Upload
annsstand
View
461
Download
1
Embed Size (px)
Citation preview
Project Management Professional (PMP) Exam Preparation
Free Sample
(Based on Guide to PMBOK 5th Edition)(Based on Guide to PMBOK 5th Edition)ByBy
Ready to PresentReady to Presenthttps://www.facebook.com/ReadyToTrainMaterialshttps://www.facebook.com/ReadyToTrainMaterials
Chapter 1
Introduction to Project Management
05/03/23 12:42 2
What is Project Management?
• The application of knowledge, skills, tools and technique to The application of knowledge, skills, tools and technique to project activities to meet project requirementsproject activities to meet project requirements
• Project Management is accomplished through the application and integration of the processes such as
– Initiating Initiating – Planning Planning – ExecutingExecuting– Monitoring and Controlling Monitoring and Controlling – ClosingClosing
05/03/23 12:42 3
The Triple Constraint of Project Management
Cost
ScopeTim
e
05/03/23 12:42 4
It is the project manager’s duty to balance and achieve It is the project manager’s duty to balance and achieve
these three often-competing goals.these three often-competing goals.
Constraint of Project Management
Scop
eSc
ope Tim
eTim
e
CostCost
Customer Customer SatisfactionSatisfaction
Ris
kR
isk
ProjectProject
Quality
Quality
05/03/23 12:42 5
05/03/23 12:42 6
Project, Program, Portfolio
Project E
Project, Program, Portfolio
05/03/23 12:42 7
Project-Based Organizations
Project-based organizations (PBOs) refer to various organizational forms that create temporary systems for carrying out their work. (as in telecommunications, oil and gas, construction, consultancy, and professional Services)
05/03/23 12:42 8
Chapter 2
Project Life Cycle and Organization
05/03/23 12:42 9
Project Life Cycle (Technical Work)
• Project Life Cycle is a collection of generally sequential and
sometimes overlapping project phases.(not black box).(not black box)
• Project Phases are marked by the completion of a deliverable deliverable
(Tangible, verifiable work product).
– Review of deliverables and approval/denial-phase end
review- are “phase exits, stage gates, or kill points???”
• All projects are divided into phases, and all projects, large
or small, have a similar life cycle structure.
05/03/23 12:42 10
Initiation Conclusion
Handoff Handoff Handoff
GatesGatesGates
Deliverables Deliverables Deliverables
05/03/23 12:42 11
Project Life Cycle
Project phases differ from project to another
Construction: Feasibility-> Planning -> Design -> Production -> Turnover -> StartupIT Project: Requirement -> Design -> Program -> Test -> Implement
Fast Tracking
• There are times when phases are overlapped
to shorten or compress the project schedule.
This is called Fast Tracking.
• Fast tracking means that a later phase is
started prior to completing and approving the
phase, or phases, that come before it.
• This technique is used to shorten the overall
duration of the project.
05/03/23 12:42 12
Project Stakeholders
05/03/23 12:42 13
• An important part of a project manager’s responsibility is to manage
stakeholder expectations, which can be difficult because
stakeholders often have very different or conflicting objectives.
• Part of the project manager’s responsibility is to balance these
interests and ensure that the project team interacts with
stakeholders in a professional and cooperative manner.
Cos
t and
sta
ffing
leve
l
Time
Initial Phase Intermediate Phase(s) Final Phase
cost of changes
influence of stakeholders
Stakeholders Influence Over Time
05/03/23 12:42 14
Project Success
The success of the project should be measured in terms of completing the project within the constraints of scope, time, cost, quality, resources, and risk as approved between the project managers and senior management.
05/03/23 12:42 15
Organizational Structure- Functional Organization
• The organization is grouped by areas of specialization within different
functional areas.
• Projects generally occur within a single department.
• Information required from other department will be routed through
departmental heads.
• Team members complete project work in addition to normal department
work.05/03/23 12:42 16
Organizational Structure- Balanced Matrix Organization
• Two Bosses
• Team members reports to
Project Manager and Functional
Manager
• Team members do project work
in addition to normal
departmental work
• Power is shared between the
functional and project manager
05/03/23 12:42 17
Iterative and Incremental Life Cycles
Ones in which project phases (also called iterations) intentionally repeat one or more project activities as the project team’s understanding of the product increases, while increments successively add to the functionality of the product.
