Upload
ahmed-higazi-pmp-csm
View
145
Download
3
Embed Size (px)
DESCRIPTION
CAPM Study Guide Time Management PMP Study Guide Time Management PMI PMBK Study Guide Time Management Higazi PMP CSM Ahmed Higazi
Citation preview
Time Management
By Ahmed Higazi, PMP CSM
Define Activities (Planning) Inputs Tools & techniques Outputs
Scope Baseline Decomposition Activity List
Enterprise Environmental Factors Rolling Wave Planning Activity Attributes
Organizational Process Assets Templates Milestone List
Expert Judgment
Sequence Activities (Planning) Inputs Tools & techniques Outputs
Activity List Precedence Diagramming Method (PDM) Project Schedule Network Diagrams
Activity Attributes Dependency Determination Project Document Updates
Milestone List Apply leads & Lags
Project Scope Statement Schedule Network Temples
Organizational Process Assets
Estimates Activity Resources (Planning) Inputs Tools & techniques Outputs
Activity List Expert Judgment Activity Resource Requirements
Activity Attributes Alternatives Analysis Resource Breakdown Structure (RBS)
Resource Calendar Published Estimating Data Project Document Updates
Enterprise Environmental Factors Bottom-Up Estimating
Organizational Process Assets Project Management Software
Estimating Activity Duration (Planning) Inputs Tools & techniques Outputs
Activity List Expert Judgment Activity Duration Estimates
Activity Attributes Analogous Estimating Project Document Updates
Activity Resource Requirements Parametric estimates
Resource Calendar Three-Point Estimates
Project Scope Statement Reserve Analysis
Enterprise Environmental Factors
Organizational Process Assets
The specific actions to be performed to
produce the project deliverables
Sequence Activities is the process of
identifying and documenting relationships
among the project activities
Type and quantities of material, people,
equipment, or supplies required to
perform each activity
Approximating the number of work
periods needed to complete individual
activities with estimated resources
Develop Schedule (Planning) Inputs Tools & techniques Outputs
Activity List Schedule Network Analysis Project Schedule
Activity Attributes Critical Path Method Schedule Baseline
Project Schedule Network Diagram Critical Chain Method Schedule Data
Activity Resource Requirements Resource Leveling Project Document Updates
Resource Calendar What-if Scenario Analysis
Activity Duration Estimates Applying Leads and Lags
Project Scope Statement Schedule Compression
Enterprise Environmental Factors Scheduling Tool
Organizational Process Assets
Control Schedule (M&C) Inputs Tools & techniques Outputs
Project Management Plan Performance Reviews Work Performance Measurements
Project Schedule Variance Analysis Organizational Process Assets updates
Work Performance Information (WPI) Resource Leveling Change Requests
Organizational Process Assets What-if Scenario Analysis Project Management Plan Updates
Project Management Software Project Document Updates
Adjusting Leads and Lags
Schedule Compression
Scheduling Tool
PMI®, PMP®, CAPM® and PMBOK® Guide are trademarks of the Project Management Institute, Inc PMI® has not endorsed and did not participate in the development of this product. PMBOK-4th
The process of analyzing activity
sequences, durations, resource
requirements, and schedule constraints to
create the project schedule
the process of monitoring the status of
the project to update project progress
and managing changes to the schedule
baseline