Bond Program Website Development – Executive Summary Page
Page 1 of 2
HCC 2013 Capital Improvements Program Houston Texas
Budget: $425M
Program Duration: Sept 2013 – Sept 2017
Architects of Record: HDR, Kirksey, PBK, PDG, PGAL, and SHW Group
Services Provided: Designs for new and renovated facilities and technology in academic areas associated with medical/healthcare, health sciences, science, technology, engineering and mathematics (STEM) and Workforce Centers. All programs in CIP total approximately 1Million square feet of academic space
Program Manager: Jacobs Program Management Co.
Services Provided: Overall Program Management
Master Scheduling
Master Planning Management
Overall Design Management
Construction Process Management
Overall Master Budget
Overall Cost Estimating
Overall Budget Controls
Overall Procurement Support
Real-time Web Reporting Support
Project Managers: Freese & Nichols, Heery, and Jones, Lang & Lasalle
Services Provided: Project Scheduling
Project Level Design Management
Construction Process Management
Project Level Budgeting
Project Level Cost Estimating
Project Level Procurement
Program Executive Summary: October 2012
Our current $425 million program includes all CIP team members under contract and working collaboratively on critical planning and management portions of the 2013 Capital Improvements Program (CIP). Over the past 60 days there has been major progress made on Program Start-up activities/mobilization, HCC Design Standards Evaluation, Program Validation efforts between the A/E
Bond Program Website Development – Executive Summary Page
Page 2 of 2
firms and key Campus staff including each Campus President. There is also accomplishment in completing the Small Business Enterprise Implementation Plan and the publication of the Request for Proposal for the Construction Manager at Risk (scheduled for selection recommendation in February 2014).
The CIP team has completed the first phase of development for the Program Execution Plan (PEP). This document contains all of the critical procedures and flow diagrams that will be used by all CIP team members to ensure consistency in all daily operations and compliance with policies and regulations to eliminate delays and confusion. The first phase development effort included HCC Administrative and Construction Management staff, HCC Financial and Legal staff, HCC Procurement and Technology staff and outside Construction Audit consultant contracted by HCC.
What’s Next: The PEP will move to Phase Two development over the upcoming weeks. Building Programming efforts by the A/E firms will continue until early 2014. The CMAR selection process will begin in the up-coming weeks. Our first SBE Outreach Event is targeted for January 2014
Bond Program Website Development – Project Summary Pages
Page 1 of 14
Central Campus Building Renovations & Parking Garage Alabama Street & LaBranch Street 77004 Central Campus
Scope of Work: New Culinary Arts Facility Construction, Existing Facility Renovations & Parking
Budget: $23.5M
Project Manager: Freese & Nichols
Architect of Record: SHW Group
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Sep 2013 - Feb 2016 = 30 Months7% Overall Percent Complete
2017Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 3
2013 2014 2015 2016Qtr 2 Qtr 3 Qtr 4Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1Qtr 4 Qtr 1 Qtr 2 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Aug 2014)
Construction (Oct 2014 ‐ Jan 2016)
FF&E Installation & Move‐in (Dec 2015 ‐ Feb 2016)
Permitting (Sep 2014 ‐Oct 2014)
Bond Program Website Development – Project Summary Pages
Page 2 of 14
Central South Campus Workforce Building 1990 Airport Boulevard 77051 South Campus
Scope of Work: New Workforce Facility Construction
Budget: $24.5M
Project Manager: Freese & Nichols
Architect of Record: SHW Group
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
2013 2014 2015 2016 2017
Sep 2013 - May 2016 = 33 Months6% Overall Percent Complete
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Oct 2014)
Construction (Jan 2015 ‐Mar 2016)
FF&E Installation & Move‐in (Mar 2016 ‐May 2016)
Permitting (Nov 2014 ‐ Jan 2015)
Bond Program Website Development – Project Summary Pages
Page 3 of 14
Coleman College Health Care Education Facility Expansion Main Street & Pressler Street 77030 Coleman College for Health Sciences
Scope of Work: New Healthcare Educational Facility Construction
Budget: $120M
Project Manager: Heery
Architect of Record: HDR
