7
ARUNDAS.D Mechanical Engineer Contact Nos.: 00966549443641/ 00914792437883 E-Mail: [email protected] Seeking assignments in MEP Project Engineering and Management with an organization of high repute preferably in Construction (EPC) industry PROFILE SUMMARY A performance driven professional with 08 years and 7 months of hand own experience in: ~ MEP Projects Execution & Management in Hospitals, Hotels, Factories, Warehouses, High rise and residential building construction projects. ~ Project planning through MS project Gantt chart. ~ Preparation, execution & monitoring, testing and commissioning of all MEP systems like HVAC ,Plumbing. (drainage ,water supply, chiller piping, pumps & Firefighting), FM 200 ,Air Sampling system, Medical Gas ,BMS, Complete Electrical & Low Current systems as per compliance with the plan, shop drawing, specification, standards and schedule. ~ Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision. ~ Hospitals and Hotels Engineering (MEP and civil) standards. ~ Medical Engineering standards for various medical projects like radiology,laboratories,operation theatres,morgue etc. ~ Post & Pre Installation for Health care equipments like MRI SCAN,CT SCAN, X-RAY and ultrasound machineries including installation, testing and commissioning of all required MEP systems and sub-systems. ~ Facility management, Operation and maintenance, Maintenance operation policies & procedures. ~ Shop drawing and As built preparation in Auto cad ,its submittal and obtaining client/consultant approval. ~ Sub contractor, vendor, Contractor bills and Manpower management. ~ Raising of purchase orders, purchase requisitions. ~ Detailed Quantity Calculations for BOQ/Tender, BOM, Invoicing, Estimation, Budgeting, Costing, Measurements of work, Extra Items with Rate Analysis & Deviation Etc.. ~ Review and Check shop Drawings, Technical Bid Analysis, and Specifications, Prepare and Monitor Engineering Documents ~ Assisting in the formulation, strict implementation, monitoring and reporting of safety Rules & standards in the project sites. ~ Preparing technical proposals, its submittal and obtaining client/consultant approval. ~ Material Procurement, Sub Contracts management, Sub contracts agreement, Price negotiations. ~ Documentation (Project related ,Administration, ISO, EMS and OHSAS). Sound exposure in HVAC standards like ASHRAE, SMACNA. Plumbing codes like NFPA, IPC & Electrical code (NEC). Sound exposure in Plumbing pipes selection and its sizing, Medical gas Plumbing fixtures & equipment selection (pumps, valves etc.), Irrigation system, water features, Centralized water heater system, drainage and water supply network. Sound exposure in Fire fighting sprinkler system, FM200, Automatic co2 extinguisher, Air sampling system, Fire extinguisher cylinders. Sound exposure in Installation, testing and commissioning of various pipe like galvanized steel, black steel, stainless steel, copper, u PVC, c PVC, PVC, PPR, HDPE, LDPE pipes and relevant joints like rubber ring, solvent, welded joints and fittings. Sound exposure in HVAC heat load calculation, HVAC equipment selection, Duct materials selection and Duct sizing. Adept in DX & chilled water systems, FCU's, AHU's, Air and water cooled Chillers, Cooling towers, Heat exchangers Package roof top units, Exhaust Fans, VRF air conditioning system, Desert coolers and its electrical systems and requirement. Sound exposure in Electrical power load calculation and all Electrical systems installations like installation of EMT, RSC and pvc conduits, Bus Bar with tap offs cable trays and ladders, feeder cables, panel boards, MCC panels, electrical MDB'S, Earthing & lightning arrestor systems, Lighting and power system Wiring with looping and home run. Sound exposure in low current systems like Matv, Cctv, BMS, Public address, Master Clock, Data and telephone network Systems (network switches, patch panels, Fiber optic cables, MDF's, IDF's). Deft in preparing daily work plans and ensuring that PTW and safety measures for better HSE are completed before the start. Track record of targeting zero safety violation of team members, in terms of PPE and other works carried out at site. Sound exposure in OHSAS, ISO&TS environment, fire and safety and Environment management system (EMS).