05/03/23 12:42 18
Chapter 4
Project Integration Management
05/03/23 12:42 19
Project Integration Management
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.
05/03/23 12:42 20
Develop Project Charter
• Project Charter Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
• The Project Manager The Project Manager should always be assigned prior to the start of planning, and preferably while the project charter is being developed.
• The Project Charter is Issued by a sponsor, not the project manager, but preferred to be participated in developing it.
05/03/23 12:42 21
Project Selection Methods
Project selection Project selection is generally the responsibility of Portfolio Managers,
Steering Committees. In smaller companies, Presidents and Vice- Presidents.
These methods generally fall into one of two broad categories:
•Benefit measurement methods (comparative approach) that are comparative
approaches:murder board, peer review, scoring models, benefit contribution,
or Economic models.
•Constrained optimization methods (Mathematical approach) that use
programs; linear, nonlinear, dynamic, integer, or multi-objective programming
algorithms
05/03/23 12:42 22
1.1. Present valuePresent value Present value :PV = FV/(1 + r)n
•FV = amount of money t years from now•r = interest rate (also called “discount rate”)•n = time period
Assume a 10% interest (or discount) ratePV (Year 1) = FV / (1 + r)t =$35,000/(1 + 0.1)1= $31,819
Economic Model
Year FV PV
0 $50,000 $50,000
1 $35,000 $31,819
2 $15,000 $12,397
05/03/23 12:42 23
2. Net present value: 2. Net present value: This Means the total benefits (income or revenue) less
the cost. To calculate NPV you need to calculate the present value of each
of the income and revenue figures then add up the present values.
TimePeriod
Income orrevenue
Present Value at 10% interest
rate
Costs Present Value at Costs 10% interest rate
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
Total 353 291
NPV=353-291=6205/03/23 12:42 24
Economic Model
Requirements Traceability Matrix• A grid that links product requirements from their origin to the deliverables that satisfy
them.It provides a mean to track requirements throughout the project life cycle.
• Matrix helps to ensure that requirements approved in requirements documentation
are delivered at the end of the project.
• Attributes associated with each requirement can be recorded in the requirements
traceability matrix.
Collect Requirements – Outputs
05/03/23 12:42 25
Create WBS
• The WBS is a deliverables-orientated
decomposition of the work to be executed by
project team to accomplish the project
objectives and create the required
deliverables.
• The planned work is contained within the
lowest level WBS components (work
packages) which can be scheduled, cost
estimated, monitored and controlled.
• The top most level of each WBS is the total
project itself
05/03/23 12:42 26
Question
You're the project manager for an advertising campaign. The stakeholders,
including the client, approved your completed WBS. Later, after some of the
artwork has been printed, the client wants to add a registered trademark
symbol, which will cost a considerable amount of money. The client says that
your company's salesperson, prior to signoff on the WBS, promised this
feature would be included. Who should pay for the change?
A. Your company managing the project
B. Both the client and your company should pay part of the cost
C. The change should not be implemented
D. The client
05/03/23 12:42 27
Create WBS – Outputs
• A WBS structure may be created through various approaches. Some of the
popular methods include the top down approach, the use of organization-
specific guidelines, and the use of WBS templates. A bottom-up approach
can be used during the integration of subcomponents
• The WBS is a hierarchical decomposition of the total scope of work to be
carried out by the project team to accomplish the project objectives and
create the required deliverables.
05/03/23 12:42 28
Validate Scope
Validate Scope is the process of formalizing acceptance of the completed
project.
•The Validate Scope process differs from the Control Quality process in that
the former is primarily concerned with acceptance of the deliverables, while
quality control is primarily concerned with correctness of the deliverables
and meeting the quality requirements specified for the deliverables.
•Control Quality is generally performed before Validate Scope, although the
two processes may be performed in parallel.
05/03/23 12:42 29
Three Point Estimates (PERT)
05/03/23 12:42 30
PERT Calculations
• If all activities are on critical, then total estimated project duration = sum of PERT
values for each activities.
• Standard Deviation shall not be added. Add variance of each activities and take
square root of sum to get standard deviation for total project.