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Additional programming efforts to focus on preliminary site analysis to confirm final land allocation required from Texas Medical Center.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Qtr 2 Qtr 3 Qtr 4 Qtr 1
5% Overall Percent CompleteSep 2013 - Dec 2016 = 40 Months
2013 2014 2015 2016 2017Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1
Status Completion Bar
Programming (Sep 2013 ‐Nov 2013)
Design (Dec 2013 ‐Dec 2014)
FF&E Installation & Move‐in (Oct 2016 ‐Dec 2016)
Permitting (Jan 15 ‐ Feb 2015)
Construction (Feb 2015 ‐Oct 2016)
Bond Program Website Development – Project Summary Pages
Page 4 of 14
Northline Instructional Building & Parking/Multi-Use Facility 8001 Fulton Street 77022 Northline Campus
Scope of Work: New Instructional Facility & Parking Garage/Multi-Use Facility Construction
Budget: $20M
Project Manager: Freese & Nichols
Architect of Record: PGAL
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
6% Overall Percent CompleteSep 2013 - May 2016 = 33 Months
2013 2014 2015 2016 2017Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐ Jan 2014)
Design (Feb 2014 ‐Nov 2014)
Construction (Jan 2015 ‐Mar 2016)
FF&E Installation & Move‐in (Mar 2016 ‐May 2016)
Permitting (Dec 14 ‐ Jan 2015)
Bond Program Website Development – Project Summary Pages
Page 5 of 14
North Forest Workforce & Early College High School Center of Excellence in Automotive Little York Road & Homestead Road 77016 North Forest Campus
Scope of Work: New Workforce Facility Center of Excellence & Automotive Technology Center Construction
Budget: $40M
Project Manager: Freese & Nichols
Architect of Record: PGAL
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Qtr 2 Qtr 3 Qtr 4 Qtr 1
6% Overall Percent CompleteSep 2013 - Mar 2016 = 31 Months
2013 2014 2015 2016 2017Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Aug 2014)
Construction (Nov 2014 ‐ Jan 2016)
FF&E Installation & Move‐in (Jan 2016 ‐Mar 2016)
Permitting (Sep2014 ‐Nov 2014)
Bond Program Website Development – Project Summary Pages
Page 6 of 14
New Acres Homes Campus Little York Road & North Shepherd Drive 77091 New Northeast Campus
Scope of Work: New Campus/Academic Facility Construction
Budget: $13M
Project Manager: Jones, Lang & Lasalle
Architect of Record: PBK
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
7% Overall Percent CompleteSep 2013 - Feb 2016 = 30 Months
2013 2014 2015 2016 2017Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Aug 2014)
Construction (Oct 2014 ‐Dec 2016)
FF&E Installation & Move‐in (Dec2015 ‐ Feb 2016)
Permitting (Sep2014 ‐Oct 2014)
Bond Program Website Development – Project Summary Pages
Page 7 of 14
The West Houston Institute Westheimer Road & Eldridge Parkway 77082 Westside Campus
Scope of Work: New Campus/Science, Technology, Engineering & Math Facility Construction
Budget: $53M
Project Manager: Jones, Lang & Lasalle
Architect of Record: PBK
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Qtr 2 Qtr 3 Qtr 4 Qtr 1
5% Overall Percent CompleteSep 2013 - Sep 2016 = 37 Months
2013 2014 2015 2016 2017Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1
Status Completion Bar
Programming (Sep 2013 ‐Nov2013)
Design (Dec 2013 ‐Dec2014)
FF&E Installation & Move‐in (Aug 2016 ‐ Sep 2016)
Permitting (Jan 2015 ‐Mar 2015)
Construction (Feb2015‐Aug 2016)
Bond Program Website Development – Project Summary Pages
Page 8 of 14
Alief Campus Improvements 2811 Hayes Road 77082 Alief Campus
Scope of Work: Existing Facility Finish-out for New Center for Entrepreneurship & Film Program Curriculum Center
Budget: $10M
Project Manager: Jones, Lang & Lasalle
Architect of Record: PBK
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
6% Overall Percent CompleteSep 2013 - Apr 2016 = 32 Months
2013 2014 2015 2016 2017Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Nov2013)
Design (Dec 2013 ‐Nov 2014)
Construction (Jan2015‐Mar 2016)
FF&E Installation & Move‐in (Mar 2016 ‐Apr 2016)
Permitting (Dec 2014 ‐ Jan 2015)
Bond Program Website Development – Project Summary Pages
Page 9 of 14
New Eastside Campus 6815 Rustic Drive 77087 Eastside Campus
Scope of Work: New Campus/Workforce Facility Construction
Budget: $26.5M
Project Manager: Heery
Architect of Record: PDG
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation effort commenced on portions of project not impacted by land acquisition.
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue on portions of project not impacted by land acquisition.
