19
1 Project Appraisal & Financing Business Idea: FLY ASH BRICKS

Project Appraisal and Financing of a Business Idea in Fly ash Bricks

Embed Size (px)

Citation preview

Page 1: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

1

Project Appraisal & Financing

Business Idea: FLY ASH BRICKS

Page 2: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

2

INTRODUCTION 3 MARKET DEMAND: ............................................................................................................................. 4

Why fly ash bricks? ............................................................................................................................. 4

Technical Specifications ...................................................................................................................... 4

Demand potential estimate ................................................................................................................ 5

Supply status: ...................................................................................................................................... 5

Scope of the project: ........................................................................................................................... 5

Acquiring the raw materials: ............................................................................................................... 6

Economic concerns: ............................................................................................................................ 6

Product pricing .................................................................................................................................... 6

Promotional plans: .............................................................................................................................. 6

Marketing plans .................................................................................................................................. 6

STP:...................................................................................................................................................... 6

Country Scenario ................................................................................................................................. 7

Steps involved ..................................................................................................................................... 8

Equipment Suppliers ........................................................................................................................... 8

Raw Materials & Utilities .................................................................................................................... 8

Manpower Requirements ................................................................................................................... 8

Location & Infrastructure .................................................................................................................... 8

Implementation .................................................................................................................................. 9

SOURCES: ................................................................................................................................................ 9

PAF FINAL RANK 1 IDEAS OF OUR TEAM .............................................................................................. 10

Reasons for Selecting Fly Ash Bricks ................................................................................................. 10

Reasons for Not Selecting Others ..................................................................................................... 10

LIST OF ASSUMPTIONS .......................................................................................................................... 11

FEASIBILITY STUDY ................................................................................................................................ 12

Estimation of Installed Capacity........................................................................................................ 12

Raw Materials for Product 1 ............................................................................................................. 13

Production and Sales Realization ...................................................................................................... 13

Salary and Wages .............................................................................................................................. 13

Miscellaneous Fixed Assets ............................................................................................................... 14

Preliminary and Preoperative Expenses ........................................................................................... 14

Depreciation ...................................................................................................................................... 14

Assumption for Estimated Cost of Production ................................................................................. 15

Project Cost Estimation ..................................................................................................................... 15

Page 3: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

3

Profitability Statement ...................................................................................................................... 16

Break Even Point ............................................................................................................................... 17

Working Capital Calculation .............................................................................................................. 18

Debt Service Coverage Ratio ............................................................................................................. 19

INTRODUCTION

Fly Ash bricks are made of fly ash, lime, gypsum and sand. These can be extensively

used in all building constructional activities similar to that of common burnt clay bricks. The

Page 4: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

4

fly ash bricks are comparatively lighter in weight and stronger than common clay bricks.

Since fly ash is being accumulated as waste material in large quantity near thermal power

plants and creating serious environmental pollution problems, its utilization as main raw

material in the manufacture of bricks will not only create ample opportunities for its proper

and useful disposal but also help in environmental pollution control to a greater extent in the

surrounding areas of power plants. In view of superior quality and eco-friendly nature, and

government support the demand for Fly Ash Bricks has picked up.

MARKET DEMAND:

180 billion tons of common burnt clay bricks are consumed annually approximately

340 billion tons of clay- about 5000 acres of top layer of soil dug out for bricks manufacture,

soil erosion, emission from coal burning or fire woods which causes deforestation are the

serious problems posed by brick industry. The above problems can be reduced some extent

by using fly ash bricks in dwelling units. Demand for dwelling units likely to raise to 80

million units by year 2015 for lower middle and low income groups, involving an estimated

investment 0f $670 billion, according to the associated chamber of commerce and industry.

Demand for dwelling units will further grow to 90 million by 2020, which would require a

minimum investment of $890billion. The Indian housing sector at present faces a shortage of

20million dwelling units for its lower middle and low income groups which will witness a

spurt of about 22.5million dwelling units by the end of Tenth plan period. There is ample

scope for fly ash brick and block units... But good quality of bricks as well as required

quantity is not available moreover during the Rainey seasons supply of clay bricks are very

difficult. Therefore, in order to fulfill the required demand there will be a great chance to start

more units in the field of fly ash bricks. At present 20nos units are engaged and 40 lakhs no’s

of bricks per month are manufactured in our state. And there will be scope to start near about

100 units, which will be produced more than 2 cores no of bricks per month in future. Thus

marketing of these product are well shinning.