• In the example above, range will be 170.167 +/-10.060
Estimate Activity Durations : Tools & Techniques
Activity O M P PERT SD Variance Range
A 14 27 47
B 41 60 89
C 39 44 48
D 29 37 42
05/03/23 12:42 31
PERT Calculations
• If all activities are on critical, then total estimated project duration = sum of PERT
values for each activities.
• Standard Deviation shall not be added. Add variance of each activities and take
square root of sum to get standard deviation for total project.
• In the example above, range will be 170.167 +/-10.060
Estimate Activity Durations : Tools & Techniques
Activity O M P PERT SD Variance Range
A 14 27 47 28,167 5.5 30,25 28.167+/-5.5
B 41 60 89 61,667 8 64 61.667+/-8
C 39 44 48 43,833 1.5 2.25 43.833+/-1.5
D 29 37 42 36,500 2.167 4.694 336,5+/-2.167
05/03/23 12:42 32
Group Decision-Making Techniques
• Team-based approaches, such as brainstorming, the Delphi or nominal
group techniques, are useful for engaging team members to improve
estimate accuracy and commitment to the emerging estimates. By involving
a structured group of people who are close to the technical execution of
work in the estimation process, additional information is gained and more
accurate estimates obtained.
Estimate Activity Durations : Tools & Techniques
05/03/23 12:42 33
Reserve Analysis
• Contingency Reserve time —also called buffer or time reserves
• Reserve is added to account for schedule risk.
• You might choose to add a percentage of time or a set number of work
periods to the activity or the overall schedule.
• If not done properly can lead to padding
• Contingency reserve shall be clearly identified and documented for future
analysis
Estimate Activity Durations : Tools & Techniques
05/03/23 12:42 34
Develop Schedule-Tools & Techniques
Schedule Network Analysis
• Schedule network analysis is a technique that generates the project
schedule.
• It employs a schedule model and various analytical techniques, such as
critical path method, critical chain method, what-if analysis, and resource
levelling to calculate the early and late start and finish dates for the
uncompleted portions of project activities.
Critical Path Method
• A method used to estimate the minimum project duration and determine the
amount of scheduling flexibility on the logical network paths within the
schedule model
05/03/23 12:42 35
Example of Critical Path Method
05/03/23 12:42 36
Network Diagram Nodes
• ES = Earliest date an activity can be started• EF = Earliest date an activity can be completed• LS = Latest date an activity can start• LF = Latest date an activity can be completed
ES
LS LF
EF
Duration
Forward pass
Backward pass
05/03/23 12:42 37
Critical Chain Method
• Critical Chain is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
• The resource-constrained critical path is known as the critical path.
05/03/23 12:42 38
Develop Schedule: Tools and TechniquesResource Optimization Techniques
1. Resource leveling. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
05/03/23 12:42 39
Develop Schedule: Tools and Techniques Modeling Techniques
1. What-If Scenario Analysis. is the process of evaluating scenarios
in order to predict their effect, positively or negatively, on project
objectives.
2. Simulation. involves calculating multiple project durations with
different sets of activity assumptions, usually using probability
distributions constructed from the three-point estimates
05/03/23 12:42 40
Develop Schedule: Tools and Techniques Schedule Compression
• Fast Tracking Performing critical path tasks in parallel and
riskier than crashing Eg,.Design is half finished and start coding
• Crashing Analyze cost and schedule trade-offs Determine most compression for least cost Crash the tasks that cost the least first,
focusing on minimizing project cost
05/03/23 12:42 41
Milestone Chart
05/03/23 12:42 42
Project Calendars
• project calendar identifies working days and shifts that are available
for scheduled activities. It distinguishes time periods in days or parts
of days that are available to complete scheduled activities from time
periods that are not available. A schedule model may require more
than one project calendar to allow for different work periods for
some activities to calculate the project schedule. The project
calendars may be updated.
05/03/23 12:42 43
05/03/23 12:42
44
Sample PMP Sample PMP Certification Certification QuestionsQuestions
Exercise
Q1. The estimate for a task is O = 3 days, P = 7 days, M = 4 days. What is the standard deviation of the task?– A. 5/6 of a day -B. 2/3 of a day -C. 1 ½ days -D. 5 2/3 days
Solution: SD = (P-O)/6 = (7-3)/6 = 2/3
Q2. You are the project manager for a new project and have figured out the following dependencies:
• Task 1 can start immediately and has an estimated duration of 3 weeks• Task 2 can start after Task1 is completed and has an estimated duration of 3 weeks• Task 3 can start after Task 1 is completed and has an estimated duration of 6 weeks• Task 4 can start after Task 2 is completed and has an estimated duration of 8 weeks• Task 5 can start after task 4 is completed and after Task 3 is completed . This task
takes 4 weeks.• What is the duration of the critical path?