Arun das latest resume

Embed Size (px)

Citation preview

Page 1: Arun das latest resume

ARUNDAS.D

Mechanical Engineer

Contact Nos.: 00966549443641/ 00914792437883

E-Mail: [email protected]

Seeking assignments in MEP Project Engineering and Management with an organization of high repute

preferably in Construction (EPC) industry

PROFILE SUMMARY

A performance driven professional with 08 years and 7 months of hand own experience in:

~ MEP Projects Execution & Management in Hospitals, Hotels, Factories, Warehouses, High rise and

residential building construction projects.

~ Project planning through MS project Gantt chart.

~ Preparation, execution & monitoring, testing and commissioning of all MEP systems like HVAC ,Plumbing.

(drainage ,water supply, chiller piping, pumps & Firefighting), FM 200 ,Air Sampling system, Medical Gas ,BMS,

Complete Electrical & Low Current systems as per compliance with the plan, shop drawing, specification, standards

and schedule.

~ Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

~ Hospitals and Hotels Engineering (MEP and civil) standards.

~ Medical Engineering standards for various medical projects like radiology,laboratories,operation theatres,morgue etc.

~ Post & Pre Installation for Health care equipments like MRI SCAN,CT SCAN, X-RAY and ultrasound machineries

including installation, testing and commissioning of all required MEP systems and sub-systems.

~ Facility management, Operation and maintenance, Maintenance operation policies & procedures.

~ Shop drawing and As built preparation in Auto cad ,its submittal and obtaining client/consultant approval.

~ Sub contractor, vendor, Contractor bills and Manpower management.

~ Raising of purchase orders, purchase requisitions.

~ Detailed Quantity Calculations for BOQ/Tender, BOM, Invoicing, Estimation, Budgeting, Costing, Measurements of work,

Extra Items with Rate Analysis & Deviation Etc..

~ Review and Check shop Drawings, Technical Bid Analysis, and Specifications, Prepare and Monitor Engineering

Documents

~ Assisting in the formulation, strict implementation, monitoring and reporting of safety Rules & standards in the project

sites.

~ Preparing technical proposals, its submittal and obtaining client/consultant approval.

~ Material Procurement, Sub Contracts management, Sub contracts agreement, Price negotiations.

~ Documentation (Project related ,Administration, ISO, EMS and OHSAS).

Sound exposure in HVAC standards like ASHRAE, SMACNA. Plumbing codes like NFPA, IPC & Electrical code (NEC).

Sound exposure in Plumbing pipes selection and its sizing, Medical gas Plumbing fixtures & equipment selection (pumps,

valves etc.), Irrigation system, water features, Centralized water heater system, drainage and water supply network.

Sound exposure in Fire fighting sprinkler system, FM200, Automatic co2 extinguisher, Air sampling system, Fire

extinguisher cylinders.

Sound exposure in Installation, testing and commissioning of various pipe like galvanized steel, black steel, stainless

steel, copper, u PVC, c PVC, PVC, PPR, HDPE, LDPE pipes and relevant joints like rubber ring, solvent, welded joints and

fittings.

Sound exposure in HVAC heat load calculation, HVAC equipment selection, Duct materials selection and Duct sizing.

Adept in DX & chilled water systems, FCU's, AHU's, Air and water cooled Chillers, Cooling towers, Heat exchangers

Package roof top units, Exhaust Fans, VRF air conditioning system, Desert coolers and its electrical systems and

requirement.

Sound exposure in Electrical power load calculation and all Electrical systems installations like installation of EMT, RSC

and pvc conduits, Bus Bar with tap offs cable trays and ladders, feeder cables, panel boards, MCC panels, electrical

MDB'S, Earthing & lightning arrestor systems, Lighting and power system Wiring with looping and home run.

Sound exposure in low current systems like Matv, Cctv, BMS, Public address, Master Clock, Data and telephone network

Systems (network switches, patch panels, Fiber optic cables, MDF's, IDF's).

Deft in preparing daily work plans and ensuring that PTW and safety measures for better HSE are completed before

the start.

Track record of targeting zero safety violation of team members, in terms of PPE and other works carried out at site.

Sound exposure in OHSAS, ISO&TS environment, fire and safety and Environment management system (EMS).