Why fly ash bricks?

Fly ash bricks are can be used as an alternative to burnt clay bricks. These are

environment friendly cost saving building products. These are 3 times stronger than

conventional bricks with consistent strength. These are ideally suited for internal, external,

load bearing and non-load bearing walls. These bricks with higher strength /weight ratio

(about 3 to 4 times that of burnt clay bricks) aid in designing stronger yet more economic

structures. Fly ash bricks are durable, have low water absorption, less consumption of mortar,

economical &ecofriendly, low energy consumption and no emission of greenhouse gases.

These bricks are not affected by environmental conditions and remain static thus ensuring

longer life of the building. Also the savings with regard to wastages in fly ash bricks are

considerable during unloading and construction due to true shape and size, consistency in

quality and the workability of the fly ash bricks unlike traditional clay bricks. These bricks

are very economical / cost effective.

Technical Specifications

Sizes available :230x110x70 mm

Page 5: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

5

Raw Material Used : fly ash, sand, grit, cement

Uses : constructions of walls

Colors & packaging available : light grey, minimum 1 load truck can be delivered

Demand potential estimate

The construction industry contributes to about 10 % of the Gross Domestic Product

(GDP), registering an annual growth of about 9 %. Clay fired bricks form the backbone of the

construction industry which is valued at approximately US$ 70.8 billion. The brick sector in

India, although unorganized, is tremendous in size and spread. India is the second largest

brick producer (China dominates with 54 % share) in the world. It is continuously expanding

on account of a rapid increase in demand for bricks in infrastructure and housing industries.

In order to meet this demand, over 150,000 brick units provide direct employment to more

than 8 million workers. During the Ninth Five-year Plan period (1997-2002), the annual

demand of 170 million bricks per year was estimated to be generating revenues of over US$

4.8 billion.

Supply status:

Raw materials required for making of fly ash bricks are fly ash, lime and gypsum. Fly

ash can be procured from thermal power plants. Lime and gypsum are available in the market

and can be bought as per the requirement

The need for clay ash bricks:

1) The bricks we currently use made up of specific quality of top soil( app 10000 hc of

top soil is lost every year for brick manufacturing)

2) If the top soil consumption carries on at the same pace, very soon, we will not have

enough soil for the cultivation.

3) The thermal power plants and the industrial units using coal as a fuel have no use with

the fly ash left after the combustion

Scope of the project:

1) Nearly 75 % of India’s total installed power generation capacity is thermal, of which

coal based generation is 90%, the remaining comprising of diesel and gas.

2) The 85 utility thermal power plants use coal and producing large quantities of fly ash.

Features:

1) Size of the bricks will be 230 x 110 x 76 mm

2) Less mortar consumption

3) Ash content as high as 60%

4) Faster construction

Page 6: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

6

Acquiring the raw materials:

1) Fly ash is readily available with thermal power plants and can be acquired from them

even without spending on transportation

2) Lime, gypsum and sand are available in the market and can be purchased as per the

requirement.

Economic concerns:

1) Currently the demand for bricks is very high from the supply

2) Demand and supply gap is around 270 billion bricks per annum

3) In India the annual production of fly ash can result in manufacturing 790 billion

bricks

4) To reduce the demand and supply gap we will need to expand in this sector at a larger

rate than what is undergoing at the present time.

Product pricing

1) Penetration price of Rs.5.00 per brick for the first two years and then concession to

high end buyers at a rate of 5%

Promotional plans:

1. Discounts on large buying

2. Large volume of institutional sales

3. Aggressive selling

4. Trade promotion

5. Publicity

Marketing plans

1) The government has imposed rules for the use of 100% fly ash bricks in a radius of

100 mms from thermal power plants. However, the government is itself not implying

to the norms. The govt. can be forced to imply to such norms by NGOs and when

such a scenario occurs, the demand for the bricks from the side of the govt. will

increase many folds.

