View
426
Download
0
Embed Size (px)
DESCRIPTION
Part 2 of the presentation entitled "Water Management Financing in the Caribbean."
Citation preview
Finance Models/Source of Finance Finance Models/Source of Finance
Traditional Method via Multi/Bi-Lateral Traditional Method via Multi/Bi-Lateral Agencies Agencies Alternative Project Development Approach Alternative Project Development Approach (APDA(APDA) ) - Value Engineering Option- Value Engineering OptionGrant Financing Grant Financing Public Private Partnership (PPP)Public Private Partnership (PPP)Commercial Bank LoansCommercial Bank LoansTariff via K-Factor Programme Tariff via K-Factor Programme Credit Enhancement Fund - CReW Credit Enhancement Fund - CReW
Programme Programme
TRADITIONAL APPROACH TRADITIONAL APPROACH TO PROJECT FINANCINGTO PROJECT FINANCING
Construction & expansion of water & wastewater infrastructure usually requires
LARGE CAPITAL INPUT
LONG AMORTIZATION PERIOD
INTERNATIONAL FUNDING AGENCIES
CAPITAL MORATORIUM, LONG REPAYMENT TERM, LOW INTEREST RATES
Implementation of water supply and sewerage Implementation of water supply and sewerage projects have been undertaken projects have been undertaken
‘‘Traditionally via the Application of Standard Traditionally via the Application of Standard Project Management ProcessesProject Management Processes’’
Preliminary DesignPreliminary Design Finance Sought (Multi-lateral/Bi-lateral Agency)Finance Sought (Multi-lateral/Bi-lateral Agency) Detailed DesignDetailed Design
• Tendering & selection of Design consultantsTendering & selection of Design consultants• Design workDesign work
ConstructionConstruction• Tendering & selection of contractorTendering & selection of contractor• Implementation of the worksImplementation of the works
Delays due to issues relating to :Delays due to issues relating to :1.1. Procurement process - Multi Agencies & Multi Layer Procurement process - Multi Agencies & Multi Layer
Approval Processes Approval Processes 2.2. Terms of the financing - Level of inflexibility to respond Terms of the financing - Level of inflexibility to respond
to changes of situations to changes of situations
Traditional Finance MethodTraditional Finance Method No. Project / Sponsor Loan
Value
US$M
Project Initiated in Year
Project Status
Rate %
Moratorium Years
Tenure Years
Elapse Time
in Years (From Loan Approval –
Implementation )
1.0KMA Water Supply Improvement Project (JICA)
85.0M 1990’s 2010 Phase # 1 Completed.
2.50 4 25 10
2.0 Port Antonio Water Supply Improvement Project (EIB)
40.0M Mid 1990’s
Work delayed. No Fiscal Space.
3.00 5 1510
3.0 Kingston Water & Sanitation Project (IDB)
40.0M 1998 New loan being negotiated.Components being implemented.US$15.0M diverted Food Safety Program.
1.10 4 247
Loan Terms and Conditions are attractive & favourable. Challenge : Duration between Loan Approval & Completion of Project is long.Unsuitable for works with ‘Relatively Fast Commercial
Returns’
Alternative Project Development Alternative Project Development Approach (APDAApproach (APDA))
LONG LEAD TIMEFORTUNATELY SOME PROJECTS REPRESENT AN
OPPORTUNITY FOR RELATIVELY FAST COMMERCIAL RETURNS
SO THEY ALSO OFFER AN OPPORTUNITY FOR AN ALTERNATIVE IMPLEMENTATION & FINANCING APPROACH
• EARLY (and LARGE) REVENUE STREAM
•
• IMPACT CHARGES - CONNECTION FEES
Alternative Project Development ApproachAlternative Project Development Approach
DEVELOPING AND IMPLEMENTING PROJECTS DEVELOPING AND IMPLEMENTING PROJECTS USING THE TRADITIONAL APPROACH – USING THE TRADITIONAL APPROACH – WITH WITH FUNDING ASSISTANCE FROM INTERNATIONAL FUNDING ASSISTANCE FROM INTERNATIONAL AGENCIESAGENCIES - IS DIFFICULT - IS DIFFICULT
Alternative Project Development Approach (APDA)
Integrated Project Management Team Established with the
- NWC
- Independent Consultant
- Construction Company
BUILT ON MUTUAL RESPECT AND TRUST
An innovative approach to Project Development and Implementation has been developed
GENERAL PROCEDURE for APDA
1. NWC DEFINES PRIORITY OBJECTIVES
2. NATIONAL CONTRACTS COMMISSION (NCC) APPRAISED
3. INDEPENDENT CONSULTANT APPOINTED
4. CONSTRUCTION COMPANY SELECTED
6a. CONSULTANT’S COST ESTIMATE
6b. CONSTRUCTION COMPANY’S PROPOSAL FOR COST & FINANCING
7. NEGOTIATIONS
5. PROJECT TEAM, USING COLLECTIVE EXPERIENCE, DEFINES PROJECT IN DETAIL – TO OPTIMIZE NWC INVESTMENT
8. “VALUE-FOR-MONEY” SUBMISSION TO NCC FOR APPROVAL
10. IMPLEMENTATION
