23
Simplifying Managing Stakeholder Expectations using the Nine-System Model and the Holistic Thinking Perspectives Joseph Kasser Temasek Defence Systems Institute (NUS) Yang Yang Zhao Norwegian Institute of System Engineering (HBV) Chandru Mirchandani Lockheed-Martin IS&GS Civil 24 th Annual INCOSE International Symposium

Simplifying managing stakeholder expectations using the 9 systems 4

Embed Size (px)

Citation preview

Page 1: Simplifying managing stakeholder expectations using the 9 systems  4

Simplifying Managing Stakeholder Expectations using the Nine-System Model and the Holistic Thinking Perspectives

Joseph KasserTemasek Defence Systems Institute (NUS)

Yang Yang ZhaoNorwegian Institute of System Engineering (HBV)

Chandru MirchandaniLockheed-Martin IS&GS Civil

24th Annual INCOSE International Symposium

Page 2: Simplifying managing stakeholder expectations using the 9 systems  4

July

2

Topics

• The MSOCC Data Switch Replacement Project

• Stakeholder management in the literature• Managing stakeholder expectations using

– the Holistic Thinking Perspectives – the Nine-System Model

• Questions and comments

Page 3: Simplifying managing stakeholder expectations using the 9 systems  4

July

3

MCSS Replacement Project• The undesirable situation

– The perception that the MSOCC will not be able to cope with its anticipated future switching requirements

– Some undesirable aspects of the current switching system need to be eliminated.

• The Feasible Conceptual Future Desirable Situation (FCFDS) – An MSOCC that will be able to cope with its anticipated future switching

requirements.

• The solution – An upgraded higher performance switch operating within the context of the

FCFDS.

• The problems 1. To develop the plan to transition from the undesirable situation to the FCFDS. 2. How to gain consensus on the plan to transition from the undesirable situation to

the FCFDS.

Page 4: Simplifying managing stakeholder expectations using the 9 systems  4

July

4

MSOCC Big picture perspective• In 1989, the Goddard Space Flight Center (GSFC) Multi-Satellite

Operations Control Center (MSOCC) was facing the problem of replacing the data switch that routed signals from multiple low earth orbit (LEO) satellites to data processing computers

• The MSOCC was the major interface between the LEO data streams from the global tracking network (Nascom) and the Telemetry Tracking and Control system at NASA’s GSFC

• Loss of LEO satellite scientific data could not be tolerated • Principle Investigators (PI) would be very upset if they lost scientific

data• There were a plurality of stakeholders in the MSOCC• There was minimal data capture and storage functionality in the

ground stations and Nascom• The MSOCC was supported by two somewhat overlapping contracts,

SEAS and NMOS

Page 5: Simplifying managing stakeholder expectations using the 9 systems  4

July

5

MSOCC Operational perspective

• Various data routing scenarios documented in the CONOPS

• The data streams from the satellites could not be switched off

• Data could arrive at any time without warning

Page 6: Simplifying managing stakeholder expectations using the 9 systems  4

July

Functional/Structural Perspectives

6

NASCOM

/49/12

/24 /16

/8

/1

/4

/8

/10NASCOM SWITCH

RUPS

TAC

DOCS

MPT

CMF

SPIF

AP

Control & Status

MODLAN

Page 7: Simplifying managing stakeholder expectations using the 9 systems  4

July

7

Continuum perspective

• Differences between– Stakeholder interests. – Stakeholders and customers.– “No loss of data” and “no downtime” (during

the transition) – Stakeholder communications and control

(contractual) interfaces

1

2

4

5

Customer

Contractor

Page 8: Simplifying managing stakeholder expectations using the 9 systems  4

July

8

Scientific Perspective

• Two well-structured problems 1. Determine the requirements for the MCSS. 2. Convert the stakeholder plurality of opinions

on the transition from the existing switch to the replacement switch to a consensus on an approach.

• Each problem has its own and shared stakeholders– Expectations that need to be managed

Page 9: Simplifying managing stakeholder expectations using the 9 systems  4

July

9

Well-structured problematic situation (MCSS)

• Seven pertinent systems• CONOPS in S3 almost identical to CONOPS in S1

– Standard situation for upgrade/replacement project (Generic HTP)– Requirements for MCSS (S6) are based on anticipated number of

input data streams and data processing equipment in future– Quick check identified COTS switches that could meet the

requirements for numbers of inputs and outputs • Uncertainty restricted to S5

– Remaining complexity can be abstracted out– Stakeholder plurality on transition of MCSS into the MSOCC (S5)

Undesirable situation (S1)Future Conceptual Feasible

Desirable Situation (S3)

Actual (created) situation (S7)1

Process to determine degree of remedy (S8)

Solution system (S6)

Process performing transition (S5) to

Process developing (S2) Operating in context of

Process planning transition (S4)

Page 10: Simplifying managing stakeholder expectations using the 9 systems  4

July

10

Topics

• The MSOCC Data Switch Replacement Project

• Stakeholder management in the literature

• Managing stakeholder expectations using– the Holistic Thinking Perspectives – the Nine-System Model

• Questions and comments

Page 11: Simplifying managing stakeholder expectations using the 9 systems  4

July

11

Stakeholder management in the literature

• Communicate with stakeholders

• Subset of an undefined list• Which are relevant?• How to manage conflicting

concerns?– QFD/QRD?