2) Use of these bricks result savings of almost 37% in the construction cost.

STP:

Segmentation: We will first try to capture the local markets and then we will move to the

neighboring states.

Positioning: It can be positioned as environmental pollutant cleaner.

Targeting: Builders, consultants, architects, government

Page 7: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

7

Study revealed that out of the different building blocks existing in the market, burnt

clay bricks account for more than 95% of the total market for walling material in larger parts

of the country.Q

Type of Walling material Market Size % of Total market

(Rs Crore)

Burnt Clay Bricks 32825 95.3%

Cement Concrete blocks 1135 3.3%

Fly ash bricks 485 1.4%

Fly ash: Fly ash is the major raw material used in the manufacturing of burnt clay

bricks. The availability of the raw material is described as follows:

Andhra Pradesh Scenario

1) The current utilization of Fly ash in the state in tune of 36.9 % of total fly ash

generated from all of its thermal power stations

2) The fly ash utilization in Andhra Pradesh in 2005-06 is around 46% which is

increased to 60% in 2014

Country Scenario

a) In accordance to Central Electricity Authority, an amount of 130.7million tons of fly

ash is generated from the coal based thermal power plants. However the total

utilization of fly ash is only 72.8 million tons (i.e. 56%) of which 35.2 million tons

(i.e. 27% of total fly ash) were consumed by the cement industry. The other users

included Brick Manufacturers 4.59 million tons (3.5%), Roads, Embankment and Ash

Dykes 8.52 million tons (6.5%), Reclamation and Mine-filling 15.19 million tons

(11.5%), and other misc. applications 9.34 million (7%). Balance 57.90 million tons

which is about 44% of the total fly ash remained unutilized12.

b) Paper Published in Journal of scientific and industrial research13refers to “tick” report

that refers to a total ash utilization of 38% In India

c) Publication by Department of Science and Technology outlined the availability of fly

Ash as below

1. The utilization of fly ash during 1993-94 was one million tons only as against a

generation of 40 million tons.

2. Fly ash utilization rose to 60 million tons during the year 2006-07 in compared to

fly ash generation in the country of 130 million tons per year.

3. The quantum of un-utilized fly ash has also increased from 39 million tons per year

to 100 million tonne per year in 2006-2007.

Page 8: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

8

TECHNICAL REQUIREMENTS

Steps involved

1) Collection of Different clay and Flash.

2) Mixing and preparation of clay-flash mix.

3) Preparation of Bricks through moulds.

4) Drying of Bricks.

5) Filling of Kiln.

6) Burning of Bhatta.

7) Cooling of Bhatta.

8) Empty & Refilling of Bhatta.

9) Inspection and sorting of Bricks according to grades.

10) Dispatch.

Equipment Suppliers

Benny Enterprise, Coimbatore, Tamil Nadu

Shri Engineering Enterprises, Pune

Shree Hari Engineering, Ahmedabad, Gujarat

Columbia-Pakona Engineering Pvt. Ltd., Mumbai

Concept Tech-Know Equipment Pvt. Ltd., Maharashtra, Pune

Raw Materials & Utilities

->From Thermal power station & local suppliers of lime etc

->Fly ash, Lime, Gypsum, Sand and down metal

Manpower Requirements

->12-14 people/shift

Location & Infrastructure

Technically advanced manufacturing unit with modern technology. The

manufacturing unit is well equipped with high end latest machinery, Computerized Design

Unit, Laboratory, Conference Hall for arranging business meet, technology based meet to

promote and/or training for ecofriendly product. Highly experienced and diligent team of

experts who assists offer high quality products. Research and Development team is remain

connect with global market. The products are continuous update with innovative latest

technologies. Professionals have expertise in all areas and can fully support our equipment,