Page 2: Arun das latest resume

Proficient in swiftly completing up projects with competent cross-functional skills and ensuring on time deliverables within

pre-set cost parameters.

Track record of developing operations & maintenance procedures to increase the efficiency and accordingly implementing

standards and ensuring adherence to quality standards through in-process checks.

An effective communicator, proactive planner & negotiator with strong analytical, problem solving, strong communication

skills and organizational abilities.

Instrumental in maintenance of the rotary and static equipments.

Adept in fasteners, fittings, piping, pumps, valves, Hydraulic and pneumatic systems.

CORE COMPETENCIES

Analyzing project requirements and reviewing all the project proposals wherein mapping requirements of manpower/

materials resources in which ensuring cost effective execution as per schedule.

Capability to Handle Multiple Projects.

Investigation and Resolution of Field-initiated Questions Pertaining To Design and Engineering.

During installation resolve the conflicts between different systems and make as built drawing with the approval of the

consultant before the installation to avoid any discrepancies.

Liaising with Consultants/Clients for Materials and drawings Submissions(RFA) and approvals.

Ensuring that inspection request (RFI) are raised for the consultant and the client inspection and coordinate for inspection.

Perform all MEP site activities and coordinate with construction, structure, engineering and architecture departments

during installation of electrical and mechanical systems to ensure quality, compliance and execution of works according

to the Consultant and Work Owner expectations in most economical manner.

Performing Pre/ Post installation audit at site with final Drawings.

Developing project baselines while monitoring and controlling projects with respect to cost, resource deployment, time

over-runs and quality compliance to ensure its satisfactory execution.

Anchoring erection & commissioning of equipments and ensured completion of project in minimum turnaround time with

effective resource utilization to maximize the output.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Identifying areas of obstruction/ breakdown and taking steps to rectify the equipments through application of troubleshooting

tools.

Well versed with Scheduled maintenance (TBM) and condition based maintenance (CBM) Tools and activities.

WORK EXPERIENCE

Since Sept’10 Dani Ellia Building Solutions, Riyadh, Kingdom of Saudi Arabia

Projects Engineer (MEP Division)

Key Result Areas:

Planning and ensuring mechanical and electrical installation as per approved drawings and material approvals.

Supervising day-to-day site operations.

Preparation, execution & monitoring, testing and commissioning of all MEP systems as per compliance with

the plan, shop drawing, specification, standards and schedule.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Developing the Bill of Materials for the completion of works.

Project Reporting, , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Quantity Calculations for BOQ/Tender, Invoicing, Estimation, Budgeting, Costing, Measurements of work, Extra Items with

Rate Analysis & Deviation Etc.

Receive quotations, classify, compare and negotiate.

Monitor consumption of material with respect to the ordered materials.

Maintaining a system of documentation for monitoring the productivity of teams.

Ensuring that inspection request (RFI) are raised for the consultant and the client inspection

Liaising with Consultants for Materials Submissions and approvals (RFA).

Ensuring that approved method statements are available explaining the method statements to the foreman and charge

hand while maintaining proper documentation for records.

Testing and commissioning of all MEP systems like HVAC, Plumbing, Electrical, Low current systems.

Handling QHSE and EHS audits and documents.

Efficiently worked in coordination:

o For obtaining ISO, EMS And OHSAS Certifications.

o With various departments of hospitals like engineering, infection control etc.

to ensure that project is in line with hospital standards.

Page 3: Arun das latest resume

o With vendors and sub-contractors.

o With major clients as SEIMENS HEALTH CARE LTD and GE HEALTH CARE LTD & is aware of their

systems , Standards, policies and procedures.

Played a key role in:

o Preparation and submission of shop drawings, as built drawings and O&M manuals.

o Preparation of documents and coordinate for main vendor/subcontractor audits. Handling of QHSE and EHS

audits and documents.

Highlight:

Successfully received 2 Awards as Best Project Engineer for completing the projects on time at King Fahad Medical City,

Prince Sultan Military Medical City and AL-Batal Design.

