19

Click here to load reader

PGSR Workstation Presentation

Embed Size (px)

Citation preview

Page 1: PGSR Workstation Presentation

Clean

Dry

Warm

Environmentally ....friendly Safe working ....environment

• Clean air in Clean air out• Carbon ...exhaust filters• Compact

• 60kg total ...weight• Cost effective

Page 2: PGSR Workstation Presentation
Page 3: PGSR Workstation Presentation

Looking towards the exhaust filter wall

Page 4: PGSR Workstation Presentation

Workstation prepared for rotor placement

Page 5: PGSR Workstation Presentation

Rotor stands awaiting the steam turbine rotor

Page 6: PGSR Workstation Presentation

Steam turbine ready for grit blasting

Page 7: PGSR Workstation Presentation

Protective sheets installed for grit over spray

Page 8: PGSR Workstation Presentation

Grit blasting being conducted on the steam turbine rotor

A noise survey showed 112dB inside and 99dB outside the workstation

Page 9: PGSR Workstation Presentation

Current methods of “clean, warm and dry” environment for generator rotor

Page 10: PGSR Workstation Presentation

With old methods if crane work is to be carried out, licensed scaffolders are required to modify the structure

Page 11: PGSR Workstation Presentation

Workstation floor section for the generator rotor is 11m long and 3 m wide

Page 12: PGSR Workstation Presentation

Workstation inflation is complete in approximately 5 minutes

Page 13: PGSR Workstation Presentation

No licences are required for personnel to erect, modify or move the Workstation

Page 14: PGSR Workstation Presentation

Clear sides allow adequate ambient lighting for safe work conditions

Page 15: PGSR Workstation Presentation

Halogen lamps are used to increase the Workstation temperature

Page 16: PGSR Workstation Presentation

A de-humidifier is used to control humidity for ideal generator rotor conditions

A temperature of 32o C and humidity of 40% has been maintained for over 2 weeks on the turbine deck

Page 17: PGSR Workstation Presentation

Additional heating can be introduced when required

Page 18: PGSR Workstation Presentation

Workstation fan unit and services penetration point

Page 19: PGSR Workstation Presentation

Hire RatesAre available on request

Custom sizes available

Low transport costs

No erection costs