Page 9: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

9

providing parts, service, installation and training to Indian and global customers. We are

planning to establish this plant near NTPC/ Ramagundam, Karimnagar

Implementation

->6-8 Weeks

SOURCES:

http://www.taramachines.com/Tara-fly-ash.aspx

http://www.ecobrick.in/resource_data/KBAS100082.pdf

http://www.bmtpc.org/DataFiles/CMS/file/01_Flyash_Brick1.pdf

http://nstfdc.nic.in/userfiles/fly_ash_bricks.pdf

http://www.dsir.gov.in/reports/ExpTechTNKL/Abs%20new/Engineers.htm

Page 10: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

10

PAF FINAL RANK 1 IDEAS OF OUR TEAM

HARI HARSHA SHAKEER HARESH SUDHEERA

SAIR

AM

FACTORS

WEIGHT

(R1)RAIN

WATER

HARVEST

ING TOOL

KIT

R1(PETR

OL

BUNKS)

(R1) FLY

ASH

BRICKS

R1(SCHOOL

CHILDRENS

CULTURAL

ACTIVITIES

)

R1 (ORGANIC

GARDEN

CARE

BUSINESS)

(R1)

ORGA

NIC

FARMI

NG

CAPITAL

REQUIREMENT 25% 4 1 3 4 1 1

DEMAND 20% 3 3 4 3 2 2 COMPETITORS

AVAILABILITY 10% 3 2 5 3 3 3 LAND,

BUILDING,

MACHINERY

AVAILABILITY 15% 2 1

3

3 2 2 POLITICAL

REFERENCE 10% 4 2 4 4 4 4

ECO-FRIENDLY 20% 5 3 5 4 5 5

TOTAL 100% 3.6 2 3.9 3.55 2.65 2.65

Reasons for Selecting Fly Ash Bricks

1. The total score is high i.e. 3.9.

2. Change in Govt. is supporting make in India which encourages infrastructure.

3. It is environment friendly.

4. High demand for bricks.

5. High availability of labor.

Reasons for Not Selecting Others

1. RAIN WATER HARVESTING - It can be copied easily and its usage period is limited

only to rainy season.

2. PETROL BUNKS- It needs high political reference.

3. ORGANIC GARDEN CARE BUSINESS- Target audiences are very less.

4. ORGANIC FARMING- Its break even duration is very high & low productivity.

5. SCHOOL CHILDRENS CULTURAL ACTIVITIES- High care should be taken

because it is a matter about children.

Page 11: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

11

LIST OF ASSUMPTIONS

(Amount in Rupees)

ESTIMATION OF INSTALLED CAPACITY

1 production Unit 1000 /Hr.

2 No of hrs. per day 8 /Hr.

3 No. Of working Days per year 300 /Day

4 No of Shift 1

production per year 2,400,000 units

RAW MATERIALS FOR PRODUCT 1

Details of Raw material Quantity (MT) Rate(5% increase

every year)

1 Fly Ash 420 500

2 Gypsum Lime 70 2000

3 Lime 105 1500

4 Sand 35 1000

Total 630 5000

PRODUCTION AND SALES RELIASATION

Details

Name of the products Demand(UNITS) selling price per

unit(5% Increase YoY)

Fly ash brick 2,000,000 Rs 5.00

Annual sales 10,000,000.00

SALARY AND WAGES

Designation Number Salary/Month

1 Production manager 1 25,000

2 Un Skilled Workers(8000*25) 25 200,000

3 office assistant 1 12,000

4 Watch man 1 8,000

Total 53,000

MISCELLANEOUS FIXED ASSETS

S.No Amount

Office Equipment’s 30000

Telephone Etc. 1200

Furniture 35000

Computer 20000

Printers 5000

Fire Fighting Equipment’s 2000

Total 93200

PRELIMINARY AND PREOPERATIVE

EXPENSES

Details Amount

1 Project report preparation 30,000

2 Sal. During construction % Age of Sal. 120,000

Page 12: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

12

3 Trial runs (2 Days) 5,000

4 Travelling 5,000

5 Deposits 20,000

6 Application processing Fees 5,000

7 Misc.…….

Total 185,000

DEPRECIATION (SLM)

1 20% ON BUILDING

2 20% ON PLANT & MACHINERY

3 10% ON FIXED ASSETS

ASSUMPTION FOR ESTIMATING COST OF

PRODUCTION

Details Basis

1 Consumables 1% of sales 84000

2 Repairs and maintenance 2%, 3%, 4% of

P/M

36400

3 Rent, rates and taxes Rs. Per month 1000

4 Interest on term loan 12% of term loan 480000

5 Interest on working capital loan

6 selling & Administration exp. 1% of sales 100000

7 Misc. Expenses 1% of sales 100000

8 Rate of taxation 30% of Net Profit

FEASIBILITY STUDY

Estimation of Installed Capacity

Sr. No Estimation of installed

capacity

1 production Unit 1000 /Hr.