– A. 18.5 weeks -B. 19 weeks -C. 20 weeks -D. 18 weeks
05/03/23 12:42 45
• You are the project manager for a project with the following network diagram. Studying the diagram, which path is the critical path?
A. ABCD B. EBCD C. EFH D. EGH
05/03/23 12:42 46
Exercise
Chapter 7 Project Cost Management
05/03/23 12:42 47
Forecasting
• Using the earned value analysis, team can now forecast the project
performance.
• Estimate at completion (EAC) may differ from Budget at Completion (BAC)
• Estimate to complete (ETC) is the estimate of remaining work. Now
Estimate at completion = AC + ETC.
Control Costs- Tools and Techniques
05/03/23 12:42 48
Plan Human Resource Management: Outputs
Human Resource Management Plan - which includes:
Roles and Responsibilities
• Role. The function assumed by or assigned to a person in the project.
• Authority. The right to apply project resources, make decisions, sign approvals,
accept deliverables, and influence others to carry out the work of the project.
• Responsibility. The assigned duties and work that a project team member is
expected to perform in order to complete the project’s activities.
• Competency. The skill and capacity required to complete assigned activities
within the project constraints.
05/03/23 12:42 49
Acquire Project Team
The process of confirming human resource availability and obtaining the team
necessary to complete project activities.
05/03/23 12:42 50
• Multi-Criteria Decision AnalysisMulti-Criteria Decision Analysis
Knowledge. Consider if the team member has relevant knowledge of the customer,
similar implemented projects, and nuances of the project environment.
Skills. Determine whether the member has the relevant skills to use a project tool,
implementation, or training.
Attitude. Determine whether the member has the ability to work with others as a
cohesive team.
International factors. Consider team member location, time zone and
communication capabilities.
05/03/23 12:42 51
Acquire Project Team: Tools & Techniques
Develop Project Team
• Develop Project Team is the process of improving competencies, team member interaction, and overall team environment to enhance project performance.
05/03/23 12:42 52
Motivation Theory: McGregor’s X & Y Theory
Theory XTheory X
• People tends to be negative, passive e.g. Avoid responsibility, People tends to be negative, passive e.g. Avoid responsibility,
need to be watchedneed to be watched
• Extrinsic MotivationExtrinsic Motivation
Theory YTheory Y
• People tends to be positive e.g. Want to achieve, willing to People tends to be positive e.g. Want to achieve, willing to
work without supervision, can direct their own effortwork without supervision, can direct their own effort
• Intrinsic MotivationIntrinsic Motivation
05/03/23 12:42 53
Herzberg’s Theory
• Job Satisfaction due to lack of hygiene factors
• Job satisfaction due to motivation factorsHygiene FactorsWorking conditionSalaryPersonal lifeRelationship at workSecuritystatus
Motivations FactorsResponsibilitySelf actualizationProfessional growthrecognitionPersonal lifeRelationship at workSecuritystatus
05/03/23 12:42 54
Develop Project Team: Tools & Techniques
05/03/23 12:42 55
Develop Project Team: Tools and Techniques
Team Building Activities
One theory states that there are 5 stages of development that the teams may
go through. Usually these stages occur in an order .
1. Forming : this phase is where the team meets and learns about the project
and what their formal roles and responsibilities are . Team members tend to
be independent and not as open in this phase
2. Storming : During this phase , the team begins to address the project work,
technical decisions , and the project management approach . If team
members are not collaborative and open to differing ideas and perspectives
the environment can become destructive.
.
05/03/23 12:42 56
Plan Communications Management: Tools and Techniques
• Communication Requirements AnalysisThe total number of potential
communication channels is n(n – 1)/2, where n represents the number of stakeholders
05/03/23 12:42 57
2)1( NN
Communication Methods:Communication Methods:
• Interactive communication - Between two or more parties in
multidirectional (Phone calls, meetings, interviews). (Phone calls, meetings, interviews). Most effective way.