PREVIOUS WORK EXPERIENCE

1 Sep’08 to 17 Aug’10 with MRF Tyres Limited, Arkonam (Tamil Nadu)

Mechanical Engineer(Jr. Executive) - Engineering Department

Key Result Areas:

Facility management, Operation and maintenance, carrying out Maintenance operation as per policies & procedures.

Handled Erection and commissioning of all machineries required for tyre manufacturing (Engineering projects), Operation

and maintenance of tyre manufacturing machineries, Conveyor systems, Pumps, Air compressors, D.G sets, Boilers,

Hydraulic and pneumatic systems, heat exchangers, cooling towers, chillers, Fire Hydrants, HVAC system, Electric hoists,

Hydraulic lifting equipments, Diesel forklifts, Gearboxes etc.

Handled shifts, Effective initialization and utilization of Manpower.

Played a key role in:

o Arranging of spares.

o Coordinating and carrying out scheduled maintenance (TBM) and condition based maintenance (CBM) activities.

o Managing, Coordination of TPM activities.

Gained practical experience in OHSAS, ISO&TS environment, fire and safety and Environment management system (EMS).

Effective initialization and utilization of Manpower.

Highlight:

Played a stellar role in implementing procedures like maintenance cost reduction, achieving zero breakdowns,

maintenance time reduction(MTTR) and reduction of time between failure (MTBF) wherein attained a reward for the same

as a part of continual improvement program.

1 May’06 to 30 Aug’08 with CII Gaurdian International Ltd., Cochin (SEZ)

Mechanical Engineer (Utility &Maintenance Department)

Key Result Areas:

Facility management, Operation and maintenance, carrying out Maintenance operation as per policies & procedures.

Played a key role in:

o Arranging of spares.

o Coordinating and carrying out scheduled maintenance (TBM) and condition based maintenance (CBM) activities.

Gained practical experience in OHSAS, ISO&TS environment, fire and safety and Environment management system (EMS).

Coordinating and carrying out scheduled maintenance (TBM) and condition based maintenance (CBM) activities.

TRAININGS

Successfully attended various trainings on:

o TPM, Occupational Health & Safety (OHSAS )in 2008 and 2009 and TQM in the year 2011.

o ISO,EMS,5S, Kaizen and Lean Manufacturing techniques in 2007.

KNOWLEDGE PURVIEW

Professional Software like AutoCAD, MS Project, Carrier HAP heat load calculation, MS Office.

Well versed with Electrical, Plumbing (drainage, water supply and fire fighting), HVAC and Civil Drawings.

ASHRAE, SMACNA, SASO (Saudi Arabian standards), IPC, NFPA, NEC codes.

HVAC Cooling Load Calculation (by manual calculation and HAP software), Duct designing using ductilator.

Electrical Load calculation and selection of wires and cables, MCCB and Circuit breakers, Lighting and power systems.

civil works like sub and super civil structure, dry and wet Gypsum ceilings and partitions, Flooring, False ceiling ,Interior

decorations, aluminum and structural steel fabrication.

Page 4: Arun das latest resume

Communication and networking system, BAS (Building automation system), BMS (Building Management Systems).

ACADEMIC DETAILS

2006 BE in Mechanical Engineering from Mailam Engineering College, Mailam, (Anna University, Chennai) with 78%.

Pursuing MBA (Part Time) in Operations and Management from ISBM, Cochin.

IT SKILLS

Platforms: DOS, Windows, Linux.

Tools: MS office, MS project AutoCAD, SAP, ERP, Oracle 11 I, Microsoft outlook and LAN Environment.

PERSONAL DETAILS

Date of Birth: 10th March, 1985

Contact Address: C/O K.Devadasan, Arunodayam (H), Kappil Mekku, Krishnapuram P.O., Kayamkulam, Alleppey Dist.

Kerala,PIN Code - 690533

Languages Known: English, Hindi, Malayalam, Tamil and Arabic

Passport Number : F 9495223

Driving License Holding : valid Indian and Saudi Arabian

I do hereby confirm that the information furnished is true to the best of my knowledge and belief.