Weekly team meetings including real-estate agents, continue for progress status and acquisition closing dates confirmation.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Qtr 2 Qtr 3 Qtr 4 Qtr 1
5% Overall Percent CompleteSep 2013 - Feb 2017 = 42 Months
2013 2014 2015 2016 2017Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐ Jul 2015)
Construction (Sep 2015 ‐Dec 2016)
FF&E Installation & Move‐in (Dec 2016 ‐ Feb 2017)
Permitting (Aug 2015 ‐ Sep 2015)
Bond Program Website Development – Project Summary Pages
Page 10 of 14
Felix Fraga Stem Facility 301 North Drennan Street 77003 Felix Fraga Campus
Scope of Work: New Science, Technology, Engineering & Math Facility Construction
Budget: $16M
Project Manager: Heery
Architect of Record: PDG
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
7% Overall Percent CompleteSep 2013 - Feb 2016 = 30 Months
2013 2014 2015 2016 2017Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Aug 2014)
Construction (Oct 2014 ‐Dec 2015)
FF&E Installation & Move‐in (Dec 2015 ‐ Feb 2016)
Permitting (Sep 2014 ‐Oct 2014)
Bond Program Website Development – Project Summary Pages
Page 11 of 14
West Loop Parking & Multi-Use Facility 5601 West Loop South 77801 West Loop Center
Scope of Work: New Parking Garage/Multi-Use Facility Construction
Budget: $18M
Project Manager: Jones, Lang & Lasalle
Architect of Record: Kirksey
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Qtr 2 Qtr 3 Qtr 4 Qtr 1
7% Overall Percent CompleteSep 2013 - Jan 2016 = 29 Months
2013 2014 2015 2016 2017Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Aug 2014)
Construction (Oct 2014 ‐Dec 2015)
FF&E Installation & Move‐in (Dec 2015 ‐ Jan 2015)
Permitting (Sep 2014 ‐Oct 2014)
Bond Program Website Development – Project Summary Pages
Page 12 of 14
Brays Oaks New Campus Workforce Building West Belfort & Riceville Road 77031 Brays Oaks Campus
Scope of Work: New Campus/Workforce Facility Construction
Budget: $12M
Project Manager: Jones, Lang & Lasalle
Architect of Record: Kirksey
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
6% Overall Percent CompleteSep 2013 - Jun 2016 = 34 Months
2013 2014 2015 2016 2017Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Dec 2014)
Construction (Feb 2015 Apr 2016)
FF&E Installation & Move‐in (Apr 2016 ‐ Jun 2016)
Permitting (Jan 2015 ‐ Feb 2015)
Bond Program Website Development – Project Summary Pages
Page 13 of 14
Stafford New Workforce Building 10041 Cash Road 77477 Stafford Campus
Scope of Work: New Workforce Facility Construction
Budget: $27M
Project Manager: Jones, Lang & Lasalle
Architect of Record: Kirksey
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Qtr 2 Qtr 3 Qtr 4 Qtr 1
8% Overall Percent CompleteSep 2013 - Jun 2016 = 25 Months
2013 2014 2015 2016 2017Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐ Jul 2014)
Construction (Sep 2014 Aug2015)
Permitting (Aug 2014 ‐ Sep 2014)
FF&E Installation & Move‐in (Aug 2015 ‐ Sep 2015)
Bond Program Website Development – Project Summary Pages
Page 14 of 14
Missouri City Center for Entrepreneurship, Technology, & Health (CETH) 5855 Sienna Springs Way 77459 Missouri City Center
Scope of Work: New Center for Entrepreneurship, Technology, & Health Facility Construction
Budget: $21.5M
Project Manager: Jones, Lang & Lasalle
Architect of Record: Kirksey
Construction Manager at Risk: Feb-14 Board Approval
Schedule
Executive Summary Activities Performed Last 30 Days: Programming validation efforts commenced
Meetings included Campus Presidents and Key Staff.
Follow-up recap meetings conducted by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
Activities Projected Next 30 Days: Programming validation efforts continue.
Follow-up recap meetings continue by Project Managers, AE, HCC Construction Managers, and Program Manager to resolve issues as applicable.
8% Overall Percent CompleteSep 2013 - Oct 2015 = 26 Months
2013 2014 2015 2016 2017Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
Status Completion Bar
Programming (Sep 2013 ‐Oct 2013)
Design (Nov 2013 ‐Aug 2014)
Construction (Oct 2014 Aug2015)
Permitting (Sep 2014 ‐Oct 2014)
FF&E Installation & Move‐in (Aug 2015 ‐Oct 2015)