2 No of hrs. per day 8 /Hr.

3 No. Of working Days per

year

300 /Day

4 No of Shift 1

production per year 2,400,000 units

Page 13: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

13

Raw Materials for Product 1

Sr. No

Details

of raw

material

Quantity

(MT)

Rate(5%

increase

every

year) 1st 2nd 3rd 4th 5th

1 Fly Ash 420 500

210,000 220500 231525 243101 255256

2

Gypsum

Lime 70 2000

140,000 147000 154350 162068 170171

3 Lime 105 1500

157,500 165375 173643.75 182326 191442

4 Sand 35 1000

35,000 36750 38587.5 40517 42543

Total 630

542,500

569,625

598,106 628012 659412

Production and Sales Realization

Details

Sales

realization

Name of

the

products

Demand

(UNITS)

selling

price per

unit 1 year 2 year 3 year 4 year 5 year

Fly ash

brick 2,000,000 Rs 5.00 5 5.25 5.775 6.3525 6.98775

Annual

sales

10,000,000 10,500,000 11,550,000 12,127,500 12,733,875

Salary and Wages

Salaries and Wages increases

5% from 3rd year

Designation Number

Salary

/Month

Annual

Sal 1 year 2 year 3 year 4 year 5 year

Production

manager 1

25,000

300,000

300,000

300,000

315,000

330,750

347,288

Un Skilled

Workers 25

8,000

2,400,000

2,400,000

2,400,000

2,520,000

2,646,000

2,778,300

office

assistant 1

12,000

144,000

144,000

144,000

151,200

158,760

166,698

Watch man 1

8,000

96,000

96,000

96,000

100,800

105,840

111,132

Total

53,000

2,940,000

2,940,000

2,940,000

3,087,000

3,241,350

3,403,418

Page 14: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

14

S.No Final Salaries Year 1 Year 2 Year 3 Year 4 Year 5

1 Total Salary 2,940,000 2,940,000 3087000 3241350 3403418

2 % annual increase 5% 0 0 147,000 154,350 162,068

Miscellaneous Fixed Assets

Miscellaneous Fixed Assets

S.No Amount

Office Equipment’s 30000

Telephone Etc. 1200

Furniture 35000

Computer 20000

Printers 5000

Fire Fighting Equipment’s 2000

Total 93200

Preliminary and Preoperative Expenses

Preliminary and preoperative Expenses

S.No Details Amount

1 Project report preparation 30,000

2 Sal. During construction % Age of Sal 120,000

3 Trial runs (2 Days) 5,000

4 Travelling 5,000

5 Deposits 20,000

6 Application processing Fees 5,000

7 Misc.…….

Total 185,000

Depreciation

Calculation for

Depreciation 1 2 3 4 5

Building

opening Balance - 800,000 600,000 400,000 200,000

Original cost of Acquisition 1,000,000

Dep@20% 200,000 200,000 200,000 200,000 200,000

SLM 800,000 600,000 400,000 200,000 -

Page 15: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

15

Calculation for

Depreciation 1 2 3 4 5

Plant & machinery

opening Balance - 1,456,000 1,092,000 1,928,000 1,264,000

Original cost of Acquisition 1,820,000

1,500,000

Dep@20% 364,000 364,000 664,000 664,000 664,000

SLM 1,456,000 1,092,000 1,928,000 1,264,000 600,000

Calculation for Depreciation 1 2 3 4 5

Misc. Fixed Assets

opening Balance - 83,880 74,560 65,240 55,920

Original cost of Acquisition 93200

Dep@10% 9,320 9,320 9,320 9,320 9,320

SLM 83,880 74,560 65,240 55,920 46,600

Total 573,320 573,320 873,320 873,320 873,320

Assumption for Estimated Cost of Production

Details Basis 1 2 3 4 5

