M cKenney’s provided a turnkey design/build solution to replace an outdated chiller plant in the operating classroom complex of a government training center. THE CHALLENGE The specified chillers were much larger than the training center’s existing units, would not fit in the existing central plant’s configuration, and jeopardized the project’s timing and bud- get. Since training was in session, chilled water service could not be interrupted, and tempo- rary chillers were beyond the budget scope. THE SOLUTION McKenney’s implemented the turnkey design solution in phases and used existing central plant equipment during new central plant construction to minimize shutdowns and stay within budget. A redesign of the central plant was necessary to accommodate the new equipment, and installation took place during four complicated, prolonged shutdowns on weekends. THE RESULTS Although the scope of work dramatically changed, McKenney’s executed and com- pleted this complicated turnkey energy project on time and within budget without interrupting chilled water service. The energy savings now achieved will pay for the project costs. Turnkey Solution Saves Energy PROJECT NAME Government Facility PROJECT LOCATION Charleston, South Carolina PROJECT TEAM Owner: Federal Government Performance Contractor: Noresco Engineer: McKenney’s, Inc. SPECIALIZATIONS Building Information Modeling Design/Build Energy Management Pipe Shop Prefab MARKETS Government Central Plants The content of this document is not intended as an endorsement. www.mckenneys.com © 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A. McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners. 404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316 704-357-1200 [email protected] 3601 Performance Road Charlotte, North Carolina 28214

Turnkey Design-Build Solution Saves Energy

Embed Size (px)

DESCRIPTION

McKenney’s provided a turnkey design/build solution to replace an outdated chiller plant in the operating classroom complex of a government training center.

Citation preview

Page 1: Turnkey Design-Build Solution Saves Energy

McKenney’s provided a turnkey design/build solution to replace an outdated chiller plant in the

operating classroom complex of a government training center.

THE CHALLENGEThe specified chillers were much larger than the training center’s existing units, would not fit in the existing central plant’s configuration, and jeopardized the project’s timing and bud-

get. Since training was in session, chilled water service could not be interrupted, and tempo-rary chillers were beyond the budget scope.

THE SOLUTIONMcKenney’s implemented the turnkey design solution in phases and used existing central plant equipment during new central plant construction to minimize shutdowns and stay within budget. A redesign of the central plant was necessary to accommodate the

new equipment, and installation took place during four complicated, prolonged shutdowns on weekends.

THE RESULTSAlthough the scope of work dramatically changed, McKenney’s executed and com-pleted this complicated turnkey energy project on time and within budget without interrupting chilled water service. The energy savings now achieved will pay for the project costs.

Turnkey Solution Saves EnergyPROJECT NAME

� Government Facility

PROJECT LOCATION

� Charleston, South Carolina

PROJECT TEAM

� Owner: Federal Government

� Performance Contractor: Noresco

� Engineer: McKenney’s, Inc.

SPECIALIZATIONS

Building Information Modeling

Design/Build

Energy Management

Pipe Shop Prefab

MARKETS

� Government

� Central Plants

The content of this document is not intended as an endorsement.

www.mckenneys.com© 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.

McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.

404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316

704-357-1200 [email protected]

3601 Performance Road Charlotte, North Carolina 28214