• Push communication - Sent a specific information to specific recipients.
Examples are letters, memos, e-mails, faxes etc.Examples are letters, memos, e-mails, faxes etc. This ensures that
message is sent but will but will not certify that it is actually received or
understood. (Push the message to recipient)
• Pull communication – Used for large volume of information and large
audiences. Examples are internet sites, company data bases, e-learning Examples are internet sites, company data bases, e-learning
etc.etc. Recipients has to access the communication content (Pull out
information) at their own discretion.
Plan Communication : Tools & Techniques
05/03/23 12:42 58
Chapter 11 Project Risk Management
05/03/23 12:42 59
• Modelling and Simulation: Project simulations allow the project team to
play “what-if” games without affecting any areas of production. The Monte
Carlo technique is the most common simulation.
• Monte Carlo, typically completed through a computer software program,
completely simulates a project with values for all possible variables to
predict the most likely model.
Perform Quantitative Risk Analysis – Tools & Techniques
05/03/23 12:42 60
Control Risks
Control Risks is the process of implementing risk response plans, tracking
identified risks, monitoring residual risks, identifying new risks, and evaluating
risk process effectiveness throughout the project.
Control Risks – Tools & Techniques
Reserve Analysis: it compared the amount of the contingency reserves
remaining to the amount of risk remaining at any time in the project
05/03/23 12:42 61
Chapter 12 Project Procurement Management
05/03/23 12:42 62
Project Procurement Management
• Plan Procurement Management is the process of documenting project
procurement decisions, specifying the approach, and identifying potential
sellers.
• PM must be involved in the creation of the contracts
05/03/23 12:42 63
Project Procurement Management– Tools & Techniques
Make-or-Buy AnalysisIt is a general management technique used to determine whether particular work can best be accomplished by the project team or must be purchased from outside sources.•You are trying to decide whether to lease or buy an item for your project. The daily lease cost is Dhs. 120. To purchase the item investment cost is Dhs. 1000 and the daily cost is Dhs. 20. How long will it take for the lease cost to be the same as the purchase cost?•Let D equal the number of days when the purchase and lease costs are equal.•QR 120 D = QR 1000 + QR 20 DQR 120 D = QR 1000 + QR 20 D•QR 120 D - QR 20 D = QR 1000QR 120 D - QR 20 D = QR 1000•QR 100 D = QR 1000QR 100 D = QR 1000•D = QR 1000 / QR 100D = QR 1000 / QR 100•D = 10D = 10The least cost will be the same as the purchase cost after ten days.
05/03/23 12:42 64
Contract Types:
Contract is a mutually binding legal agreement that
obligates the seller to provide the specified products,
services or results, and obligates the buyer to
compensate the seller.
• The contract may includes the following: An offer,
Acceptance, Pricing, roles and responsibilities,
penalties, warranty,
1. Purchase Order: Contract to purchase 30 linear
meters of wood at Dhs. 40 per meter
Legal Contractual Relationships
05/03/23 12:42 65
Chapter 13
Project Stakeholder ManagementProject Stakeholder Management
05/03/23 12:42 66
Identify Stakeholders
• Identify Stakeholders is the process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project, analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
• It is critical for project success to identify the stakeholders early in the project or phase and to analyze their levels of interest, their individual expectations, as well as their importance and influence.
05/03/23 12:42 67
Identify Stakeholders: Tools and Techniques
• Stakeholder Analysis: is a technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
05/03/23 12:42 68
Identify Stakeholders : Tools & Techniques
• Step 1:Identify all potential project stakeholders and
relevant information such as their roles, departments,
interest, knowledge levels, expectations and influence
levels .
• Step 2 :Identify the potential impact or support each
stakeholder could generate and classify them so as to
define an approach strategy.
• Step 3 : Access how key stakeholders are likely to react
in various situations and plan how to influence them for
their support and mitigate potential negative impact
05/03/23 12:42 69
Plan Stakeholder Management: Tools and Techniques
• Analytical Techniques:
The engagement level of the stakeholders can be classified as follows:
Unaware. Unaware of project and potential impacts.
Resistant. Aware of project and potential impacts and resistant to
change.
Neutral. Aware of project yet neither supportive nor resistant.
Supportive. Aware of project and potential impacts and supportive
to change.