Consumables 1% of sales 84000 107100 249480 274428 301871

Repairs and maintenance

2%, 3%, 4% of

P/M 36400 54600 72800 72800 72800

Rent, rates and taxes Rs. Per month 1000 1100 1210 1331 1464

Interest on term loan 12% of term loan 480000 384000 288000 192000 96000

Interest on working capital

loan 12% of W C Loan 45383 53180 104132 113471 123707

selling & Administration exp. 1% of sales 100000 107100 249480 274428 301871

Misc. Expenses 1% of sales 100000 105000 115500 121275 127339

Rate of taxation 30% of Net Profit 763643 1252225 4117353 4614714 5161737

Project Cost Estimation

Assets

ESTIMATED

Project Cost 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR

Land 2,500,000

2,500,000

2,500,000

2,500,000

2,500,000

2,500,000

Building 1,000,000 800000 600000 400000 200000 0

Plant & Machinery 1,820,000 1456000 1092000 1928000 1264000 600000

working Capital

25% margin 126,063 126063 147723 289255 315197 343630

Misc. Fixed assets 93,200 83880 74560 65240 55920 46600

504,254 590,892 1,157,022 1,260,788 1,374,522

Pre & Preoperative

Expenses 185,000 185,000

Page 16: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

16

Cash 275,737

3,268,471

4,812,076

12,652,758

14,332,065

16,171,930

Total 6,000,000

8,923,668

9,817,251

18,992,275

19,927,971

21,036,682

Liability

Promoters

contribution 2,000,000.00

2,000,000

2,000,000

2,000,000

2,000,000

2,000,000

Reserves and

surplus 2545478 4174082 13724509 15382379 17205791

Term loan 4,000,000.00

4,000,000

3,200,000

2,400,000

1,600,000

800,000

Working Capital

loan

378,190

443,169

867,766

945,591

1,030,891

Balancing figure

TOTAL 6,000,000

8,923,668

9,817,251

18,992,275

19,927,971

21,036,682

Profitability Statement

Sr.

No. Unit 1 year 2 year 3 year 4 year 5 year

1 Installed capacity

2,400,000

2,400,000

4,800,000

4,800,000

4,800,000

2 Capacity utilization 70% 85% 90% 90% 90%

3 Actual production

1,680,000

2,040,000

4,320,000

4,320,000

4,320,000

4 Selling price

5

5.25

5.78

6.35

6.99

5 Total Sales

8,400,000

10,710,000

24,948,000

27,442,800

30,187,080

COST OF

PRODUCTION

A Production cost 1 year 2 year 3 year 4 year 5 year

1 Raw Materials

542,500

569,625

598,106

628,012

659,412

2

Supplies &

consumables

84,000

107,100

249,480

274,428

301,871

3 Fuel & Power

30,000

30,000

30,000

30,000

30,000

4

Repair &

Maintenance

36,400

54,600

72,800

72,800

72,800

5 Wages & Salaries

2,940,000

2,940,000

3,087,000

3,241,350

3,403,418

6 Rent, rates and taxes

12,000

13,200

14,520

15,972

17,569

7 Depreciation

573,320

573,320

873,320

873,320

873,320

TOTAL

4,218,220

4,287,845

4,925,226

5,135,882

5,358,390

Page 17: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

17

B Financial Exp.

8

Int. on term loan

(12%)

480,000

384,000

288,000

192,000

96,000

9

Int. on working

capital (12%)

45,383

53,180

104,132

113,471

123,707

C

Selling &

Administration exp. 20000 22000 24200 26620 29282

TOTAL COST OF

PRODUCTION

4,763,603

4,747,025

5,341,558

5,467,973

5,607,379

SR.

NO

1 Operating profit

4,755,100

6,995,475

20,896,094

23,180,238

25,702,010

2

Operating profit after

Dep.