• No systemic and systematic method for managing stakeholder expectations

Page 12: Simplifying managing stakeholder expectations using the 9 systems  4

July

12

Traditional complex view of stakeholders

Stakeholder interface

12

3

456

7

8

9• Need to manage

stakeholders in the NASA MSOCC MCSS Replacement project

• Traditional view of stakeholders does not provide any guidance

Page 13: Simplifying managing stakeholder expectations using the 9 systems  4

July

13

Stakeholder Management process

1. Identifying the stakeholders.2. Identifying the areas of concern of each

stakeholder.3. Addressing the areas of concern of each

stakeholder.4. Informing the stakeholders how their areas of

concern were considered.5. Gaining stakeholder consensus on the

outcome.

Page 14: Simplifying managing stakeholder expectations using the 9 systems  4

July

14

Topics

• The MSOCC Data Switch Replacement Project

• Stakeholder management in the literature• Managing stakeholder expectations

using– the Holistic Thinking Perspectives – the Nine-System Model

• Questions and comments

Page 15: Simplifying managing stakeholder expectations using the 9 systems  4

July

15

MCSS Nine systems1. The undesirable situation

a. NASCOM data switch would not be able to cope with future anticipated needsb. Deficiencies and irritancies in existing switches

2. Most of Hitchins’ systems engineering process (Hitchins, 2007)3. FCFDS: MSOCC data switch coping with future anticipated needs

without deficiencies and irritancies in existing switches4. Transition planning task in SEAS contract, ended at SRR

– Last part of Hitchins’ systems engineering process (Hitchins, 2007)

5. Transition realization task to be assigned after SRR6. MCSS7. MSOCC in its upgraded situation8. MCSS Acceptance test9. SEAS, NMOS and NASA

Undesirable situation (S1)

Future Conceptual Feasible Desirable Situation (S3)

Actual (created)

situation (S7)1

Process to determine degree of remedy (S8)

Solution system (S6)

Process performing transition (S5) to

Process developing (S2)

Operating in context of

Process planning transition (S4)

Page 16: Simplifying managing stakeholder expectations using the 9 systems  4

July

16

The MCSS Stakeholders

• MSOCC Operators.• NASA Managers.• SEAS and NMOS managers.• Hardware and Software Developers and

testers.• NASCOM personnel.• Experiment PIs.

Page 17: Simplifying managing stakeholder expectations using the 9 systems  4

July

17

Stakeholder concern matrix [typical] at SRR time

Stakeholder S1 S2 S3 S4 S5 S6 S7 S8 S9

Dr Principle Investigator O

Oswald Operator X X X X X

Ollie Operator X X X X X

Danny Developer X X X X

Debora Developer X

Development manager X X X X X

Tammy Tester X X

Thomas Tester X

Undesirable situation (S1)

Future Conceptual Feasible Desirable Situation (S3)

Actual (created) situation (S7)1

Process to determine degree of remedy (S8)

Solution system (S6)

Process performing transition (S5) to

Process developing (S2)Operating in context of

Process planning transition (S4)

• O: Only concerned if data not forthcoming

• X: Concerns and Needs information

Page 18: Simplifying managing stakeholder expectations using the 9 systems  4

July

18

Stakeholder Management process

1. Identifying the stakeholders.2. Identifying the areas of concern of each

stakeholder.3. Addressing the areas of concern of each

stakeholder.4. Informing the stakeholders how their areas

of concern were considered.5. Gaining stakeholder consensus on the

outcome.

Page 19: Simplifying managing stakeholder expectations using the 9 systems  4

July

19

Generic perspective• Change management process• Requests for changes due to

1. Not doing what it should be doing, becausea. Something is brokenb. Something does not have capability any more (it is

overloaded)

2. Not doing something it could be doing.3. Doing something, but not as well as it could be

doing it.4. Doing something it should not be doing.

Page 20: Simplifying managing stakeholder expectations using the 9 systems  4

July

Functional perspective of change management process

Stakeholder(Source of Change)

Customer’s decision

Total impact assessment(customer & contractor)

AcceptReject

Modification

Assign ID number

Change/requirement request

Notification of decision

Convert concern or need to a requirement request

Done in S4 this for all pertinent stakeholders in S5 and S6

20 20

Page 21: Simplifying managing stakeholder expectations using the 9 systems  4

July

Direct/indirect stakeholders

MCSS

Switching system Control system

MSOCC

GSFC

NASA

Adjacent

Metasystem

Adjacent

Adjacent

Others

MCSS Requirements

flow down

Stakeholder concerns flow down

and up

Direct stakeholders are in1. Metasystem (S7)2. System (S6)3. Subsystems

Adjacent

21

Page 22: Simplifying managing stakeholder expectations using the 9 systems  4

July

22

Summary

• The MSOCC Data Switch Replacement Project

• Stakeholder management in the literature• Managing stakeholder expectations using

– the Holistic Thinking Perspectives – the Nine-System Model

• Questions and comments

Page 23: Simplifying managing stakeholder expectations using the 9 systems  4

July

23

Questions and comments

• What are the HTPs?• What are the

nine systems in the Nine-System Model?