ARUN DAS.D

REFER TO ANNEXURE FOR PROJECTS EXECUTED

ANNEXURE

PROJECTS EXECUTED

At Dani Ellia Building Solutions, Riyadh, Kingdom of Saudi Arabia

Title: King Fahad Medical City

Role: MEP Project Engineer

Responsibilities:

Handled all the post/pre-installation works required for the installation of GE and SEIMENS Made MRI Scan Machines.

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Ensure that all installations are as per hospital standards and MRI machine requirements.

Liaised with client, GE, SEIMENS and consultant (RAD Planning - USA) for the work quality

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Coordinate with hospital to ensure the hospital standards in various streams.

Handled installation of:

o Installation, testing and commissioning of Systems like medical gas, drainage and water supply system, Fire

fighting system, chilled water systems with necessary piping for MRI magnets, plumbing, AHU, DX type chiller,

pre-insulated duct system, exhaust and fresh air fans.

Page 5: Arun das latest resume

o Fire fighting sprinkler system, FM 200 system, Air sampling system.

o Complete electrification works like cabling, cable termination, lighting and power, earthing and lightning

protection

o Low power systems like data, telephone, public address system(PAS),Master clock system, Intercom system.

Handled testing and commissioning of all MEP systems.

Carried out safety assurance and audits in coordination with SEIMENS, GE and Hospital.

Ensured effective preparation of:

o BOQ ,BOM, bills.

o supplier enquiry, Receive supplier quotations and negotiation.

o RFI, RFA and Project handover reports.

o Snag list and Correction.

Title: Prince Sultan Military Medical City

Role: MEP Project Engineer

Responsibilities:

Liaised with client, GE, and consultant (RMAE Planning ) for the work quality.

Handled all the post/pre-installation works required for the installation of GE MRI & CT Scan Machines.

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Carried out safety assurance and audits in coordination with GE and Hospital.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Handled all the pre-installation works required for the installation of GE Made MRI Scan Machines, CT SCAN machines

and ultrasound machines to ensure that all installations are as per hospital standards and MRI machine requirements.

Handled installation of:

o Installation, testing and commissioning of Systems like medical gas, drainage and water supply system, Fire

fighting system, chilled water systems with necessary piping for MRI magnets, plumbing, AHU, Roof top

packaged units, pre-insulated and sheet metal duct system, exhaust and fresh air fans.

o Fire-fighting sprinkler system, fm200 system, Air sampling system.

o Complete electrification like cabling, cable termination, lighting and power, earthing and lightning protection.

o Low power systems like data,telephone,public address system(PAS),centralized clock system, intercom system.

o Systems like BMS,AIR SAMPLING DETECTION SYSTEM, HONEYWELL FIRE ALARM SYSTEMS.

Ensured effective preparation of:

o BOQ, BOM, bills.

o supplier enquiry, Receive supplier quotations and negotiation.

o RFI, RFA and Project handover reports.

Title: Inter Continental Hotel in Riyadh:

Role: MEP Project Engineer

Responsibilities:

Supervising day-to-day site operations.

Preparation, execution & monitoring, testing and commissioning of all MEP systems like HVAC ,Plumbing (drainage ,

water supply, chiller piping, irrigation & Firefighting), FM 200 ,BMS, Complete Electrical & Low Current systems

as per compliance with the plan, shop drawing, specification, standards and schedule.

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Shop drawing and As built preparation in Auto cad ,its submittal and obtaining client/consultant approval.

Sub contractor, vendor, Contractor bills and Manpower management.

Detailed Quantity Calculations for BOQ/Tender, BOM, Invoicing, Estimation, Budgeting, Costing, Measurements of work,

Extra Items with Rate Analysis & Deviation Etc..

Review and Check shop Drawings, Technical Bid Analysis, and Specifications, Prepare and Monitor Engineering

Documents.

Assisting in the formulation, strict implementation, monitoring and reporting of safety Rules & standards in the project

sites.

Sub contractor, vendor, Contractor bills and Manpower management.

Material Procurement, Sub Contracts management, Sub contracts agreement, Price negotiations.

During installation resolve the conflicts between different systems and make as built drawing with

the approval of the consultant before the installation to avoid any discrepancies.