4,181,780

6,422,155

20,022,774

22,306,918

24,828,690

3 Taxable income

3,636,397

5,962,975

19,606,442

21,974,827

24,579,701

4 Income tax (30%)

1,090,919

1,788,892

5,881,933

6,592,448

7,373,910

5 net profit

2,545,478

4,174,082

13,724,509

15,382,379

17,205,791

6

operating profit /

Sales %age 57% 65% 84% 84% 85%

7

net profit / Sales

%age 30% 39% 55% 56% 57%

Break Even Point

1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR

1 Sales

8,400,000

10,710,000

24,948,000

27,442,800

30,187,080

2 Variables expenses

Raw materials

542,500

569,625

598,106

628,012

659,412

Consumables

84,000

107,100

249,480

274,428

301,871

Salaries & wages

2,940,000

2,940,000

3,087,000

3,241,350

3,403,418

Interest on WC loan

45,383

53,180

104,132

113,471

123,707

Selling exp.

20,000

22,000

24,200

26,620

29,282

TOTAL

3,631,883

3,691,905

4,062,918

4,283,881

4,517,689

3 Contribution

4,768,117

7,018,095

20,885,082

23,158,919

25,669,391

Page 18: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

18

4 Fixed

cost/Expenses

Repair &

Maintenance

36,400

54,600

72,800

72,800

72,800

Wages & Salaries

2,940,000

2,940,000

3,087,000

3,241,350

3,403,418

Rent, rates and taxes

12,000

13,200

14,520

15,972

17,569

Depreciation

573,320

573,320

873,320

873,320

873,320

Int. on term loan

480,000

384,000

288,000

192,000

96,000

Int. on working

capital

45,383

53,180

104,132

113,471

123,707

Selling &

Administration exp.

20,000

22,000

24,200

26,620

29,282

GROSS PROFIT

661,014

2,977,794

16,421,110

18,623,387

21,053,295

P/V Ratio 57% 66% 84% 84% 85%

BEP

1,164,510

4,544,279

19,615,620.99

22,068,295

24,758,574

BEP % of Sales 14% 42% 79% 80% 82%

Working Capital Calculation

1.CURRENT ASSETS 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR

Raw materials 1.5months

67,813

71,203

74,763

78,501

82,427

Work-in-progress 1/2 week

40,560

41,229

47,358

49,383

51,523

Finished Goods

1/2

months

175,759

178,660

205,218

213,995

223,266

Sundry Debtors 15 days

345,205

440,137

1,025,260

1,127,786

1,240,565

TOTAL CURRENT

ASSETS

629,337

731,230

1,352,599

1,469,666

1,597,781

2. CURRENT

LIABLITIES

Creditors 2 month

104,417

112,788

141,264

150,407

160,214

Fuel & Power 2%

600

600

600

600

600

Repair & Maintenance 2 months

6,067

9,100

12,133

12,133

12,133

Supplies & consumables 2 month

14,000

17,850

41,580

45,738

50,312

Page 19: Project Appraisal and Financing of a Business Idea in Fly ash Bricks

19

TOTAL CURRENT

LIABILITIES

125,083

140,338

195,578

208,878

223,259

3. WORKING

CAPITAL GAP

504,254

590,892

1,157,022

1,260,788

1,374,522

4. MARGIN ON

WORKING CAPITAL

(25% OF 3.)

126,063

147,723

289,255

315,197

343,630

5. BANK

BORROWINGS (3. - 4.)

378,190

443,169

867,766

945,591

1,030,891

Debt Service Coverage Ratio

SR.

NO. Particulars 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 YEAR

1 Net profit after tax

2,545,478

4,174,082

13,724,509

15,382,379

17,205,791

2 Interest

525,383

437,180

392,132

305,471

219,707

3 Income tax (30%)

1,090,919

1,788,892

5,881,933

6,592,448

7,373,910

TOTAL

4,161,780

6,400,155

19,998,574

22,280,298

24,799,408

INTEREST +

INSTALLMENTS

4,000,000

3,200,000

2,400,000

1,600,000

800,000

1 Installment

800,000

800,000

800,000

800,000

800,000

2 Interest

480,000

384,000

288,000

192,000

96,000

3 Working cap. Int.

45,383

53,180

104,132

113,471

123,707

TOTAL

1,325,383

1,237,180

1,192,132

1,105,471

1,019,707

ANNUAL D S C R

3.1

5.2

16.8

20.2

24.3

AVERAGE D S C R

1.6

2.6

8.4

10.1

12.2