9. CABINET APPROVAL
NWC’S APDA EXPERIENCE- The US$39 M GREAT RIVER PROJECT
• 5 migd EXPANSION• GREAT RIVER
TREATMENT PLANT
• 20km, 500mm Ø
TRUNK MAIN to LUCEA
NWC’S APDA EXPERIENCE -TIMELINE
GREAT RIVER PROJECT AUGUST 2000 – M.O.U. for FRENCH GOVERNMENT FINANCED STUDY (5migd Treatment Plant & 20kms 500mm Ø
Pipeline) MARCH 2001 STUDY COMMENCED
AUGUST 2001 STUDY COMPLETED
NOVEMBER 2002 INDEPENDENT CONSULTANT APPOINTED
DECEMBER 2002 SOGEA – SATOM’S PROPOSAL
DECEMBER 2002 to JULY 2002 - NEGOTIATIONS, FINANCE PACKAGING & APPROVAL JULY 2002 – CONTRACTS SIGNED
DECEMBER 2002 – FINANCIAL CLOSURE
MARCH 2003 – ORDER TO COMMENCE
OCTOBER 2004 – PROJECT COMPLETED ON BUDGET
ELAPSED TIME – 4 YEARS
FINANCINGThe GREAT RIVER PROJECT
ARRANGED BY CONTRACTOR:
COMMERCIAL LOAN 6 Million EURO - 4 years - 7.5%
FRENCH BUYER CREDIT 9 Million EURO - 7 years - 3.6%
ARRANGED BY NWC:
COMMERCIAL LOAN 3.8 Million EURO - 8 years - 9.25%
3 Million US$ - 4 years - 7.5%
46% of PROJECT COST
54% of PROJECT COST
17.2 Million US$ - 5 years - 9.25%
JAMAICA WATER SUPPLY JAMAICA WATER SUPPLY IMPROVEMENT PROJECTIMPROVEMENT PROJECT
Alternative Project Development Alternative Project Development ApproacApproach h - APDA- APDA
JAMAICA WATER SUPPLY JAMAICA WATER SUPPLY IMPROVEMENT PROJECTIMPROVEMENT PROJECT
In 2006 NWC received an unsolicited proposal to In 2006 NWC received an unsolicited proposal to
address the water supply shortfall in KSA address the water supply shortfall in KSA – – ‘The ‘The
Kingston Improvement Project ‘Kingston Improvement Project ‘
The proposal was considered and the The proposal was considered and the Alternative Alternative
Project Development Approach appliedProject Development Approach applied
Independent Consultant was appointed in 2007Independent Consultant was appointed in 2007
Over time the project evolved into the Over time the project evolved into the Jamaica Jamaica
Water Supply Improvement Project (JWSIP)Water Supply Improvement Project (JWSIP) to to
include projects in rural areas of the island.include projects in rural areas of the island.
JAMAICA WATER SUPPLY JAMAICA WATER SUPPLY IMPROVEMENT PROJECTIMPROVEMENT PROJECT
The Project consists of (2) Segments The Project consists of (2) Segments
CATEGORY A - BNP Paribas / VINCI Grand ProjectCATEGORY A - BNP Paribas / VINCI Grand Project Rehabilition - 20MGD Constant Spring & Seaview WTP Rehabilition - 20MGD Constant Spring & Seaview WTP New wells (Halls Green) – 1 mgdNew wells (Halls Green) – 1 mgd Replacement of asbestos cement Rio Cobre Pipeline (Bog Walk to Replacement of asbestos cement Rio Cobre Pipeline (Bog Walk to
Dam Head) Dam Head) Consumer Metering – 70,000 metersConsumer Metering – 70,000 meters
CATEGORY BCATEGORY B - Bank of Nova Scotia (BNS) - Bank of Nova Scotia (BNS) New 15 mgd WTPNew 15 mgd WTP Replacement of asbestos cement Rio Cobre Pipeline (Dam Head Replacement of asbestos cement Rio Cobre Pipeline (Dam Head
to Ferry)to Ferry) Network improvements (F/Hills & Stony Hill)Network improvements (F/Hills & Stony Hill) Connecting Pipeline to F/HillsConnecting Pipeline to F/Hills Rural WS ProjectsRural WS Projects
Replacement of Rio Cobre
PipelinePart 1 & 2
Construction of Rio Cobre WTP 15 MGD Construction
of Ferry to Red Hills relift scheme
Refurbishment of Constant Spring WTP
Refurbishment of Seaview
WTP
Halls Green Wells and Reservoir
Forest Hills / Red Hills Network Improvement
Stony Hill Network
Improvement
Category ACategory A - - Commenced - March 2010 Commenced - March 2010 Scheduled Completion - April 2012 Scheduled Completion - April 2012
JWSIP JWSIP Project Benefits include :Project Benefits include :
A.A. Addressing the Addressing the Water Supply Shortfall/Deficit Water Supply Shortfall/Deficit in in the Kingston Metropolitan Area – KMA via :the Kingston Metropolitan Area – KMA via :• New sources ( New Treatment Plants 15MGD /Well)New sources ( New Treatment Plants 15MGD /Well)• reduction of water lossesreduction of water losses
B.B. Improve ReliabilityImprove Reliability• Rehabilitation of two major WTPs in the KSARehabilitation of two major WTPs in the KSA• Network improvement - Stony Hill Network improvement - Stony Hill
C.C. Improvement in the Improvement in the efficiencyefficiency of the operations of the operations ELAPSE TIME : 2006 TO 2012ELAPSE TIME : 2006 TO 2012
JAMAICA WATER SUPPLY JAMAICA WATER SUPPLY IMPROVEMENT PROJECTIMPROVEMENT PROJECT