Handling of material and drawing submission (RFA).

Raising of inspection request (RFI) and coordinate with client/consultant for site inspection.

Page 6: Arun das latest resume

Title: Marriot Courtyard Hotel - Olaya, Riyadh, Saudi Arabia

Role: MEP Project Engineer

Responsibilities:

Handled installation, testing and commissioning of all MEP systems like chilled water system, air cooled system, AHU,

HVAC ducts, fad, various types of exhaust, smoke and fresh air fans, complete fire fighting systems and plumbing

including drainage and domestic water supply systems.

Complete electrification like cabling, cable termination, lighting and power, earthing and lightning protection.

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Handled Installation, Testing and Commissioning of complete electrical systems like Lighting Systems, Panel Boards,

Smoke Detectors, Fire Alarm System, CCTV, Pas, Intercom System and BMS System.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Ensured effective preparation of:

o BOQ, bills, and supplier enquiry and negotiation.

o RFI, RFA and Project handover reports

Liaised with consultants and clients.

Title: MSD office at Wassel Tower - Riyadh, Saudi Arabia

Role: MEP Project Engineer

Responsibilities:

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Handled the installation, testing and commissioning of chilled water systemand necessary pipings, AHU, HVAC Ducts,

FAD, Exhaust Fans, fire fighting systems and other utilities.

Complete electrification like cabling, cable termination, lighting and power, earthing and lightning protection.

Liaised with consultants (Global Office Solutions-Riyadh).

Handled complete electrification works, smoke detectors, fire alarms.

Carried out supplier enquiry and negotiation.

Title: Saudi Aramco - Dammam, Saudi Arabia

Role: MEP Project Engineer

Responsibilities:

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Efficiently designed, installed, tested and commissioned exhaust system including ducts and fans for TMEIC inverters.

Ensured effective preparation of BOQ, bills, quotations.

Carried out supplier enquiry and negotiation, Safety assurance and audits.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Managed preparation and submission of O&M manuals.

Preparation of RFI, RFA and Project handover reports.

Testing and commissioning of all MEP systems.

Ensured effective preparation of:

o BOQ, bills, and supplier enquiry and negotiation.

o RFI, RFA and Project handover reports.

Title: Saudi Investment Bank (SIB) Office – Riyadh, Saudi Arabia

Role: MEP Project Engineer

Responsibilities:

Managed erection and commissioning of MEP works like HVAC system, firefighting system, exhaust and FAD’S and

Plumbing including Drainage and domestic water supply systems other utilities.

Complete electrification like cabling, cable termination, lighting and power, earthing and lightning protection.

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Preparation of BOQ, bills.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Supplier enquiry and negotiation. SAFETY assurance and audits.

Preparation and submission of O&M manuals and preparation of RFI, RFA and Project handover reports

Page 7: Arun das latest resume

Testing and commissioning of all MEP systems.

Ensured effective preparation of:

o BOQ, bills, and supplier enquiry and negotiation.

o RFI, RFA and Project handover reports.

Title: AL-Batal Design Factory - Furniture Factory in Riyadh:

Role: MEP Project Engineer

Responsibilities:

Project Reporting , Site Co-ordination, Client Meeting-Presentation and Team Supervision.

Supervising day-to-day site operations.

Carried out project management of complete electrical, plumbing and HVAC works.

Handled erection and commissioning of:

o Industrial coolers, chillers, chiller piping and package units with ducts, exhaust fans and cooling towers, handled

testing and balancing of all HVAC systems.

o Complete fire fighting systems.

o Complete drainage system and domestic water supply system.

o Complete electrification like cabling, cable termination, lighting and power, earthing and lightning protection.

Managed complete electrification of factory including installation, testing and commissioning of lighting systems, panel

boards, busbar, data and telephone system, CCTV, public address system, fire alarms and smoke etectors, earthing and

lightning protection systems.

Handled installation, testing and commissioning of compressors and diesel generator set.

Ensuring timeliness in schedule and maintaining a punch list of to-do and accomplished work.

Ensured effective preparation of BOQ, bills, and supplier enquiry and negotiation RFI, RFA and Project handover reports.