Project Progress – 28 th Dec 2013

My Home Vihanga Status as on Dec 28th 2013

Embed Size (px)

DESCRIPTION

Vihanga Status REport as on Dec 28th 2013

Citation preview

Page 1: My Home Vihanga Status as on Dec 28th 2013

Project Progress – 28th Dec 2013

Page 2: My Home Vihanga Status as on Dec 28th 2013

TOP VIEW

Page 3: My Home Vihanga Status as on Dec 28th 2013

SOUTH SIDE RETAINING WALL IN PROGRESS

Page 4: My Home Vihanga Status as on Dec 28th 2013

RETAINING WALL SHUTTERING 1ST LIFT IN PROGRESS

Page 5: My Home Vihanga Status as on Dec 28th 2013

SOUTH SIDE VIEW COLUMNS ABOVE TIE BEAM DONE,DEEP BEAM TO BE DONE CURING IN PROGRESS

Page 6: My Home Vihanga Status as on Dec 28th 2013

WEST SIDE VIEW BACKFILLING IN PROGRESS FOR DEEP BEAM

Page 7: My Home Vihanga Status as on Dec 28th 2013

WESTSIDE RETAINING WALL

Page 8: My Home Vihanga Status as on Dec 28th 2013

RETAINING WALL 1ST LIFT IN PROGRESS

Page 9: My Home Vihanga Status as on Dec 28th 2013

BLOCK-2 SOUTH SIDE VIEW STUB COLUMNS IN PROGRESS

Page 10: My Home Vihanga Status as on Dec 28th 2013

BLOCK-2 STUB COLUMNS IN PROGRESS

Page 11: My Home Vihanga Status as on Dec 28th 2013

BLOCK-2 NORTH SIDE VIEW

Page 12: My Home Vihanga Status as on Dec 28th 2013

NORTH –EAST VIEW

Page 13: My Home Vihanga Status as on Dec 28th 2013

BLOCKS EXCAVATION PODIUM AREA UNDER PROGRESS

Page 14: My Home Vihanga Status as on Dec 28th 2013

PCC DONE -6 NOS & FOOTING REINFORCEMENT TIEING IN PROGRESS

Page 15: My Home Vihanga Status as on Dec 28th 2013

BLOCKS EXCAVATION DONE

Page 16: My Home Vihanga Status as on Dec 28th 2013

BLOCKS 5 &6 IN PROGRESS

Page 17: My Home Vihanga Status as on Dec 28th 2013

IN PROGRESS

Page 18: My Home Vihanga Status as on Dec 28th 2013

HT & LT YARD ERECTION ,INSPECTION &CHARGING DONE,FENCING TO BE DONE

Page 19: My Home Vihanga Status as on Dec 28th 2013

BATCHING PLANT-2 FOUNDATION IN PROGRESS