risk assessment and agree to risk containment

strategy. If not, then Project Manager must perform an initial risk assessment, understand project risks and risk

category. This should be the precondition to accepting project responsibility. It is at this stage you could be

blamed as being bureaucratic, rigid and even a business killer. Don’t worry. If you are convinced what you are

doing is right, be firm. What is at stake at this stage is your assignment. But if you give in to pressure, you are

putting both your job and reputation at stake.

Page 7: From chaos to success

© 2006, Sheikh Nisar Ahmed 7 / 7

Remember, just delivering good work is not enough, the work must be perceived as Good Work by the

stakeholders.

Managing Scope Change: In stage 1 IBM accepted demands for scope changes (increases) without

renegotiating the price. This created doubt about the fairness of the price quoted earlier and strengthened the

view of the opponents of the project. This was a fixed priced contract. With country’s average inflation rate of

10% at that time the project organization had less money for more work.

Lesson: Changes to all three baselines (Budget, Scope and Schedule) must be managed, negotiated and accepted

by the project organization. Project Manager must act as a custodian of project baselines especially budget. Any

undue concession given to the client must be supported through Management Reserve.”

Project Sponsorship: During Stage 1, IBM could achieve initial milestones with ease because the project

could find sponsor of right level. In spite of excellent initial project work, IBM failed later primarily because

project lost sponsor. During stage 3, one of the reasons for the turnaround was sponsor’s commitment and

support to the project.

Lesson: Every project must have a Sponsor who would own and defend the project. No fun in wasting time and

resources on the project, that fails to find the Sponsor.

Project Visibility: While it is advisable that your project is visible, but this may not be true in case of public

sector projects in countries like Pakistan. Almost all large projects have support and face resistance. As a project

progresses, it experiences schedule slippage and overspending and the resistance becomes stronger and vocal.

The higher is the project visibility the stronger is the resistance. This is exactly what happened with the NADRA

project in first two stages. This distracts project management from core project activities to expectation

management, issues handling and other non-performing activities. In Turnaround phase the new NADRA

management handled project visibility part intelligently. Only required information was shared outside project

organization. It was ensured that public announcements were made after achieving the key Milestones.

Lesson: While managing large public sector projects, avoid your temptation to be visible and media coverage.

Fame will automatically come with the success of the project.

Influence of the organizational culture and structure: In the 90s IBM Global Services in Europe and USA

was well organized to manage services business through projects. However in the Middle East and Africa most

of the business focus was on Product marketing and related after sales support services. The marketing and

finance functions enjoyed more power. The project management support for this project came from

headquarters mostly located in Europe. Most of the input to headquarter project management processes came

from Marketing and Finance functions of these countries. This resulted in poor contracting, and risk assessment

not only on this project but many others in this region. In Stage 3, NADRA organization came closer to

Balanced Matrix structure. This reorganization had significant role in turning around this failing project to

success.

Lesson: If you want to be successful in project based business, you must reorganize and move from a Functional

to a Projectized organization structure. The reorganization may be in stages. You must create the project culture

through implementation of project management processes.

Accuracy in performance evaluation of team members: One of the reasons for failure in Stage 2 was the

lack of a performance evaluation process. Annual PE was just a formality. Managers were casual while

performing evaluations. This gave employees the impression that their hard work will not help them in career

growth. Even during stage 1, in spite of very sound and accurate Career Planning and Performance Planning

processes in place, when the marketing team was awarded for closing the contract, the symptoms of unrest

amongst the project delivery team were clearly visible. This was because; by this time the team was aware of the

lapses and omissions in the contract. Project Manager had to make extra efforts to manage team morale.

Lesson: Performance Evaluation is a strong tool in the hands of the project managers. By using this tool with

accuracy, honesty and care, the success of a project can be ensured. When in doubt, postpone the award, but

never award a poor performer.