Leading. Aware of project and potential impacts and actively
engaged in ensuring the project is a success.05/03/23 12:42 70
Chapter 13Professional Responsibility
05/03/23 12:42 71
Professional Responsibility
• About 18 questions on the exam cover this part.
• The PMP must adhere to a high set of principles, rules, and policies.
• On the PMP exam, always choose the answer which best supports the PMP
profession and the higher set of principles the PMP is expected to adhere to.
• Did you realize that it is unethical to manage a project if you have not been
trained in project management? Did you know that it is unethical to provide a
project schedule that you do not believe to be accurate?
05/03/23 12:42 72
Responsibility- ownership of decisions and actions
• Make decisions based on the best interests of the company and the team,
as well as society, rather than your own interest.
• Inform the sponsor of your real qualifications if its not matching the project
before accepting the assignment
• Do what you say you will do
• Acknowledge your own errors
• Respect confidentiality requirements
• Uphold laws
• Report unethical behaviour to the management
• Report violations of PMI’s code of ethics and professional conduct
05/03/23 12:42 73
Respect- the appropriate treatment of people and resources
• Maintain an attitude of mutual cooperation
• Respect cultural differences
• Don't gossip or saying things that could damage another persons reputation
• Engage in good faith negotiations
• Respect others
• Be direct in dealing with conflict
• Do not use your power or position to influence others for your own [personal
benefit
05/03/23 12:42 74
Q4You are the project manager of the LKH Project. This project must be completed
within six months, but after two months the schedule has begun to slip. As of now,
the project is one week behind schedule. Based on your findings, you believe you
can make some corrective actions and recover the lost time over the next month to
get the project back on schedule for its completion date. Management, however,
requires weekly status reports on cost and schedule. Which of the following should
you do?
A. Report that the project is one week behind schedule, but will finish on schedule
based on cited corrective actions.
B. Report that the project is on schedule and will finish on schedule.
C. Report that the project is off schedule by a few days, but will finish on schedule.
D. Report that the project is running late.
05/03/23 12:42 75
Q5You are a project manager within an organization that completes technical
projects for other entities. You have plans to leave your company within the next
month to launch your own consulting business—which will compete with your
current employer. Your company is currently working on a large proposal for a
government contract that your new company could also benefit from. What should
you do?
A. Resign from your current job and bid against your employer to get the contract.
B. Decline to participate due to a conflict of interest.
C. Help your employer prepare the proposal.
D. Inform your employer that you will be leaving their company within a month and
it would be inappropriate for you to work on the current proposal.
05/03/23 12:42 76
Q6
Your company does not allow project managers to accept gifts from vendors
of any kind. A friend that you have known for years now works for a vendor
that your company may be doing business with. Your friend from the vendor
asks you to lunch to discuss an upcoming project and you accept. When the
check arrives at the lunch table, your friend insists on paying. You should:
A. Allow the friend to buy because you’ve been friends for years.
B. Allow the friend to buy because lunch isn’t really a gift.
C. Don’t allow the friend to buy because your company does not allow any
gifts from vendors.
D. Insist that you purchase your friend’s lunch and your friend buys yours.
05/03/23 12:42 77
Q7
You are the project manager of the AAA Project. Due to the nature of the
project, much of the work will require overtime between Christmas and New
Year’s Day. Many Day. Many of the project team members, however, have requested
vacation during that week. What is the best way to continue?
A. Refuse all vacation Refuse all vacation requests and require all team members to work.
B. Only allow vacation requests for those team members who are not needed
during that week.
C. Divide tasks equally among the team members so each works the same
amount of time.
D. Allow team members to volunteer for the overtime work.
05/03/23 12:42 78
Tricks for the PMP Exam
• Bring the authorization letter from PMI to the test siteBring the authorization letter from PMI to the test site
• Bring snacks, you can not eat in the test room, but you can out of Bring snacks, you can not eat in the test room, but you can out of
the room.the room.
• The exam will not be adapted according to you, 200 Q’s will be The exam will not be adapted according to you, 200 Q’s will be
selected in the beginning and it will not be changedselected in the beginning and it will not be changed
• You can mark questions in order to return to it backYou can mark questions in order to return to it back
• Most of the questions are situationalMost of the questions are situational
• You can re-take the exam for 2 times only.You can re-take the exam for 2 times only.
05/03/23 12:42 79